PROJECT LOCATION
No. of
Designation No. of hours Hourly rate Amount (PHP)
Person
Project Engineer 1 3 ₱ 100.00 ₱ 300.00
Skilled Laborer 1 3 ₱ 50.00 ₱ 150.00
Manpower
Subtotal ₱ 675.00
No. of
Name & Capacity No. of hours Hourly rate Amount (PHP)
Units
Machineries
Subtotal ₱ 67.50
Description UOM Quantity Unit Cost Amount (PHP)
Coco Lumber bd.ft 120 ₱ 18.00 ₱ 2,160.00
Plywood Marine, 1/4" thk. sheets 3 ₱ 450.00 ₱ 1,350.00
Materials
No. of
Designation No. of hours Hourly rate Amount (PHP)
Person
Safety Practicioner 1 106.24 ₱ 87.50 ₱ 9,296.00
Safety Officer 1 106.24 ₱ 62.50 ₱ 6,640.00
Manpower
Subtotal ₱ 29,216.00
No. of
Name & Capacity No. of hours Hourly rate Amount (PHP)
Units
Machineries
Subtotal ₱ -
Description UOM Quantity Unit Cost Amount (PHP)
Hard Hat ea 25 ₱ 150.00 ₱ 3,750.00
Safety Shoes pairs 25 ₱ 850.00 ₱ 21,250.00
Materials
No. of
Designation No. of hours Hourly rate Amount (PHP)
Person
Safety Practicioner 1 106.24 ₱ 87.50 ₱ 9,296.00
Safety Officer 1 106.24 ₱ 62.50 ₱ 6,640.00
Manpower
Subtotal ₱ 53,120.00
No. of
Name & Capacity No. of hours Hourly rate Amount (PHP)
Units
2-way radio (2 years life span) 10 106.24 ₱ 2.00 ₱ 2,124.80
Machineries
Subtotal ₱ 3,718.40
Description UOM Quantity Unit Cost Amount (PHP)
Speed Restrictions ea 4 ₱ 320.00 ₱ 1,280.00
Road work Ahead ea 4 ₱ 320.00 ₱ 1,280.00
End Roadwork ea 4 ₱ 320.00 ₱ 1,280.00
Speed Restrictions ea 4 ₱ 320.00 ₱ 1,280.00
Workmen Ahead ea 4 ₱ 320.00 ₱ 1,280.00
Prepare to Stop ea 2 ₱ 320.00 ₱ 640.00
Materials
t
os
C
Value Added Tax (VAT) - 5% ₱ 4,705.96
ct
re
Total Cost ₱ 15,655.98
di
In
.
PROJECT TITLE
PROJECT LOCATION
No. of
Designation No. of hours Hourly rate Amount (PHP)
Person
Project Engineer 1 0 ₱ 100.00 ₱ -
Construction Foreman 1 8 ₱ 62.50 ₱ 500.00
Manpower
Subtotal ₱ 2,300.00
No. of
Name & Capacity No. of hours Hourly rate Amount (PHP)
Units
Low Bed Trailer 1 8 ₱ 2,200.00 ₱ 17,600.00
Bulldozer 0 8 ₱ 3,200.00 ₱ -
Machineries
₱ -
₱ -
Price Fluctuation 3% ₱ -
Subtotal ₱ -
Total Cost ₱ 181,500.00
t
os
C
ct
.
PROJECT TITLE
PROJECT LOCATION
No. of
Designation No. of hours Hourly rate Amount (PHP)
Person
Project Engineer 1 16 ₱ 100.00 ₱ 1,600.00
Construction Foreman 1 16 ₱ 75.00 ₱ 1,200.00
Manpower
Subtotal ₱ 4,800.00
No. of
Name & Capacity No. of hours Hourly rate Amount (PHP)
Machineries
Units
Bulldozer 0 16 ₱ 3,200.00 ₱ -
Backhoe 1 16 ₱ 2,800.00 ₱ 44,800.00
Transit Concrete Mixer 0 16 ₱ 1,200.00 ₱ -
Subtotal ₱ 44,800.00
Description UOM Quantity Unit Cost Amount (PHP)
Payment for trees ea 80 ₱ 400.00 ₱ 32,000.00
as per Agriculture ₱ -
Materials
₱ -
₱ -
.
