Professional Documents
Culture Documents
PRACTICE
(CE-421)
LECTURE NO 1
QUANTITY SURVEYING
Quantity surveying is basically estimating quantities of all
possible items of work required for construction of any building or
structure.
If the estimated cost is greater than the money available, then attempts
are made to reduce the cost by reducing the work or by changing the
specifications.
It is used for framing the tenders for the works and to check contractor’s
work during and after its execution for the purpose of making payments
to the contractor.
Estimate
Cost per square foot of covered area (plinth area) is the most
commonly adopted criterion for preparing rough cost estimate for
most of the residential buildings. (Plinth area estimate)
The quantities for each item may be estimated and shown in the
pattern which is called "Bill of Quantities."
Rates
Rates per unit of various items of work, rates of various materials,
wages of skilled and unskilled labors etc.
DOCUMENTS SUBMITTED WITH DETAILED ESTIMATE
FOR OBTAINING TECHNICAL SANCTION
This is the total floor area minus the Circulation area of verandahs,
passages, corridors, balconies, entrance hall, porches, stair cases etc. and
minus other non-useable areas such as sanitary accomodations
(Bathroom and latrine), kitchen, stores and similar other rooms which
are not used for living purposes.
For office building Carpet area is the lettable area (rentable area) or
useable area and for residential building it is liveable area.
SCHEDULE OF RATES
As the rates vary slightly from year to year, the rates are increased or
decreased by a percentage on the ‘Schedule of Rates’.
If the workable rates differ much from the ‘Schedule of Rates’, then the rates
are revised and a new ‘Schedule of Rates” is prepared.
COST FOR UNFORESEEN ITEMS/CONTINGENCY COST
Direct cost on actual work of a project = Approx. 85% of the whole cost
In KPK Schedule of rates, amount equal to 22% of the estimated cost is allocated for
contractor’s profit and overhead costs.
TOOLS AND PLANTS (T&P)
Normally the contractor has to arrange and use his own tools and
plants.
ADMINISTRATIVE APPROVAL/SANCTION
After the technical sanction of the estimate is given, only then the
work is taken up for construction.
Thanks