Professional Documents
Culture Documents
Reducing of Line
Stoppages in CGL-2
CGL 1 1
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
TEAM MEMBERS
CGL 1 2
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
DEFINE
CGL 1 3
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
CGL 1 4
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
CGL 1 5
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
EFFECTS OF DELAY
Line stoppages.
Diversion of Material.
Sheet breakage.
Time loss in setting line again.
Production loss .
CGL 1 6
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
Methodology
1) Data Collection. (July-06)
2) Analyzed the Process & Data. (Aug-06)
3) Verification. (15th Sep-06)
4) Implements of Action. (March-07)
5) Hand over of project.
CGL 1 7
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
MEASURE
CGL 1 8
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
CGL2 DELAY FOR 2006-2007
0.7 70
No. of Stoppages
Power Failure is not Included 0.59
0.6 60
in this Graph % DELAY
0.5 50
0.4 40
0.3 30
0.2 0.17 22 20
13
0.1 10 10
0 0
Apr-06 May-06 Jun-06
MONTH
CGL 1 9
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
M o t o r/ D riv e 28 3 42 12 102 5 4 1 95 2 7 2
P LC 28 5 0 0 0 0 0 0 0 0 0 0
F urna c e 0 0 0 0 0 0 15 1 422 3 0 0
Ele c t
F ie ld D e v ic e 0 0 356 7 100 7 23 3 0 0 4 1
W e ld e r 15 1 0 0 0 0 20 1 3 1 0 0
Ot he rs 3 1 26 3 52 1 140 1 0 0 131 1
R EA S ON F OR Oct No v Dec J an Feb M ar
D EP T
D ELA Y S
R ES P ON S IB LE Time (min) Delay Time (min) Delay Time (min) Delay Time (min) Delay Time (min) Delay Time (min) Delay
M o t o r/ D riv e 0 0 11 2 36 6 9 2 40 3 19 3
P LC 0 0 0 0 536 3 0 0 0 0 0 0
F urna c e 0 0 65 2 30 1 110 1 0 0 0 0
Ele c t
F ie ld D e v ic e 0 0 0 0 0 0 0 0 0 0 0 0
W e ld e r 0 0 4 1 64 1 109 1 22 1 0 0
Ot he rs 0 0 15 1 195 3 0 0 66 1 0 0
CGL 1 1
0
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
DELAY (Min)
FREQUENCY
400
Welder 237 7 8.04
50
TOTAL 2947 94 100
300 41
237 40
200 30
18
20
100
12
8 8
10
7
0 0
Furnace Others PLC Field Device Motor/Drive Welder
EQUIPMENT
CGL 1 1
1
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
ANALYSIS
CGL 1 1
2
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
Line Stoppages
Mechanical
Breakdown
Utility
Raw Material
Breakdown
Schedule Problem
Shutdown
CGL 1 1
3
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
Fishbone Analysis
Electrical Breakdown
PLC
Furnace
Field Devices
Electrical
Stoppages
Motor /Drives
Welder
CGL 1 1
4
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
Fishbone Analysis
Operation Breakdown
Steering Units New Product development
Welding machine
Made logic in PLC for Hearth Roll oscillation mode selection during Line Stop. so that if
operator forget to put in oscillation mode it will go Automatically. This will avoid roll bending
Problem.
Additional Valve provided for N2 Quenching during line stop in Zone-3.This additional
quenching avoid the strip breakage in line stop.
Made logic in PLC for automatic Seal Roll DN after line starting & its F/B given in HMI. This
will avoid the Adherence or Furnace pressure problem.
Provided delay time for valve Activation F/B in PLC. This will avoided spurious tripping of
furnace.
CGL 1 1
7
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
Damper Flow S/W FB taken in PLC & HMI & Also taken in furnace tripping interlock . It
will
avoid the damper failure in case of water flow fail in damper.
CGL 1 1
8
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
Implemented Action Plans & Action against the root causes & its Advantages:
1) FURNACE SECTION.
B) Counter Measures Implemented Action Plan:-
Done furnace PID tuning & changeover it to STC mode & Auto Control.
Furnace Entry seal blower temp. FB given in HMI to monitor seal temp.
Made logic for damper Open with N2 Quenching as well as with line stop. to avoid the damper failure
due to high temp. & pressurized flue gases.
Water Level of emergency tank F/B given in HMI. With minimum limit Alarm this will alert to
operator & avoid the water cool damper & JCF heat exchanger.
CGL 1 1
9
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
A) Counter Measures:-
Line HMI Communication Failure because of TCP/IP Cable loosed at PLC.
L-2 Automation to be Implemented with L-1 for line set points.
