Professional Documents
Culture Documents
1
“Contract” is derived from the Latin word
“contractum” which means “a promise or set
of promises which the law will enforce”
4
The terms of contract must be:
Precise
Definite, and
Without any ambiguities
Standard forms of contracts should be adopted
Modifications May be Required as are considered
necessary in respect of individual contracts
The modifications should be carried out only after
obtaining financial and legal advice.
Contract Agreement has Legal status as per Indian
Contract Act
5
For Works Contracts & Stores Contract below
Rs. Ten Lakhs against standard bidding
documents, the Offer of the Bidder and Issue of
Letter of Acceptance will form the Binding
Contract
For Value of Rs.10 Lakh or More, invariably
Contract Document Should be Executed
Contract Document Should be Self Contained
Document Comprising, NIT, ITB, GCC, SCC,
Scope of Work & Specification etc
No Work to Commence Without Execution of an
Agreement
6
Performance Guarantee
Inward Logistics
Advances
LD Clause
Extension With/Without LD
PVC
Taxes & Duties
Force Majeur
Termination & Forfeiture of Performance Guarantee
7
Performance Guarantee by the Successful Bidder is
required for Successful Execution of Work/Supply
Performance Guarantee May be in the Form of
Bank Draft, Fixed Deposits, Bank Guarantee etc
To be given by All Successful bidders irrespective of
its Registration Status
Value Should be 5 to 10% of Contract Value
Should Remain Valid for the Period 60 days beyond
the Completion of the Contractual Obligations
including Warranty
8
Bid Guarantee should be returned on submission of
Performance Guarantee
Bank Guarantee is the Most Common Form of
Performance Guarantee
Contractual Failure & Irrevocable Right of
Purchaser for encashment of BG
The Clauses of the Bank Guarantee have to be
carefully worded to avoid Litigation with Bank
A System has to be in place to keep a Control on the
Expiry of its Validity
9
Supply is FOR Destination of the Consignee –
Rate is Inclusive of freight on Rail or Road
Till Materials are delivered to Consignee,
Insurance Cover is by Supplier
For Supply of Over Dimension Consignment
(ODC) Clearances have to be Arranged by the
Client
In Fabrication Contracts Where Material is To
be Supplied at Site, Client Has to Provide
Road Permits etc
10
In case of Imports, Ocean Freight & Marin
Insurance is by :
By Consignee – FOB or CFR
By Supplier - CIF
Tenders are Invited With both the options of
FOB & CIF/CFR and Decision is taken after
detailed evaluation by the Tender Committee
On Arrival of Consignment at Port, Clearance,
Transportation & Insurance is by Consignee
11
Quality Assurance (QA) is a way of preventing
mistakes or defects in manufactured products
Avoiding problems when delivering solutions or
services to customers
Quality management focuses on Providing
Confidence that Quality Requirements will be
fulfilled
Specifies Standards & Tests in All Components
Contributing to Quality of Manufacture
12
Organizational structure Detailing
Each employee's responsibilities, and
Qualifications an employee needs to fulfill those
responsibilities.
Suppliers, and the materials Supplied correspond
to the requirements for the product.
