PROPOSED CONSTRUCTION OF

FOUR (4) STOREY - SIXTEEN


(16) CLASSROOMS SCHOOL
BUILDING
I.S.N.H.S.
January 14,2024
Overview
- Current Phase: The phase the project is currently in Construction.

- PROGRESS PERCENTAGE : 23.67%


KEY MILESTONES
COMPLETED MILESTONES
Slab on Fill

LEGEND:

- FOR PREPARATION

- CONCRETED
2nd FLOOR BEAM

LEGEND:

- PENDING

- COMPLETED
KEY MILESTONES
UPCOMING MILESTONES
2nd FLOOR BEAM

January 31,2024 January 24,2024 January 17,2024


2nd FLOOR SLAB

FEBRUARY 1,2024
SITE PICTURES
END