PROJECT TITLE
PROJECT LOCATION
No. of
Designation No. of hours Hourly rate Amount (PHP)
Person
Project Engineer 1 0.5 ₱ 100.00 ₱ 50.00
Construction Foreman 1 0.5 ₱ 62.50 ₱ 31.25
Manpower
Subtotal ₱ 81.25
No. of
Name & Capacity No. of hours Hourly rate Amount (PHP)
Units
Low Bed Trailer - - ₱ 2,200.00 ₱ -
Bulldozer - - ₱ 3,200.00 ₱ -
Machineries
Payloader - - ₱ 2,500.00 ₱ -
Backhoe 1.00 0.50 ₱ 2,800.00 ₱ 1,400.00
Road Grader - - ₱ 2,200.00 ₱ -
Vibratory Roller - - ₱ 1,800.00 ₱ -
Water truck - - ₱ 1,500.00 ₱ -
Transit Concrete Mixer - - ₱ 1,200.00 ₱ -
Dumptruck 1.00 0.50 ₱ 1,200.00 ₱ 600.00
Subtotal ₱ 2,000.00
Description UOM Quantity Unit Cost Amount (PHP)
Common Soil Embankment cu.m 10 ₱ 20.00 ₱ 200.00
Base coarse cu.m 3 ₱ 360.00 ₱ 1,080.00
Materials
.
PROJECT TITLE
PROJECT LOCATION
No. of
Designation No. of hours Hourly rate Amount (PHP)
Person
Project Engineer 1 1 ₱ 100.00 ₱ 100.00
Construction Foreman 1 1 ₱ 62.50 ₱ 62.50
Manpower
Subtotal ₱ 237.50
No. of
Name & Capacity No. of hours Hourly rate Amount (PHP)
Units
Low Bed Trailer - - ₱ 2,200.00 ₱ -
Bulldozer - - ₱ 3,200.00 ₱ -
Machineries
Payloader - - ₱ 2,500.00 ₱ -
Backhoe 2.00 1.00 ₱ 2,800.00 ₱ 5,600.00
Road Grader - - ₱ 2,200.00 ₱ -
Vibratory Roller - - ₱ 1,800.00 ₱ -
Water truck - - ₱ 1,500.00 ₱ -
Transit Concrete Mixer - - ₱ 1,200.00 ₱ -
Dumptruck 3.00 1.00 ₱ 1,200.00 ₱ 3,600.00
Subtotal ₱ 9,200.00
Description UOM Quantity Unit Cost Amount (PHP)
₱ -
₱ -
Materials
Price Fluctuation 3% ₱ -
Subtotal ₱ -
Total Cost ₱ 9,437.50
t
os
C
ct
.
PROJECT TITLE
PROJECT LOCATION
No. of
Designation No. of hours Hourly rate Amount (PHP)
Person
Project Engineer 1 1 ₱ 100.00 ₱ 100.00
Construction Foreman 1 1 ₱ 62.50 ₱ 62.50
Manpower
Subtotal ₱ 237.50
No. of
Name & Capacity No. of hours Hourly rate Amount (PHP)
Units
Low Bed Trailer - - ₱ 2,200.00 ₱ -
Bulldozer - - ₱ 3,200.00 ₱ -
Machineries
Payloader - - ₱ 2,500.00 ₱ -
Backhoe 1.00 1.00 ₱ 2,800.00 ₱ 2,800.00
Road Grader - - ₱ 2,200.00 ₱ -
Vibratory Roller - - ₱ 1,800.00 ₱ -
Water truck - - ₱ 1,500.00 ₱ -
Transit Concrete Mixer - - ₱ 1,200.00 ₱ -
Dumptruck 1.00 1.00 ₱ 1,200.00 ₱ 1,200.00
Subtotal ₱ 4,000.00
Description UOM Quantity Unit Cost Amount (PHP)
₱ -
₱ -
Materials
Price Fluctuation 3% ₱ -
Subtotal ₱ -
Total Cost ₱ 4,237.50
t
os
C
ct
.
PROJECT TITLE
PROJECT LOCATION
No. of
Designation No. of hours Hourly rate Amount (PHP)
Person
Project Engineer 1 1 ₱ 100.00 ₱ 100.00
Construction Foreman 1 1 ₱ 62.50 ₱ 62.50
Manpower
Subtotal ₱ 237.50
No. of
Name & Capacity No. of hours Hourly rate Amount (PHP)
Units
Low Bed Trailer - - ₱ 2,200.00 ₱ -
Bulldozer - - ₱ 3,200.00 ₱ -
Payloader - - ₱ 2,500.00 ₱ -
Machineries
.