Has Appropriate Plants & Equipments
Specifies adequate product testing at Different
Stages
Feeds back test results and customer complaints
to solve problems and encourage improvements in
Quality
13
Quality Assurance Plan Is to Specify:
Organizational structure
Technical Details of Process
List of Plant & Equipment
Laboratory Test Facilities the Manufacturer has
Tests Being Performed at each stage of Production to
ensure Quality
Manufacturer’s Test Certificate
Visit of the Quality assurance Facilities by Technical
Team
14
30% Variation Clause in the Tender Document to
Cater to the Variation in Demand During the
currency of the Contract
The Clause is Optional
The Clause Is to be Incorporated In Tender
Document If It is to be Operated Later
Financial Implication of the Clause
Operation of (+) 30% Clause May Change the
Competency of Approval
15
The Clause has to be operated during the
currency of the Contract
Price Remains the same for Supply of Additional
Quantity
Appropriate Extension in Delivery Period may be
required
Price Variation Clause Will be applicable to
Supply of Additional Quantity Also
16
LD(Liquidated Damage) is leviable for Delay in
Supply of Materials at the rate of 0.5 % for delay per
week or part there of, on the value of Delayed Stores
with a maximum of 10% of the Contract Value of
Delayed Supply
LD to be recovered at the time of Payment
‘Severable’ or ‘Whole’ Contract
Waival of LD
Refixation of Delivery Schedule by the Competent
Authority
17
Supplier May ask for Extension of Delivery
Period for Completing Supplies
If Reasons are attributable to Supplier, Normally
Extension is with LD
Extension may be without LD if the Reasons are
beyond the control of Supplier
For Extension without LD, it will require
Concurrence of Finance
18
Situation beyond the control of Supplier
Such Situation may be Natural Calamity, Civil
Commotion, War, Lock Out etc
There is No Damage or Any Sort of Claim by
Either party
The Supplier is Entitled for Extension without
LD to complete the Supplies
Vetting by Finance and Sanction of Competent
Authority may be required
19
Bill payment is based on Measurement Certified
by Engineer
On Completion of Work, Final Measurement is
taken by the Engineer and Work Completion
Certificate is issued
Final Payment after Exercising following
Checks:
Amounts recoverable from Contractor, like LD
(Liquidated Damage), Materials issued to Contractor
etc are correctly accounted for
BUDGET allotment & Exchequer Exists
Amount is within Sanctioned Estimate
20
Payment on Receipt & Acceptance of Materials
For Regular Suppliers, Purchase Order generally
has Part Payment Clause (90%, 95%, 98%)
based on proof of Despatch or Delivery in Depot
{GFR- 172(2)}
Bill is Checked with respect to Vetted Copy of
Purchase Order and Despatch/ receipt Documents
Final Payment is made on Receipt of Material, its
Inspection & Acceptance
21
Payment Clause Is Incorporated in tender
Documents and Forms part of the Contract
Price Break up of components like Supply,
Installation, Commissioning, Trainings etc Is
Detailed in the Contract
Payment Terms –Inspection & Submission of
Documents Forms Basis of Payment
Front Loading of Payment Should be Avoided
Currency of Payment for imports has to be as per
the Terms of the Contract
Exchange Rate Variation Clause for Substantial
Imports Component in Domestic Contracts
22
Stage Payments for Consultancy Contracts
Payments are Correlated to Man Months
10% On Preparation of Inception Report
Detailing Understanding of the Scope and the Mode of
executing the Consultancy Work
60% On submission of Draft Report
Draft Report is Presented to the Client
The Views of the Client is Taken on Various Outcomes and
Findings
The Consultant also Offers Intellectual Inputs on Various
Issues
Agreed points are Incorporated in the Final Report
30% on acceptance of Final Report
23
In Intermediate Payments for Fabrication,
Turn Key Contracts etc Front Loaded
Payments to be avoided
Payment Terms to be suitably devised
keeping financial safeguards in mind
Mode Of Payment:
Accounts Payee Cheque to be duly despatched
& Acknowledgement kept in record
Electronic Payments through RTGS is the
current preferred mode even by CVC
24
Advance payment demanded by firms holding
maintenance contracts for servicing of Air-
conditioners, computers, other costly equipment,
etc.
Advance payment demanded by firms against
fabrication contracts, turn-key contracts etc.
Mobilisation Advance Interest Bearing in
Construction Contracts to be Included in the Tender
Not Exceeding 10 to 15% of the Contract Value
25
Such advance payments should not exceed the
following limits :
Thirty per cent. of the contract value to private firms
Forty per cent. of the contract value to a State or
Central Government agency or a Public Sector
Undertaking
In case of maintenance contract, the amount should
not exceed the amount payable for six months under
the contract.
