Professional Documents
Culture Documents
4, 2004)
• Techniques for:
– Detailed Unit Cost Estimating
– Production Rate Estimating
– Assembly Cost Estimating
– Conceptual Cost Estimating
– Design Cost
– Computer-based Estimating
• Estimating Formats and Organization
• Steps and Components of Estimates
• Indirect Costs
5%
10 min.
3 weeks
1 hour
1 day
Qu
st
an
Ac y /
Co
tit
tiv Pro
it
y* =
ity du
Un
tit st
an Co
Du cti
ra vit
tio y
n = Rat
Qu
COST TIME
e
Labor or Equip Cost =
Activity Duration * Cost/Unit of Time
Adapted from Oberlender (1993)
/ 085 21
162 sfca
x x0
37
0. .0
5 mh ch /
sfc /
a
sfc
a
/ fca a
/
da
1
s
.2
y OR
OR
$2
sfc
$358 0.432 days
$357 x $826.80
$356 x $25.84 13.77 mh
$351 x $103.35 3.40 ch
Detailed Design
Example:
Calculate the construction cost for all elements in the
grade beam
Solution: Explicit?
Prod. Unit
CSI Number Description Takeoff Unit Qty Cost
Rate Cost
Forms in place, grade
03110 435 0010 2 x 2'-4" x 25' = 117 sf sfca 530 117 $4.02 $470.34
beam, plywood, 1 use
ties: #4, 18" oc:
(25'/1.5' + 1) = 18 ties
>> 18 x 8' = 144 lf
>> 144 lf x 0.668 lb/lf = 96 lb
Reinforcing in place, longitudinal #5:
03210 600 3250 ton 2.10 0.12 $1,010 $122.21
Footings, #4-#7 4 x 25' = 100 lf
>> 100 lf x 1.043 lb/lf = 104 lf
dowels #4, 18" oc:
18 x 3.5' = 63 lf
>> 63 lf x 0.668 lb/lf = 42 lb
Concrete, Ready mix,
03310 220 0200 (25' x 2' x 2'-4") / 27 = 4.31 cy cy n/a 4.31 $64.50 $278.00
3500 psi
Placing Concrete, Grade
03310 700 3250 (25' x 2' x 2'-4") / 27 = 4.31 cy cy 180 4.31 $12.57 $54.18
Beams, Pumped
Qu
t
os
a
Ac y /
nt
C
From Triangle:
tiv Pro
it
it
y* =
Un
tit st
ity du
an Co
Unit Cost Method:
Du cti
rat vit
(1) Cost = quantity * unit cost
ion y R
Qu
= ate
Production Rate Method: COST Labor or Equip Cost = TIME
Activity Duration * Cost/Unit of Time
(2) Duration = quantity / production rate
(3) Cost = duration * wage
(4) Unit cost = wage / production rate
Example:
Clough & Sears & Sears, Place Concrete Abutment, pages 38-39.
Alternatively,
(4) Unit cost = wage / production rate = ($242/hr) / (8.75 cy/hr) =
$27.66/cy
(1) Cost = quantity * unit cost = (280 cy) * ($27.66/cy) = $7,744
Example:
Calculate the construction cost for a spread footing
Solution:
Reference Pg. 2 of RS Means Assemblies Cost Data
ISSUES:
Assume some of the
detailed quantities,
e.g., 150 kg of
rebar per m3 of
concrete
Transitions or
interfaces may not
be handled very
well
Estimating Formats
Unit
Uniformat # Description Qty Unit Cost
Cost
1. Foundations
1.1-140 Spead Footings
1.1-120 7150 Load 50K, soil capacity 3 ksf, 4'-6" sq. x 12" deep 6 ea $216.50 $1,299
.
3. Superstructure
3.1-130 Steel Columns
3.1-130 5800 Load 200k, Unsupported height = 10' 60 vlf $42.95 $2,577
.
Building components defined, 12 Sitework
e.g., spread footings, column TOTAL
UNIFORMAT
CSI Number Description Qty Unit Mat'l Labor Equip Cost
1. Foundations
.
3. Concrete
03110 Structural CIP Forms
03110 430 5000 Forms in place, footings, 1 use 192 sfca $1.69 $2.80 $862.08
03210 Reinforcing Steel
03210 600 3250 Reinforcing in place, Footings, #4-#7 0.20 ton $530 $480 $202.00
Building Component Detailed, 03310 Structural Concrete
e.g., spread footing w/ 03310 220 0200 Concrete, Ready mix, 3500 psi 7.1 cy $64.50 $457.95
03310 700 2450 Placing Concrete, footings, Pumped 7.1 cy $23.50 $11.25 $246.73
3,000 psi concrete… .
5. Metals
MASTERFORMAT 05120 Structural Steel
05120 260 7000 W10X45 60 lf $38.50 $1.67 $0.99 $2,469.60
.
16 Electrical
TOTAL
Organization of Estimating Information
• Uniformat • Masterformat
1. Foundations 1. General Requirements
2. Substructure 2. Sitework
3. Superstructure 3. Concrete
4. Exterior Closure 4. Masonry
5. Roofing 5. Metals
6. Interior Construction 6. Wood & Plastic
7. Conveying 7. Thermal & Moisture Protection
8. Mechanical 8. Doors & Windows
9. Electrical 9. Finishes
10. General Conditions 10. Specialties
11. Special Construction 11. Equipment
12. Sitework 12. Furnishings
13. Special Construction
14. Conveying Systems
15. Mechanical
16. Electrical
Scope = Cost
Building type defined
•Index Number
e.g. 45,000 sf •Cost-capacity factor (cost/fx)
Feasibility college facility •Overall Parameter (unit area,
index number)
Example:
Calculate the construction cost in 2000 of a building in
San Francisco, CA that was built in 1978 for $3.2 Million.
Index 2000 Cost 2000 Index S.F., CA in 1978 = 62.6
Index 1978 Cost 1978 Index S.F., CA in 2000 = 146.7
‘Economies of Scale’
Total
Item Item Cost Factor
Installed Cost
Example:
Calculate the current construction cost of a 45,000 sf college
facility.
Example:
Calculate the estimated construction cost of a 45,000 sf
college facility.
Solution:
Reference Pg. 107 of RS Means Square Foot Costs for College,
Laboratory
Estimating Steps
• Review plans, drawings, specifications
• Gather pricing information (such as productivity rates,
unit prices, subcontractor bids)
• Quantity takeoff
• Determine construction method
• Break down project, establish line items, level of detail
• Calculate material, labor, equipment costs
• Add Markup (overhead and profit)
• Add Bonds, interest, etc.
• Calculate cost per line item
• Aggregate and sum line items
• Group line items according to contract or bid format
Components of a cost estimate