SBS Supply to be provided for UPS system.
CGL 1 2
0
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
CGL 1 2
1
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
CGL 1 2
2
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
CGL 1 2
3
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
ROOT CAUSE & COUNTER MEASURES (ACTION PLANS): For Maintenance
4) DRIVES SECTION.
A) Root causes:-
All Furnace hearth roll & Seal Roll Drive Communication failure during Multidrives ACB off for
Maintenance.
Exit Pinch roll-5 & 6 Motor jog with starter was the cause of loop formation in exit section.
Aux. Drives MCCB Tripping Problem was due to load current setting was not proper.
Drives tripping At Cho fault still pending. Solution Awaited from M/S ABB.
CGL 1 2
4
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
ROOT CAUSE & COUNTER MEASURES (ACTION PLANS): For Maintenance
4) DRIVES SECTION.
A) Counter Measures:-
APC Blower & Air Knife drive emergency s/w to be provided at the equipment.
Entry Looper counter weight to be increase for proper tension compensation.
Exit looper position Absolute value Encoder to Be fixed & calibrated.
Fan Cooled AC Drives SFU to taken with Fan Switch on interlock.
CGL 1 2
5
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
CGL 1 2
6
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
ROOT CAUSE & COUNTER MEASURES (ACTION PLANS): For Maintenance
5) Field Devices.
A) Counter Measures:-
Air Knife Exit side Pressure was getting drooped at Air Knife.
Pneumatic Clamp to be installed in the line Entry Process & Exit Area.
Steering -3 mounting Design was not proper As per EMG. It to be mounted vertically as
per new design.
CGL 1 2
7
CONTINUOUS
ROOT GALVANIZING
CAUSE & COUNTER LINE-2
MEASURES QC PROJECT
(ACTION PLANS): For Maintenance
6) OTHERS.
A) Root causes:-
UPS Supply tripped due to spike buster got faulty. Which was the cause of line stop.
Air Knife Tilting problem due to its power cable was underrating.
Chromic Dryer Controller was getting hanged which was the cause of line stop.
Air Knife overlap was cause of screw failure because there was no Safety limit .
Steering unit tripping was cause of line stoppages.
Stagger winding was not proper because of its camera mounting frame vibrating.
CGL 1 2
9
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
ROOT CAUSE & COUNTER MEASURES (ACTION PLANS): For Maintenance
6) OTHERS.
B) Counter Measures Implemented Action Plan:-
New Load cell installed at APC & done its calibration. Taken this load cell FB for Pot tension control
in close loop.
Leveller Curvature & nest Position transducer installed & given its FB in HMI. This for ref. for the
operator for proper elongation.
Made logic for belt wrapper for Automation to minimize its time for coil feeding.
Zn Pot Inductor current , Voltage & power FB taken in HMI History, Also taken all its fault taken in
PLC & generate is Alarm & Hooter for any abnormality to operator.
New weld hole sensor installed at Bridle-4 for weld tracking for L2 Automation.
EMG Staggering Winding Camera Installed at separate column to avoid the line structure vibration
& Provide the hood above its camera to avoid external light source interference.
New CCTV camera installed at welder ,Steering -3, APC unit for the operator. This also a helpful to
avoid the line delay in case of problem in welder, steering units.
CGL 1 3
0
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
Weld hole sensor in entry & exit section to be installed for complete weld tracking.
Drives tripping At Cho fault still pending. Solution Awaited from M/S ABB.
CGL 1 3
1
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
IMPROVE
CGL 1 3
2
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
CGL2 DELAY FOR 2006-2007
No. of Stoppages
Sep-06 0.33 4 1.5 60
Oct-06 0.00 0 % DELAY Due to Drive
1.16 50
Nov-06 0.22 6 CH0 Fault
0.95
Dec-06 1.93 14 1 40
Jan-07 0.51 4
0.59 0.62 30
Feb-07 0.32 5 0.51
Mar-07 0.04 3 0.5 22 20
0.33 0.32
0.1710 13 0.22 14
8 10
4 0.00
5 6 4 5 0.043
Power Failure is not Included 0 0 0
in this Graph Apr-06 May- Jun-06 Jul-06 Aug- Sep-06 Oct-06 Nov-06 Dec-06 Jan-07 Feb-07 Mar-07
06 06
MONTH
CGL 1 3
3
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
CGL 1 3
4
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
CONTROL
CGL 1 3
5
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
CGL 1 3
6
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
DELAY ANALYSIS
CGL 1 3
7
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
3) Fixed Cost
CGL 1 3
8
CONTINUOUS GALVANIZING LINE-2 QC PROJECT
THANKS
CGL 1 3
9