PROJECT: SM MOA EXPANSION PROJECT – PHASE 6

SUBJECT: MAIN MALL CEILING WORKS

DATE: JANUARY 24, 2024

BID MEETING REPORT


1. SITE PICTURES – Ceiling Works
High Ceiling – Atrium Ceiling (25 mts high)
2. Application of Automotive Paint Finish on Skylight Structural Steel

3. Ceiling Works for Typical Toilets, Elevator Lobbies, Escalator Lobbies and U-Stairs.
Ceiling framing should be in compliance to SM EDD Standards
4. As built of Existing Ceiling Layout and Elevation for Termination Details
5. Scaffolding Cost should be incorporated/included in the unit cost for ceilings works

BID SCHEDULE

Bid Meeting - January 24, 2023

Bid Queries – January 24 to January 26, 2023

Bid Form Issuance – January 25, 2023

Response to Queries – January 26 to January 28, 2023

Bid Submission – January 28 to January 30, 2023

Bid Opening – January 31, 2023

Evaluation and Award – January 31 to February 15, 2023

Notice of Award – February 16, 2023


Mobilization Permit and Clearance Safety Orientation – February 17 to February 28, 2023

Project to Start – March 1, 2023