Professional Documents
Culture Documents
and
Financial Controls
Everglades University
Learning Objectives
• Explain the reasons for implementing cost
controls.
• Review the methods for developing a cost
control system.
• Analyze the cost control process.
• Convert the estimate into cost control items.
4-2
The Importance of Cost Control
• What is Cost Control?
– Cost control is a systematic analysis of actual
construction costs, including units of measure,
compared with the estimated cost and units,
and the use of that analysis to proactively
manage the actual costs and units to stay
within or near the budget.
4-3
The Contractor’s Accounting System
Figure 4.1
4-4
Generating Cost Data
• Labor Hours
– Labor is coded to specific activities.
– Cost codes may be organized using MasterFormat
2004 numbers, or developed from a Work
Breakdown Structure.
• Example:
– A labor cost will come from time cards. Cards will
be coded to specific cost items.
– 03 30 02 is cast-in-place concrete.
4-5
Daily Time Sheet for Cast-in-Place Concrete
Work
Date Name Classification 03 30 02-02 03 30 02-03
7/15 Anderson, F.A. Laborer -2 8
Brown, W.R. Laborer -2 8
Carter, I.L. Laborer -2 8
Smith, N.R. Laborer -2 8
Wilson, D.E. Laborer -2 4 4
Hill, J.S. Carpenter 8
Garcia, J.E. Carpenter 8
Smith, H.H. Carpenter 8
7/15 Totals 36 L2 4 L2, 24 C
Figure 4.2
4-6
Reporting Process
for Labor Hours
Figure 4.5
4-7
Reporting Process for Material Purchases
Figure 4.5
4-8
Reporting Process for
Company-Owned Equipment
Figure 4.6
4-9
Analysis of Cost Data
• Information required to examine current
progress.
• The costs to date.
• The production to date.
• The quantity (units) of work completed.
• A comparison of the estimated cost and units
with the current cost and units.
4-10
Analysis of Cost Data
• Case study: Tim and Tom at Lost Lake
• Bid of $8,320 for installing drywall (taping is a
separate line item)
• 10,667 SF
• 160 labor hours at $52/hr
• 2 installers (Tim and Tom) for 2 weeks
Worksheet 4-1
4-11
Analysis of Cost Data
(Continued)
• Tim and Tom want to take a day off and go
fishing. To accomplish this they must:
– Complete all work in nine days or less instead of
ten.
– Cover their wages for the last day $832 + $250 in
estimated expenses.
– Use the cost data from Week 1 to forecast their
final costs and determine whether they can go
fishing.
4-12
Tim and Tom’s
Week 1 Cost Analysis
Monday Tuesday Wednesday Thursday Friday Total
1-June 2-June 3-June 4-June 5-June
Hours 16 16 16 16 16 80
4-13
Information from Cost Data
• Their average production cost for Week 1 was
$0.70/SF—better than the $0.78/SF
estimated.
• They achieved $0.66/SF cost per unit on three
days.
• The costs were $472 below what was included
in the estimate for this week.
4-14
Typical Analysis Information
from Cost Data
• Quantity of work remaining
• Current percentage of work completed
• Current cost variance
• Forecasted unit cost
• Projected cost of remaining work
• Projected variance
• Percent variance
4-15
Analysis of Tim and Tom’s Cost Data Week 1
(Continued)
• Projected cost remaining
– Quantity remaining x Forecasted unit cost
– 4,727 x $0.70 = $3,308.90
• Projected variance
– Estimated cost – (Current cost + Projected cost
remaining)
– $8,320 – ($4,160 + $3,308.90) = $851.10
• Percent variance
– Projected variance/Estimated cost
– $851.10/$8,320 = 10.2%
4-16
Should Tim and Tom Go Fishing?
• Forecasted time to complete the work:
– 4,727/4 days = 1,182 SF necessary per day. They can
accomplish this.
• Forecasted cost:
– Projected savings of $851.10, which covers their
wages. They will have to finish early to pay for fishing.
– 2½ hours early on Thursday = $260.00
• Decision:
– Go for it!
4-17
Tim and Tom’s
Week 2 Cost Analysis
Monday Tuesday Wednesday Thursday Total for Week Total
8-June 9-June 10-June 11-June
Hours 16 16 16 11 59 139
4-18
Analysis of Cost Data
Labor Material Total
4-19
Converting Estimate Items
to Cost Control Items
• Cost control items need to be easily identifiable
and unique.
