Professional Documents
Culture Documents
• Interpretation
• Separate Source of Income
• Gross Income Place Your Picture Here
• Estimated Gross Profit
• Estimated Loss
• Adjusted Income
• Date of Commencement
• Date of Completion
• Deductibility of expenses incurred in respect
of warranty or defects liability
• Actual Gross Profit or Loss
PR NO.2/2009
CONSTRUCTION CONTRACTS
1. Introduction
2. Interpretation
3. Date of commencement of business
4. Recognition of income prior to completion of contract
5. Separate source of income
6. Estimated loss from uncompleted contracts Place Your Picture Here
7. Revision of estimates and tax computation
8. Completion of contract
9. Individual contractors
10. Outgoings and expenses of construction contractors
11. Other issues related to construction contractors
12. Information required for audit
Construction
Contract Commencement
Commencement of business
Involve the performance of
The following circumstances may be
construction services and are
indicative of the commencement of a
contracts specifically
construction contract business:
negotiated for the construction
i. The date on which the contract is
of an asset or combination of
secured
assets that are closely
ii. The date on which a letter of
interrelated in terms of their
award is offered
design, technology and function
iii. The date on which possession of
or their ultimate purpose or use
a construction site is obtained,
and include main & ancillary
whether in writing or otherwise; or
contracts including but not
iv. The commencement of an activity
limited to mechanical
which constitutes part of a series
engineering, electrical
of activities that are actively
engineering, public utilities
carried out in the course of a
projects, project design &
construction contract business, for
consultancy, architectural
example levelling of land.
designing and infrastructural
v. Any other date which DGIR
contracts.
consider appropriate
Building Construction
Residential: Houses / condominiums
Non residential: Schools, shop lots, community halls, college, university
Infrastructure
Highways, roads, railways, public amenities
Types of
Construction
Industrial
Industrial wiring & installation
Others
Intercompany services & maintenance contract
SEPARATE SOURCE OF INCOME
Each contract shall be treated as a
separate and distinct source of income.
Answer:
4 different contracts.
SEPARATE SOURCE OF INCOME
Question 2:
Company F, signed a contract individually with 10 owners of vacant bungalow lots located near
to one another. The owners got together and negotiated with the contractor for a package deal to
construct their houses.
Separate construction Single construction
contract contract
Answer:
If the contractor views the individual contracts to be so closely interrelated with the effect of being
a single contract and with an overall profit margin, and that the construction can be performed
concurrently or in a continuous sequence, then all the 10 contracts should be combined and
accounted for as a single construction contract, notwithstanding the fact that different contracts
have been signed with different owners.
RECOGNITION OF INCOME
- If the projects covered more than one YA/ accounting period
- Consistent & fair method until completion
% of Completion Method
Completion Method
vs or
% of Completion Method
Date of Completion
Contract of project is deemed completed upon:
i. The date on which the Certificate of Practical Completion (CPC) is issued;
ii. Where no such certificate is issued, the date upon which the contract work is
substantially completed, whichever is earlier
INCOME RECOGNITION
COMPLETED
INCOMPLETE
CONTRACT
CONTRACT
(CPC / 95%)
INCOMPLETE CONTRACT
Tax treatment for estimated profit
Example 1:
Company A, a construction contractor closes its accounts on 31 December every year. In March 2006, Company A was awarded a RM8 million contract to
construct an office building. Construction commenced on 01.07.2006 and is expected to be completed by 31.12.2008. The estimated profit for the whole
contract is RM1.2million. For tax purpose, the company has used the progress billings method to compute its estimated profit for years of assessment 2006,
2007 and 2008.