PROJECT TITLE
PROJECT LOCATION
No. of
Designation No. of hours Hourly rate Amount (PHP)
Person
Project Engineer 1 1 ₱ 100.00 ₱ 100.00
Construction Foreman 1 1 ₱ 62.50 ₱ 62.50
Manpower
Subtotal ₱ 237.50
No. of
Name & Capacity No. of hours Hourly rate Amount (PHP)
Units
Low Bed Trailer - - ₱ 2,200.00 ₱ -
Bulldozer - - ₱ 3,200.00 ₱ -
Payloader - - ₱ 2,500.00 ₱ -
Machineries
Price Fluctuation 3% ₱ -
Subtotal ₱ -
Total Cost ₱ 4,837.50
t
os
C
ct
.
PROJECT TITLE
PROJECT LOCATION
No. of
Designation No. of hours Hourly rate Amount (PHP)
Person
Project Engineer 1 1 ₱ 100.00 ₱ 100.00
Survey aid 1 1 ₱ 62.50 ₱ 62.50
Manpower
Subtotal ₱ 300.00
No. of
Name & Capacity No. of hours Hourly rate Amount (PHP)
Units
Low Bed Trailer - - ₱ 2,200.00 ₱ -
Bulldozer - - ₱ 3,200.00 ₱ -
Payloader - - ₱ 2,500.00 ₱ -
Machineries
Price Fluctuation 3% ₱ -
Subtotal ₱ -
Total Cost ₱ 10,700.00
t
os
C
ct
.
PROJECT TITLE
PROJECT LOCATION
No. of
Designation No. of hours Hourly rate Amount (PHP)
Person
Project Engineer 1 1 ₱ 100.00 ₱ 100.00
Survey aid 1 1 ₱ 62.50 ₱ 62.50
Manpower
Subtotal ₱ 300.00
No. of
Name & Capacity No. of hours Hourly rate Amount (PHP)
Units
Low Bed Trailer - - ₱ 2,200.00 ₱ -
Bulldozer - - ₱ 3,200.00 ₱ -
Payloader - - ₱ 2,500.00 ₱ -
Machineries
Price Fluctuation 3% ₱ -
Subtotal ₱ -
Total Cost ₱ 8,050.00
t
os
C
ct
.
PROJECT TITLE
PROJECT LOCATION
No. of
Designation No. of hours Hourly rate Amount (PHP)
Person
Project Engineer 1 1 ₱ 100.00 ₱ 100.00
Survey aid 1 1 ₱ 62.50 ₱ 62.50
Manpower
Subtotal ₱ 300.00
No. of
Name & Capacity No. of hours Hourly rate Amount (PHP)
Units
Low Bed Trailer - - ₱ 2,200.00 ₱ -
Bulldozer - - ₱ 3,200.00 ₱ -
Payloader - - ₱ 2,500.00 ₱ -
Machineries
.
PROJECT TITLE
PROJECT LOCATION
No. of
Designation No. of hours Hourly rate Amount (PHP)
Person
Project Engineer 1 8 ₱ 100.00 ₱ 800.00
Survey aid 1 8 ₱ 62.50 ₱ 500.00
Manpower
Subtotal ₱ 6,120.00
No. of
Name & Capacity No. of hours Hourly rate Amount (PHP)
Units
Low Bed Trailer - - ₱ 2,200.00 ₱ -
Bulldozer - - ₱ 3,200.00 ₱ -
Payloader - - ₱ 2,500.00 ₱ -
Backhoe 1.00 8.00 ₱ 2,800.00 ₱ 22,400.00
Road Grader - - ₱ 2,200.00 ₱ -
Machineries
.
PROJECT TITLE
PROJECT LOCATION
No. of
Designation No. of hours Hourly rate Amount (PHP)
Person
Project Engineer 1 10 ₱ 100.00 ₱ 1,000.00
Survey aid 1 10 ₱ 62.50 ₱ 625.00
Manpower
Subtotal ₱ 7,650.00
No. of
Name & Capacity No. of hours Hourly rate Amount (PHP)
Units
Low Bed Trailer - - ₱ 2,200.00 ₱ -
Bulldozer - - ₱ 3,200.00 ₱ -
Payloader - - ₱ 2,500.00 ₱ -
Backhoe 1.00 10.00 ₱ 2,800.00 ₱ 28,000.00
Road Grader - - ₱ 2,200.00 ₱ -
Machineries