26
Ministries or Departments of the Central
Government may relax the Ceiling in consultation
with their Financial Advisers
Payment should be secured through Bank
Guarantee
Advance should be set off pro-rata against
successive payments and recovered over the
Period of Contract
Beyond Date of Completion of the Contract, the
Advances not Recovered May invite Levy of Penal
Interest
27
During Execution of the Contract, Situations Do
Arise When the Contract Price Has to Undergo
Adjustment
Such Adjustment Is With Respect to Changed or
Unforeseen Situation at Delivery Stage Compared to
that Prevailing At the Time of Bid Submission
Normally Two Types of Situations Arise:
Change in Statutory Tax Structure
Increase/ Decrease in Input Cost Due to Inflation
28
Locally manufactured Goods Are Subject to
Variation in GST
Specific Provision may be kept in Tender
document for Variation of Statutory Duties &
Taxes by the Government after the Opening of the
Bid
To Determine Variation, the percentage and element
of duties and taxes included in the price should be
specifically stated in the Tender Document
29
Contracts for Supply of Imported Equipment,
goods etc, are Subject to Customs Duty and
Foreign Exchange fluctuations
The Bidder Should Indicate Customs Duty along
with the selling rate of foreign exchange element
taken into account in the calculation of the price
of the imported item
The Variation Permitted has to Be Clearly Laid
Down in the Tender Documents
30
Contracts for Deliveries more than 12 months
should have a clause for Price Escalation
Applicable Even for shorter Deliveries for certain
items with non-ferrous and other Raw Materials
prone to Short Term Price Volatility
To be Incorporated in Tender clauses Itself to
maintain Transparency
For Tender Evaluation this Clause is Not Taken
into Account
31
• Objectives
• Reduce Risk for Bidders
• Protect Employer from Speculative bidding
• Provide Contractor Reasonable Compensation for
Price Fluctuations
• Fixed Price
• Minor Works or Short Delivery Contracts Less than
12 months
• Supply of Machinery & Equipments
32
A Fixed Element Say 10 % in respect of Fixed
Over Heads, Profit etc
Base Indices (Material and Labour) pertains to
prior Period Say One Month Prior to Date of
Tender Opening
Variation of Indices on Delivery – Indices 2
months prior to Delivery as Defined in the
Contract
Suitable Weight to be assigned to Variation of
Material and Labour Components to Calculate
Escalation/De-escalation
33
P = Po (10 % + W1 X L1/Lo
+ W2 X M1/Mo)
W1 and W2 are Appropriate Weight
Lo and L1 are average Consumer Price Index for
Industrial Workers Published by Labour Bureau for
the base month and 2 Months prior to the Delivery
respectively.
Mo and M1 are Material Price Indices, Average of
the Base month and 2 months Prior to the Month in
which Date of Delivery Falls respectively.
34
Material Indices are Published by:
Ministry of Commerce and Industry
Chamber of Commerce like IEEMA,
RBI
London Metal Exchange or
Any Fair Source of Indices Periodically
35
P = Po/100 ( 16 + 24 C/Co + 20 S/So +
7 IS/ISo + 8 PV/PVo + 25 W/Wo)
Co – Average LME Price of Copper Wire
(Two months Prior to Tendering)
So – Price of Electrical Steel Sheets
(1 month Prior to Tendering)
ISo – Whole Sale Price Index of Iron &
Steel
(4 months Prior to Tendering)
36
PVo – Whole Sale Price Index of “Paints, Varnishes
& Lacquers (4 months Prior to Tendering)
Wo – All India Average Consumer Price Index for
Industrial Worker (2 months Prior to Tendering)
Date of Inspection/ Despatch will be taken as Date
of Delivery
Final Index Will be Taken Prior to Delivery for the
Same months as for Initial Index
37
In case of Stage Payment on Staggered Supply,
Payment Should be made as per Basic Rate
38
All Material Prices will be Basic Prices without any
Taxes and Duties and Octroi
No Price Increase is Allowed beyond Original
Delivery Unless Extended with Price Variation
In Case of Levy of LD, generally no PVC is
applicable
No Price adjustment is Admissible on Advances Paid
to Supplier
Price Adjustment may be payable if price Variation is
more than a specified Percentage
Total Price Adjustment may be subject to a Maximum
Ceiling
39
A Supply Contract awarded during Yr 2009 had
PVC Clause based on “Whole Sale Price Index”
of 1993-94 Series Published by Economic
advisor, Ministry of Commerce
The Above Series was discontinued from
September,2010 and another Series Issued
pertaining to Indices 2004-05 was in place
There was No Correlation formulae to Switch
over from Old Indices to New Ones
40
The Issue was Referred to Economic Advisor,
Ministry of Commerce.