• The work activity must be unique for reporting
and historical cost data.
• A cost control item shouldn’t be too small (in
cost, quantity, or time).
• A cost control item should align with the firm’s
historical cost control database whenever
possible.
4-20
Converting Estimate Items
to Cost Control, Gatehouses
Item Unit Labor Per Labor Quantity Unit Price Material Total Cost
hours Hour Cost Cost
Footings 5.4 12 $30.36 $364.32 132 SFCA $0.40 $375.47 $739.79
4-21
Converting Project Estimate Items
to Cost Control, Bridge 1
Item Unit Man- Per Hour Labor Quantity Unit Material Total Cost
hours Cost Price Cost
Abutment 40 crew $150.34/ $6,013.60 2107 SFCA .50 $1,053.50 $7,067.
Forms hours crew hour
Abutment 5.3 Ton $4,240.00 5.3 Ton $600 $3,180.00 $7,420.
Rebar
Pour 136 CY 8 crew $169.02/ $1,352.16 136 CY $60 $8,160.00 $9,513.
Abutment hours crew hour
Total $24,000.
4-22
Review
• Cost control is a systematic comparison of actual
costs and units with estimated costs and units,
the use of that comparison to manage the costs
and units, keeping them on or near the budget.
• Timely cost and unit comparison enables the
contractor to proactively identify and solve
problems.
• Cost and unit data comes from several sources.
4-23
Review
(Continued)
4-24
Apply What You Have Learned
Examine your project’s cost control system and
reporting.
• Do you receive daily cost and production reports?
• Does your cost control system give you the
opportunity to make decisions about managing
the costs and units during the progress of an
activity?
• How does your firm establish cost control items?
4-25
Cost Management Plan
• Step 1: Establish a budget.
• Step 2: Identify cost activities and cost control
numbers.
• Step 3: Assign responsibility for daily coding and
reporting cost data.
• Step 4: Determine a method of organizing material
purchases for the cost control system.
5-3
Cost Management Plan
(Continued)
5-4
Identifying Cost Activities
and Cost Control Numbers
• Description of the activity, from start to finish.
• Quantity of the activity.
• Crew for the activity.
• Hours necessary to complete the activity:
– Composite crew cost per hour
– Average hourly cost per hour
– Cost of each craft per hour
5-5
The Responsibility for Daily Coding and
Reporting Cost Data
5-6
Method for Organizing
Material Purchases
• Identify:
– The specific materials used in the work activity.
– The material costs for the work activity.
– The vendor and purchase order.
– The order and delivery dates.
5-7
Sample Bill of Materials
Figure 5.1
5-8
Crew Assignment Information
• Cost code number.
• Description of activity.
• Quantity of work involved.
• Crew composition.
• Time allowed for the activity.
• Cost of labor for the activity.
• Material required for the activity.
5-9
Crew Assignment Information
(Continued)
5-10
Bill of Materials for Grade Beam
Bill of Materials
Cost Code: 03 03 02 11
Item Quantity Unit Price Total
BB Form-Ply 10,800 MSF $929 $10,033.00
2x4 21.222 MBF $407 $8,637.35
Ties 27 C $75 $2,025.00
Rebar 8.72 Tons $540 $4,708.80
Concrete 220 CY $56.45 $12,419.00
5-11
Bill of Materials for Bridge 1
Bill of Materials
Cost Code: 03 03 02 11
Item Quantity Unit Price Total
3/4” Form-Ply 2.11 MSF $929 $1,960.19
4x4 12.4 MBF $858 $10,639.20
Ties 1,050 Ea $4.62 $4,851.00
Rebar 5.3 Tons $540 $2,862.00
Concrete 136 CY $60.93 $8,286.48
5-12
Crew Assignment for Grade Beam Work
STP Construction Co.
Work Assignment • Sure Fresh Project • STP Project 01-10
Cost Code: 03 03 02 11
Project Area: Building A Grade Beam
Work Description: Form grade beam at Building A Drawing of Details and Work Area:
Document Reference: Foundation plan, sheet 3; Sections, sheet 6
Quantity of Work: 10.800 SFCA formwork
Crew and Rates: 3 carpenters at $52.00 + 1 laborer at $48.00/Hour
Crew Rate: $204/Hour $1,632/Day
Daily Production: 50 LF/day
Time Allowed: 18 days
Labor Cost: $29,376.00
Material: 10,800 MSF B-B OES; 21.22 MBF 2x4 studs/walers;
2,700 snap ties; 5,400 wedges
Material Location: To be delivered to Building A
Equipment/Equipment Cost: Forklift at $100/day
Tools: 4 skill saws; cut-off saw; 2 drills; form oil sprayer
5-13
Crew Assignment for Bridge 1
STP Construction Co.
