You are on page 1of 31

PRODUCTION

PLANNING

Introduction.
Principles and Factors of efficient Production Planning.
Line Balancing (Hai Bun)
Line Balancing Calculation
Production Planning
 The planning for any organization
forms the backbone of production
process.

 Planning of productions helps


organizations to understand the
situation at the Gemba better.

 Effective planning facilitates to book


the entire capacity and also assists in
committing accurate delivery time
frames to the customers.
Production Planning
 At its core, production planning
represents the beating heart of any
manufacturing process.
 Its purpose is to minimise
production time and costs,
efficiently organise the use of
resources and maximise efficiency
in the workplace.
6 Principles of Production
Planning
 Customer Demand
 Before you can plan to assign
resources, you have to know how
much to produce.
 Production planning focuses on the
principle of meeting the targeted
customer demand rate in the most
efficient way possible while keeping
open the capability to respond to
variations in demand.
6 Principles of Production
Planning
 Materials.

 To fulfill your production target, the


materials availability needed should
be ensured.
 The most efficient production
planning keeps the minimum
materials as standard inventory.
 Planners should evaluate how much
material the company needs, the
lead times for orders, the delivery
times for suppliers and the reliability
of the supply.
6 Principles of Production
Planning
 Equipments
 The production planner industrial engineers
takes into account the capabilities of the
equipment used to produce the output. Basic
stability of equipment is comprising. Overall
Equipment Effectiveness (OEE) and TPM

 Manpower
 Manpower planning requires accurately
estimating the number of employees required to
do the work. The capacity of the workforce has
to match the capabilities of the equipment to
plan for the highest efficiency.
6 Principles of Production
Planning
 Processes
 Effective production planning makes sure that the
processes used for the output continue to operate
efficiently and safely.

 Controls
 A final production planning principle puts in place
controls that detect problems as soon as they
occur. Verification of inventory, use of qualified
suppliers and personnel, standardization where
possible.
 When controls are in place, it enables to take
possible corrective actions to minimize the effects
and return production to the required levels.
Line Balancing..
Purpose is to minimize the number
of people and/or machines on an
assembly line that is required to
produce a given number of units

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7–8


Line Balancing Example

EXAMPLE
Green Grass’s plant manager just received marketing’s latest
forecasts of fertilizer spreader sales for the next year. She
wants its production line to be designed to make 2,400
spreaders per week. The plant will operate 40 hours per week.

a. What should be the line’s cycle time or throughput rate per


hour be?
Throughput rate/hr = 2400 / 40 = 60 spreaders/hr
Cycle Time = 1/Throughput rate= 1/60 = 1 minute = 60 seconds

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7–9


Line balancing Example continued:
Assume that in order to produce the new fertilizer spreader on
the assembly line requires doing the following steps in the order
specified:
Work Time Immediate
Description
Element (sec) Predecessor(s)
A Bolt leg frame to hopper 40 None
B Insert impeller shaft 30 A
C Attach axle 50 A
D Attach agitator 40 B
E Attach drive wheel 6 B
F Attach free wheel 25 C
G Mount lower post 15 C
H Attach controls 20 D, E
I Mount nameplate 18 F, G
Total 244

b.What is the total number of stations or machines required?


TM (total machines) = total production time / cycle time = 244/60 = 4.067 or 5

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 10


Draw a Precedence Diagram
SOLUTION
The figure shows the complete diagram. We begin with work
element A, which has no immediate predecessors. Next, we add
elements B and C, for which element A is the only immediate
predecessor. After entering time standards and arrows showing
precedence, we add elements D and E,
and so on. The diagram simplifies
D
interpretation. Work element F, H
for example, can be done B 40
20
anywhere on the line after 30 E
element C is completed. 6
However, element I must A
F
await completion of 40 C
25
elements F and G. 50
I

Precedence Diagram for 18


G
Assembling the Big Broadcaster
15

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 11


Allocating work or activities to
stations or machines
 The goal is to cluster the work elements into
workstations so that
1. The number of workstations required is minimized
2. The precedence and cycle-time requirements are not
violated
 The work content for each station is equal (or
nearly so, but less than) the cycle time for the line
 Trial-and-error can be used but commercial
software packages are also available

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 12


Finding a Solution

 The minimum number of workstations is 5 and the


cycle time is 60 seconds, so Figure 5 represents
an optimal solution to the problem

D
H
B 40
20
30 E
6
A
F
40 C
25
50
I
18
G
15

Firtilizer Precedence Diagram Solution

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 13


Calculating Line Efficiency

c. Now calculate the efficiency measures of a five-station


solution:

t 244
Efficiency = (100) = = 81.3%
nc 5(60)

Balance delay (%) = 100 – Efficiency = 100% - 81.3% = 18.7%

Idle time = nc – t = 5(60) – 244 = 56 seconds

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 14


A Line Process

 The desired output rate is matched to the


staffing or production plan
 Line Cycle Time is the maximum time
allowed for work at each station is
1
c=
r

where
c = cycle time in hours
r = desired output rate

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 15


A Line Process

 The theoretical minimum number of


stations is

t
TM =
c

where
t =total time required to
assemble each unit

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 16


A Line Process

 Idle time, efficiency, and balance delay

Idle time = nc – t

where
n =number of stations

t
Efficiency (%) = nc (100)

