Professional Documents
Culture Documents
PROJECT PLANNING
TECHNIQUES – TIME
MANAGEMENT
Introduction
A Project is a planned undertaking which is a set of
interrelated and coordinated activities designed to
achieve certain specific objective, within a given
budget and period of time.
Need to:
Clearly define the objectives
Basic Facts about Construction Planning
Breakdown of equipment;
Unwillingness to cooperate;
Inadequate detailing
Delayed payment;
Fin.&Eval.
Organization
Risk
Estimating
Planning
Outline - Organisation
costs
Provide a mechanism for performance
33
Road WBS in Tabular Form
34
1.0 Concept
2.0 Preliminary Design
2.1 Feasibility Study
2.2 Alignment
2.3 Geometric Design
3.0 Detailed Design
3.1 Drainage
3.2 Structures
3.3 Pavement
3.4 Engineers Estimate
3.5 Tender Documents
4.0 etc
HOUSING PROJECT
Sub-Project Level
Block A Block B Block C Block D
Task Level
High Primary Nurse
Offices
School School ry
Filtered Road/
Sewarage Gas Supply Electrical Service
water Pavement
System System System Building
supply s
RESIDENTIAL
BUILDING
Tasks
Precast Super- Finishes
Foundation Tasks
structure Tasks Tasks
Work packages
First Second Third
Parapet
Floor Floor Floor
Electrical
Carpentry Painting,
+ Roof
Staircase and Joinery Flooring Fitting &
Mechanica Treatment
Works Fixtures
l works
Ser Features Sub-Project Task Work Package Activity Opera-
No. tions
‘1. Level Level 1 Level 2 Level 3 Level 4 Level 5
designation
‘2. Work – Project to Sub-project to Tasks to Work Work Packages to Activities
Breakdown Sub-project tasks, project to Packages Activities to
Hierachy tasks (directly) operations
‘3. Management Project Team Task- Work centres Work Centres Site
Responsibility responsibility Foreman
unit
‘4. Planning Corporate Project – Project Master Project Detailed
Level Plan summary plan, plan, constructed plan, Contracted
Design works mile stone Works control
Preparation Plan, plan, project plan, Short term
contract budget work programmes,
finalisation plan Resources
Mobilisation plan
Project
Main building
1st floor
Structures
Plumbings
Electrical
HVAC
2nd floor
Service building
Structures
Plumbings
Electrical
Procedure Approach
Project
Feasibility
Design
Basic
Detail
Bid documents
Shop drawings
Bid
Construction
Foundations subcontract
Main building
Piles
Concrete foundations
Service building
Piles
Concrete foundations
Steel erection
Finishings
Commissioning
Standard Formats?
TASK:
ARE THERE STANDARD GUIDELINES
FOR PREPARING WBS?
Outline
Further Reading:
Search NASA + WBS
Overview of Construction
Planning Techniques
(Lecture No. 6 Continued)
Scope
Gantt Charts
S- Curves;
Line of Balance Chart;
Time Chainage Charts
Critical Path Method (CPM);
Precedence Diagramming Method (PDM);
Programme Review and Evaluation Technique
(PERT)
Other advanced methods
Gantt Chart
A Gantt chart is a type of bar chart, adapted by
Karol Adamiecki in 1896 and independently by
Henry Gantt in the 1910s, that illustrates a project
schedule. Gantt charts illustrate the start and
finish dates of the terminal elements and summary
elements of a project.
Gantt charts provide a standard format for
displaying project schedule information by listing
project activities and their corresponding start and
finish dates in a calendar format
Simple Gantt (Bar) Chart)
Gantt Charts (Bar Charts) from MS Project *
56
58
Sample Tracking Gantt Chart
59
Note that PMBoK 2008 is no longer advocating the use of this tool!
Simple Example of Determining the Critical
Path
73
Consider the following project network diagram based on
(activity on the arrow). Assume all times are in days.
78
Sample Precedence Diagramming Method (PDM) Network
Diagram for Project X
79
A D H
Mon 8/3/98 Mon 8/3/98 Tue 8/4/98 Fri 8/7/98 Wed 8/12/98 Wed 8/19/98
5 5 days
J
Wed 8/5/98 Tue 8/11/98
START B
10 3 days
6 4 days
C G I
Mon 8/3/98 Wed 8/5/98 Thu 8/6/98 Thu 8/13/98 Fri 8/14/98 Mon 8/17/98
PERT
81
THANK YOU