Professional Documents
Culture Documents
Steps .
Step 2: model the actual duration of the selected delay event and
impact the as-planned program .
1. establish that the baseline schedule has been achievable. When that is
not true then the calculated delay may not be right, since some or all of
the calculated delay is inevitable.
2. ensure that the program is appropriate for dynamic simulation. This means
that it will involve the calculation of the schedule by simulation using
computers and software. If the schedule is not capable of dynamic
simulation, the contractor must make adjustments to the logic of the
schedule and, in particular, replace the constraints applied in order for the
activities to react appropriately during the analysis.
3. determine the nature, extent, and relationship of the delay event to be
established so that it can be properly linked to the schedule.
How to Perform the Impacted As Planned
Delay Analysis in (Primavera P6)
Following is the As Planned Schedule (Baseline Schedule)
• We will insert the Delay event into our schedule. Enter the Original Duration of
the delay, then Assign the right successor (which activity the delay will affect).
For example, the Original Duration of the “Design Changes” delay is 10 days.
And it will affect the “Activity D”. and add a Constraint for the event date and
here the delay event date is 18 July 2020
Then, you can calculate the total Extension of Time which will be 39– 30= 9 days.