Work Assignment • Project • STP Project 01-10
Cost Code: 03 03 02 11
Project Area: Bridge 1
Work Description: Form abutment, Bridge 1 Drawing of Details and Work Area:
Document Reference: Sheet 8
Quantity of Work: 4,220 SFCA formwork
Crew and Rates: 3 carpenters at $52.00 + 1 laborer at $48.00 +
1 equipment operator at $56.00
Crew Rate: $260/Hour $2,080/Day
Daily Production: 422 SFCA/day
Time Allowed: 10 days
Labor Cost: 20,800.00
Material: 2.11 MSF 3/4” B-B OES; 12.4 MBF 4x4; 1,050 rods/catheads
(rental) at each abutment
Material Location: To be delivered close to each abutment
Equipment/Equipment Cost: 30-ton crane
Tools: 4 skill saws; cut-off saw; 2 drills; form oil sprayer
5-14
Day-by-Day Projection of Budgeted Costs
29-Nov 30-Nov 1-Dec 2-Dec 3-Dec 6-Dec 7-Dec 8-Dec 9-Dec 10-Dec
Budgeted
Daily Labor $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544
Cost
Accumulated
Labor Cost
$1,544 $3,088 $4,632 $6,176 $7,720 $9,264 $10,808 $12,352 $13,896 $15,440
Estimated
Daily Quantity
200 200 200 200 200 200 200 200 200 200
Estimated
Accumulated 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000
Quantity
Budgeted
Cost/LF Today
$7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72
Budgeted
Cost/LF $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72
Accumulated
Figure 5.3
5-15
4-Day Comparison of Actual Costs with Budgeted Costs
29-Nov 30-Nov 1-Dec 2-Dec 3-Dec 6-Dec 7-Dec 8-Dec 9-Dec 10-Dec
Budgeted Daily
Labor Cost $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544
Actual Daily
Labor Cost $1,544 $1,544 $1,544 $2,448
Budgeted
Accumulated $1,544 $3,088 $4,632 $6,176 $7,720 $9,264 $10,808 $12,352 $13,896 $15,440
Labor Cost
Actual
Accumulated $1,544 $3,088 $4,632 $7,080
Labor Cost
Estimated Daily
Quantity 200 200 200 200 200 200 200 200 200 200
Actual Daily
Quantity 160 200 155 230
Estimated
Accumulated 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000
Quantity
Actual
Accumulated 160 360 515 745
Quantity
Budgeted
Cost/LF Today $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72
Actual Cost/LF
Today $9.65 $7.72 $9.96 $10.64
Budgeted
Cost/LF
Accumulated $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72
Actual Cost/
LF
Accumulated $9.65 $8.58 $8.99 $9.50
Figure 5.4
5-16
4-Day Comparison of Labor Cost Variances
Quantity to
Complete 1,840 1,640 1,485 1,255
Projected Cost at
Accumulated Rate $19,300.00 $17,160.00 $17,980.00 $10,000
Variance from
Budget $(3,860.00) $(1,720.00) $(2,540.00) $(3,560.00)
Figure 5.5
5-17
Comparison of Actual Costs with
Budgeted Costs, Lowered Productivity
Figure 5.6
5-18
Method for Obtaining
Supervisor Feedback
• A superintendent will need to know why a problem
happened to solve it.
• Supervisors need encouragement to supply
information.
• You need to have a system that will offer reliable
information.
• If not verbal, then develop a written report for
supervisors.
5-19
Determining the Impact
of Subcontractor Actions
• Your planning should include:
– Dates subcontractors must be on the project.
– List of subcontractor activities.
– Creating awareness among supervisors regarding
subcontractor involvement.
– A reporting method for problems.
– A predetermined channel of communication.
5-20
Review
5-21
Review
(Continued)
5-22
Apply What You Have Learned
5-23
Implementing Cost Control
• Obtain cost data.
– Organize to compare with estimate.
