TOPICS
Lead chart
Standard Schedule of Rates
Standard data
Detailed Estimate
Abstract Estimate
Note Accompanying Estimate
Drawings
LEAD CHART
calculated in Km
S.N Description Unit Sourc Lea Basic Conveyanc Deductio Conveyance Conveyanc Total cost
o of materials e d rate e charges n for charges e charges
1Km lead after initial after
lead Deduction
deduction of over
heads and
contractor
profit
13.615%
1 2 3 4 5 6 7 8 9 10 11
(col.6 +
col.10)
Standard Schedule of Rates
?
All construction items are complex one involving more
than one materials and number of activities.
Example – For construction of a brick masonry wall the
rates of bricks, sand, mortar, labour, scaffolding, curing
etc., would determine the rate of brick masonry per
cubic meter
Process of arriving at a rate of such construction items
is called Rate Analysis.
All the departments work out the rates of different
construction items after carrying out rate analysis after
assessing contribution of each item of materials, labour,
plant & equipment, tools, scaffolding, site overheads
etc., to the completed item.
Further in order to serve the above objects, offers /
tenders are invited.
Once the tenders are invited, how do we decide the best
and right offer? How do we compare the offers and rates
submitted by each bidder among themselves?
In order to compare the offers, one therefore needs to have
a basic estimated rate with which the offers can be
compared with.
All Government Departments publish standard rates for all
items collectively.
All the estimates have to be worked out based on those
rates only.
It would thus be very easy to compare offers / quotes from
different contractors.
Schedule of rates will vary from state to state. Every state
has their own Schedule of rates.
All the Government Departments every year prepare and
update rates of normally used building items / Materials /
works item/ labour rates etc.
In Andhra Pradesh, SoR is divided into four parts
1) Water Resources department items
2) Roads and Bridges items
3) Building items
4) Public Health items
The respective departments will submit their proposals to the Board of
Chief Engineers and they will review and finalize the rates.
Standard Data
Basic components for preparing any estimate
1) standard specifications,
2) standard data
3) schedule of rates.
To get the work done as per the required specifications
required quantities of recommended materials,
requirement of specific need based man power,
deployment of specific need based machinery and
duration of its utilization are to be observed and
quantified for each unit of work, and this is called
standard data.
Standard Data gives the details of various inputs in terms
of quantities required for one unit of any work.
When the schedule of rates and hire charges of
machinery are incorporated in the inputs of standard
data it will have direct bearing on the preparation of
project estimates and consequent finalization of tenders.
Classification of Standard
data
The standard data is classified into four parts
considering nature of work, location of work and
magnitude of work.
1) Irrigation and command area development
2) Roads and Bridges
3) Buildings
4) Drinking water supply schemes
Detailed Estimate