They Issued “Regression Equation” for
Correlation to Update Price of Steel etc as on
August,2010 in New Series
Taking this as Base Price, the PVC formulae was
made applicable Up to December,2011
They Also directed to devise New Formulae for
New Contracts
41
42
Applicable to International Trade - Imports
and Export
Buyers and Sellers do not know Each Other
Two Countries may have different Legal and
Statutory framework
Both need some conditions to be fulfilled
before actual Transaction takes place
43
Buyer Wants:
Assurance that Goods Will be Delivered as per
Contract in time
To Pay for Goods only after they are Shipped by
Seller
Seller Wants:
Payment soon after Shipment
Assured payment by Buyer’s Bank as per Contractual
Obligation
Convenience of receiving payments in his own
Country
44
Letter of Credit is a Written Undertaking
given by Buyer’ Bank on behalf of Buyer
through a Bank in Seller’s Country to
Seller to Effect Payment
In a Specified Period
45
Clear on Board Airbill/Bill of Lading
Original Invoice
Packing List
Certificate of Origin
Test Certificate from OEM
Insurance Policy
Warranty Certificate/Performance Bond
Authenticated Signature of Supplier
46
Type of LC
Contractual Details
Delivery Schedule & Basis of Delivery (FOB/CIF)
Amount of Credit and Currency of LC
Part Shipment allowed or Not
LD Clause
Documents to be produced by beneficiary for release
of payment from LC
47
Irrevocable Letter of Credit – Issuing Bank gives
Absolute Undertaking to Honour its Obligations
if Beneficiary Complies with all Terms &
Conditions
Confirmed Letter of credit – By another Bank
in Beneficiary’s Country adds its confirmation
at request of issuing bank to Pay/ negotiate
/accept to Enforce the Agreement
Revolving Letter of Credit – Utilised when buyer
is to receive partial shipment at specific intervals
for long duration
48
In case of Extension of delivery date in contract,
corresponding amendment in LC for revised date
of shipment may be needed
Performance Bank Guarantee may also need
extensionextension
Onus of Bearing Charges for Extension in the
above situation will be met by defaulting party
49
Warranty – Guarantee by Manufacturer for
Replacement In the Event of Manufacturing
Defects
Warranty Has to be Claimed within the Warranty
Period
50
Contractor/ Supplier abandoned or repudiated the
Contract
Has without valid reason failed to commence work
on the Site/System promptly
Persistently fails to execute the Contract in
accordance with the Contract or persistently neglects
to carry out its obligations under the Contract
without just cause
Refuses or is unable to provide sufficient Materials,
Services, or labor to execute and complete the
System in the manner specified
51
Supplier/Contractor becomes bankrupt or insolvent
Supplier assigns or transfers the Contract or any right
or interest therein in violation of the provision of
GCC
Supplier has engaged in corrupt or fraudulent
practices in competing for or in executing the
Contract
Supplier has entered into Unfair Trade Practices
52
In Case of Default, the Incidence has to be Dealt
with in accordance with the Clauses of the
Contract:
Notice Pointing Out Bad/ Unsatisfactory Performance
Levy LD / Imposing Penalty
Termination Has to be followed as Last Option
Adequate notice pointing out defaults as a matter
of Natural Justice before Termination
In case of Termination, Bank Guarantee Should
be Promptly Encashed
Short Closure of the Contract by the Contractor
/Client
53
Cease all further work, except for such work as the
Purchaser may specify in the notice of termination
to Safeguard the Executed Work
Terminate all subcontracts
Deliver to the Purchaser the parts of the System or
Work executed by the Supplier up to the date of
termination
Deliver to the Purchaser all drawings, specifications,
and other documents prepared by the Supplier or its
Subcontractors
54
Warranty – Guarantee by Manufacturer for
Replacement In the Event of Manufacturing
Defects
Warranty Has to be Claimed within the Warranty
Period
55
Mutual Obligations
Adequate Planning before Award of Work
Regular Inspection
Clarity in Directions
Quick Decision Making
56
Arbitration & Conciliation Act, 1996 (amended)
Initially Conciliation is Resorted to Resolve
Disputes
On Failure of Conciliation, Contractor may ask for
Arbitration
Provision & Procedure to Constitute Arbitration
Panel as per Clause in the Contract
Jurisdiction of High Court to Appoint Arbitrator
Arbitration Award Enforceable by Court of Law
57
Parties are free to choose number of Arbitrators in Odd
numbers – Sole or Three
One Arbitrator by each party and the Two Arbitrators
will appoint the Third as Presiding Arbitrator
Clause not applicable if Arbitrator already defined by
name or designation in the Agreement
Arbitrator to be Independent and Impartial and possesses
any qualification if defined in Agreement
Arbitration Award
58
The Award may be set aside by Court only if:
The Party making an Application Produces Proof that It was under
some Incapacity
Arbitration Agreement is not valid under law
59
Award May Also be Set Aside if Court Finds:
the subject-matter of the dispute is not capable of
settlement by arbitration under the law
the arbitral award is in conflict with the public policy
of India.
Court may, where it finds appropriate, adjourn
the proceedings of a period & direct the Tribunal
to resume proceedings to eliminate ground for
setting aside the award
60
61