– Report labor hours and cost.
– Report material cost and quantities.
– Report equipment hours and cost.
– Report subcontractor activity and progress.
– Use feedback to resolve problems.
6-3
Implementing Cost Control
(Continued)
6-4
Cost Control Summary
Figure 6.1
6-5
Accounting for the “Learning Curve”
6-6
Review Questions for Supervisors
• Were the instructions/layout adequate?
• Were the details adequate?
• Was there amount of work as expected?
• Were the shop drawings accurate/adequate?
• Was there enough material?
• Was the material in good condition?
• Was the material in a convenient location?
6-7
Review Questions for Supervisors
(Continued)
6-8
Review Questions for Supervisors
(Continued)
6-9
Management Responsibilities
6-10
Compensation from Owner
• Must have agreement.
• Areas where it might occur:
– Errors and omissions in construction documents.
– Discovery of unknown or latent conditions.
– Direction to complete additional work.
– Requirement to complete additional work to
accommodate a specified product.
6-11
A Role Play in Problem Analysis
6-12
Cost Control for
Change Orders
6-13
Change Order Estimate for Electrical Work
in Project Gatehouses
Figure 6.12
6-14
Organizing Change Order Cost
Information
• Prepare the change order information for the
Project:
– Describe the work.
– Prepare a cost breakdown for the change.
– Prepare a crew assignment isolating the two kinds
of work for cost control.
Worksheet 6-2
6-15
Dock Seals Work Assignment
STP Construction Co.
Work Assignment • Project
SCC Project 01-10 Date: ___________________________
Cost Code: 11 16 01, 11 16 03 Project Area: Building A
Work Description 11 16 01: (Change Order 2): Install dock seals at the 5 overhead doors, Building A. 11 16 03: Install
dock bumpers at the 5 overhead doors, Building A. Note: Separate cost for dock seal from door bumper.
Dock seals are Change Order 2.
Document Reference Sheets 3, 5, and 6. Section 11 16 00, loading dock equipment. Shop drawings and submittals from Ted’s
Loading Dock Supply Company.
Quantity of Work 11 16 01: 5 Dock Seals
11 16 03: 5 Dock Bumpers
Crew and Rates 1 Carpenter @ $52.00/hour
1 Laborer @ $48.00/hour
Crew Rate $100.00/Hour $800/Day
Daily Production 1 dock seal; or dock bumper and a portion of the dock seal
Time Allowed 11 16 01: Dock Seal: 8 hours
11 16 03: Dock Bumper: 2 hours
Labor Cost (11 16 01) Dock Seal: $800.00 x 5 = $4,000.00
(11 16 03) Dock Bumper: $200.00 x 5 = $1,000.00
Material Door Seals, Dock Bumpers (Ted’s Loading Dock Supply)
Miscellaneous screws and anchor bolts
Material Location In Building A
Equipment/ Rolling Scaffold, No charge
Equipment Cost
Tools Drill # 106, Rolling Dolly
Form 6.1
6-16
Dock Seals Change Order
Worksheet 6-2
6-17
Subcontractor Back Charges
• You might want to back charge subcontractors
for:
– Work in their contract that was accomplished by your
crew or by use of your equipment.
– Work in their contract that was accomplished by
another subcontractor.
– The cost of causing delays for other crews (this might
be difficult).
– Rework charges.
6-18
Subcontractor Back Charges
(Continued)
• Practices to observe:
– Be sure the contractor-subcontractor agreement has a
clause allowing back charges.
– Get agreement from the subcontractor’s supervisor on
charges.
– Keep track of exact charges.
– Present a detailed record of the back charge.
6-19
Review
• Cost data need to be organized to indicate trends in cost
variance.
• It is important to discover why the variance is occurring,
regardless of whether the variance is over or under.
• Management can be responsible for some of the
problems.
It is important to recognize the cause and take action
immediately.
• Understand the scope of work, your work and the change
order process.
6-20
Apply What You Have Learned
• Examine the challenges and cost overruns on your job:
– Is there a pattern to the causes?
• Look carefully at your scope of work and potential change
orders.
– Is there a comparison made between estimated and actual costs?
– Was there work performed outside of your scope of work?
– Were change orders requested for this additional work?
• What will you do differently on the next project?
– Where did you make money on this project?
– Where did you lose money on this project?
– Why did you make money on this job?
6-21