Balance delay (%) = 100 – Efficiency

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 17


Solved Problem 2
A company is setting up an assembly line to produce 192 units
per 8-hour shift. The following table identifies the work
elements, times, and immediate predecessors:
Work Element Time (sec) Immediate Predecessor(s)

A None
40

B A
80

C D, E, F
30

D B
25

E B
20

F B
15

G A
120

H G
145
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 18
Solved Problem 2

a. What is the desired cycle time (in seconds)?


b. What is the theoretical minimum number of stations?
c. Use trial and error to work out a solution, and show your
solution on a precedence diagram.
d. What are the efficiency and balance delay of the solution
found?

SOLUTION
a. Substituting in the cycle-time formula, we get

1 8 hours
c= = (3,600 sec/hr) = 150 sec/unit
r 192 units

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 19


Solved Problem 2

b. The sum of the work-element times is 720 seconds, so

t 720 sec/unit
TM = = = 4.8 or 5 stations
c 150 sec/unit-station

which may not be achievable.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 20


Solved Problem 2
c. The precedence diagram is shown in Figure 7.6. Each row in
the following table shows work elements assigned to each
of the five workstations in the proposed solution.
Work Immediate
Element Predecessor(s)
D A None
25 B A
C D, E, F
D B
B E C
E B
80 20 30 F B
G A
F J
A H G
15 115 I H
40 G J C, I
120
H I

145 130

Figure 7.6 – Precedence Diagram

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 21


Solved Problem 2 D
25

B E C
80 20 30
J

A F 115

40 G 15 I
H
120 130
145

Work-Element Cumulative Idle Time


Station Candidate(s) Choice
Time (sec) Time (sec) (c= 150 sec)
S1

S2

S3
S4

S5

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 22


Solved Problem 2 D
25

B E C
80 20 30
J

A F 115

40 G 15 I
H
120 130
145

Work-Element Cumulative Idle Time


Station Candidate(s) Choice
Time (sec) Time (sec) (c= 150 sec)
S1 A A 40 40 110
B B 80 120 30
D, E, F D 25 145 5
S2 E, F, G G 120 120 30
E, F E 20 140 10
S3 F, H H 145 145 5
S4 F, I I 130 130 20
F F 15 145 5
S5 C C 30 30 120
J J 115 145 5

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 23


Solved Problem 2

d. Calculating the efficiency, we get

t 720 sec/unit
Efficiency (%) = nc (100) =
5(150 sec/unit)

= 96%

Thus, the balance delay is only 4 percent (100–96).

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 24


In class - Example
A plant manager needs a design for an assembly line to
assembly a new product that is being introduced. The time
requirements and
immediate Work Element Time (sec)
Immediate
predecessors for the Predecessor
work elements are A 12 ―
as follows: B 60 A
C 36 ―
D 24 ―
E 38 C, D
F 72 B, E
G 14 ―
H 72 ―
I 35 G, H
J 60 I
K 12 F, J
Total = 435

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 25


In class - Example
Draw a precedence diagram, complete I, F, J, and K

Work Time (sec) Immediate


Element Predecessor A
A 12 ―
B 60 A
C 36 ― B
C
D 24 ―
E 38 C, D
F
F 72 B, E
D E K
G 14 ―
H 72 ― J
I 35 G, H
J 60 I
G I
K 12 F, J

43
Total = 5 H

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 26


In class - Example

If the desired output rate is 30 units per hour, what are the cycle
time and theoretical minimum?

1 1
c= = (3600) = 120 sec/unit
r 30

t 435
TM = = = 3.6 or 4 stations
c 120

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 27


In class - Example

Suppose that we are fortunate enough to find a solution with


just four stations. What is the idle time per unit, efficiency, and
the balance delay for this solution?

Idle time = nc – t = 4(120) – 435 = 45 seconds

t 435
Efficiency (%) = nc (100) = (100) = 90.6%
480

Balance delay (%) = 100 – Efficiency = 100 – 90.6 = 9.4%

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 28


In class - Example

Using trial and error, one possible solution is shown below.

Work
Elements Idle Time
Station Assigned Cumulative Time (c = 120)
1
2
3
4
5

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 29


In class - Example

Using trial and error, one possible solution is shown below.

Work
Elements Idle Time
Station Assigned Cumulative Time (c = 120)
1 H, C, A 120 0
2 B, D, G 98 22
3 E, F 110 10
4 I, J, K 107 13
5 A fifth station is not needed

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 30


Managerial Considerations

 Pacing is the movement of product from


one station to the next
 Behavioral factors such as absenteeism,
turnover, and grievances can increase after
installing production lines
 The number of models produced
complicates scheduling and necessitates
good communication
 Cycle times are dependent on the desired
output rate

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 7 – 31

You might also like