Payments received and receivable (PB) are as follows: The estimated profit for each year of assessment is computed as follows:
Year Payment Received & Receivable (RM’000) Year Estimated Profit (RM’000)
Estimated loss < The difference is the gross income from the
Estimated profit
Estimated construction contract business
loss
Contract RM Status
1 50,000 Completed
2 20,000 In progress
3 (25,000) In progress
Aggregate estimated profit = estimated loss > estimated gain. Loss disregarded
Actual profit = 50,000
Answer: RM50,000
INCOMPLETE CONTRACT
Question 4:
J Construction Sdn Bhd has 5 contracts with the following profit/losses for the year ended 31.12.2007
Contract RM Status
1 200,000 In progress
2 (100,000) In progress
3 (50,000) In progress
4 300,000 In progress
5 50,000 Completed
Answer: RM400,000
COMPLETED CONTRACT
RM’000 RM’000
Total 2,600
The final gross profit for years of assessment 2005 to 2008 will be ascertained as follows:
RM’000 RM’000
Total 2,000
CONSTRUCTION
COST
CONSTRUCTION COST
Soild
investigation
fees
Design &
technical Land survey
fees fees
DIRECT
EXPENSES
*** **
Scaffolding Main
cost Contractor/
Subcontractor
Site
overhead
Material cost expenses
** 3rd Party Confirmation
*** replacement? 2
COST AFTER PROJECT COMPLETED
AFTER
COMPLETION COST
- Usually within 24 months after completion - Payment to client for late delivery/completion of contract.
- Defect liability incurred allowed as deduction - a sum calculated at a rate as stated in the contract
based on the following circumstances and choice agreement.
made by contractor - Claim under P&L or if single contract, to reopen prior year
assessment
defects liability shall be allowed as a i. deduction against the aggregate Election to allow as a deduction against
deduction against the gross income gross income from the other contracts the gross income from the same contract
for that basis period or any following for the basis period preceding the basis
from the contract for the basis period
period in which the expenses are
or the following basis periods basis periods.
incurred. Any expenses which cannot be
fully deducted shall be allowed as a
ii. If still not sufficient, against other deduction for the next preceding
income of the contractor period and so on for the duration of the
contract.
CONSTRUCTION COST
Contractor need to distinguish between direct expenses which are part of the construction expenditure and expenses which
Direct Expenses are the day-to-day expenditure of the construction contractor business and debited to the Profit and Loss Account
All direct expenses which are related to the construction contract such as land survey fees, soil investigation fee, site overhead
Construction Cost expenses, design and technical fees, cost of construction materials etc. are costs attributable to the contract and should be
capitalized in the Construction Expenditure Account.
Fees paid for The deductibility of such expenses would depend on the purpose, nature and circumstances
soliciting contracts such fees arise.
For income tax purposes, the amount of the progress billings, including retention money, which becomes
Retention sum receivable has to be included in the gross income of the contractor at the date such progress billings are
issued.
LIQUIDATED The liability is incurred as and when the actual amount of liquidated damages is ascertained and agreed
ASCERTAINED DAMAGES by the contractor and his clients.
WARRANTY Defects liability expenses incurred by a construction contractor are allowed as deduction based on
circumstances & choice made by contractor
SHARING
EXPERIENC
ES
SEMAKAN AUDIT- PENDAPATAN
KONTRAK
LAMPIRAN 1
No Project Name Date of Date of End of Contract sum T'over T'over T'over T'over T'over
Comm YA Completion YA DLP (Letter Awards) recog before Recog Recog Recog Recog After
CPC date 2015 YE 2015 YE 2016 YE 2017 YE 2018
P1 P2 P3 P4 TOTAL
PROJECT
Completed Uncompleted Uncompleted Completed
INCOME STATEMENT
Total contract revenue recognised (A x D) f1 0 0 0
Contract revenue recognised in prior year f2 0 0
Income recognised for the period/year (f1- f2) F 0 0 0
BALANCE SHEET
Contract cost incurred todate (b1) CTD CTD 0
Attributable profit / (loss) todate (H) 0 0 0
Contract revenue recognised todate 0
Progress billings todate (E) 0 0 0
Due from customers 0 0 0
Due to customers 0 0 0
Net due from / (to) customers
KONTRAK TELAH SIAP (TARIKH CPC / 95% SIAP)
KAEDAH PENGIKTIRAFAN PENDAPATAN
KENALPASTI JUMLAH
KONTRAK/CONTRACT
SUM KENALPASTI
(Rujuk Statement of Final KEUNTUNGAN SEBENAR
Account) / Letter of Award (Rujuk Akaun Penamat/Final
Account)
KONTRAK
TELAH SIAP
KENALPASTI KOS
SEBENAR
(Rujuk kos terperinci)
CONTOH FORMAT AKAUN PENAMAT & PELARASAN AUDIT
Akaun Penamat