PROPOSED CONSTRUCTION OF

FOUR (4) STOREY - SIXTEEN


(16) CLASSROOMS SCHOOL
BUILDING
I.S.N.H.S.
January 14,2024
Overview
- Current Phase: The phase the project is currently in Construction.

- PROGRESS PERCENTAGE : 11.41 %


KEY MILESTONES
COMPLETED MILESTONES
COLUMN FOOTING

LEGEND:
Remaining Balance for Combined Footing: 6 sets
- FOR PREPARATION

- CONCRETED
FOOTING TIE BEAM

LEGEND:

- FOR PREPARATION

- CONCRETED
KEY MILESTONES
UPCOMING MILESTONES
COLUMN FOOTING

JAN. 15 JAN. 17 JAN. 19

JAN. 16 JAN. 18 JAN. 20

LEGEND:
Remaining Balance for Combined Footing: 6 sets
- FOR PREPARATION

- CONCRETED
FOOTING TIE BEAM

JAN. 16 JAN. 18 JAN. 20 JAN. 22


SITE PICTURES
LOT 17
END