Professional Documents
Culture Documents
Lab 03
Lab 03
Resources
As a project manager your primary task is to lead and manage resources to predefine goal and objective. To be able
to assign resources to tasks in Microsoft project you need to define the resources first. You do this in the Resource
Sheet and you will notice that you have three different types of resources to choose from; Work, Material and Cost.
1. Work
You should use this type when you would like to define a human resource or equipment that’s consuming time when
working on a task. For an example this could be used when you have a carpenter remodeling your house, etc.
2. Material
This type is used for recourses that are consumed over time, like petrol, nails, water or wood.
3. Cost
If you need to rent a house for a specific activity you should use this type or resource. You are able to connect a
specific cost to an activity.
Microsoft Project will provide accurate information about the cost of each task and the project as a whole.
You are able to filter out which tasks that are performed by which resource.
You are able to identify over and under-utilized resources and in that way gain a higher efficiency in the
project.
Pr # 03 Creating Resources & Assigning Tasks
1. Open the Gantt Chart-view by clicking View -> Gantt Chart or by clicking the Gantt Chart on the View Bar.
2. Select the task that you would like to assign resources to and click the assign resource-button under tools menu
or press Alt+F10.
3. Select the resource that you would like to assign to the task and enter the percentage that you would like to
assign the resource to the task. 100% is fulltime assigned to the task.
4. Repeat step 2 and 3 if you would like to assign more resources to the task.(If you forgot to add the appropriate
resource(s) in the Resource sheet you can just add the name of the resource in the first available row.)
Resource Graph
You are also able to see the planned workload for the different resources by clicking the Graphs button. You will then
see the following dialog-box.
Individual Working Hours
Microsoft Project 2007 uses, by default, the Standard Base Calendar when you create a new project but it can
sometimes be handy to set specific calendars for individual resources. If Resource 1 is for example unavailable every
Tuesday after lunch and it is much easier and secure to define this information in MS Project 2007 than to calculate this
manually.
You do this by:
2. Choose the date that you would like to set to No Working Time. In
this case 6th of April 2007. Enter the name of the Non Working
Day in the table below and choose start and end-date. Click on
Details.
Non Working Days in MS Project
1. Indicators. You are not able to enter information in this field but you will see icons here that for example indicate that you have over allocated the resource or if you
have entered a note about the resource.
2. Resource Name. The name of the resource. In the example above Its entered Resource 1, Resource 2 etc.
3. Type. Choose the type of resource as mentioned above; Work, Material or Cost.
4. Material Label. If you have entered a Material-resource you can specify a Unit for the material. You can for example enter Kilometers or Miles if you have a Fuel as a
Material resource.
5. Initials. Microsoft Project automatically chooses the first letter in the name of the resource but you are free modify in any way you would like to. It can although be
wise to make sure that you have individual and specific initials for you resources when the initials will be displayed in any view that displays the Initials.
6. Group. A resource can be often belong to a line-organization and you can for example choose to enter the home-organization or Company name if the resource is a
consultant.
7. Max. Units. Here you enter the maximum amount of work the resource is able to perform in terms of percentage. 100% = One Unit or a Full Time Resource. 50 % = half
a Unit or a Half Time Resource.
8. Std. Rate. This is the standard rate for the Resource. In my case Carpenter John charges me $80/hour.
10. Cost/Use. Some resources will require a one time cost which you enter here. You might for example want to rent some king of hardware which cost $20 to rent and
$10/hour. Microsoft Project will calculate the total cost for renting this hardware to $20+($10*number of hours).
11. Accrue At. This field specifies how and when Microsoft project will calculate and charge the cost of a resource to a task. You are able to choose between Start, End and
Prorated. If you choose Start will Microsoft Project calculate the cost as soon as the task begins. End will make Microsoft project to calculated the cost when the task is
completed. Prorated will make Microsoft Project to accrue the cost of task when the task is completed.
12. Base calendar. Defines which calendar to use for the resource. Is useful to specify different calendars for example if you have resources in different countries that have
different holidays.
13. Code. In this field you can enter more or less what you would like to, for example a cost center code or some other information that is valid to filter on.
Resource Allocation View
Which view of the 28 views are best you use? That is
up to you to decide. You need to find the Views that
suits your way of working as a Project Manager.