Professional Documents
Culture Documents
Right Quality
Right Quantity
Right time
and Right manufacturing cost.
Historical development of operations management
Concept Time Explanation
Industrial Late Brought in innovations that changed
revolution 1700s production by using machine power
instead of human power.
Scientific Early Brought the concepts of analysis and
management 1900 measurement of the technical aspects of
work design and development of moving
assembly lines and mass production.
Human 1930s - Focused on understanding human
relations 1960s elements of job design, such as worker
movement motivation and job satisfaction.
Management 1940s - Focused on the development of
science 1960s quantitative techniques to solve
operations problems.
Conti…
Electronic 2000s Uses the Internet and World Wide Web for
commerce conducting business activity.
Formulation of a model
Generating alternatives
Calculus
Mathematical programming
Complete Certainty Method(Algebra)
Solution
Location Revenue - Cost Net return
A Br 40,000 – Br 27,500 Br 12,500
B Br 36,000 – Br 25,400 Br 10,600
C Br 42,000 – Br 29,000 Br 13,000
Decision: C is optimal
Break-even (or cost-volume) analysis
PQ = FC + VC (Q)
QBEP =
Conti…
Conti…
Solution
QBEP = FC/P- VC =
Solution:
Statistical analysis(A)
Queuing theory
Simulation
Heuristic methods
Utility theory
Extreme Uncertainty Methods
2) Maximax,
3) Laplace, and
4) Minimax regret
Conti…
Minimax regret: Determine the worst regret for each alternative, and
choose the alternative with the “best worst.”
Conti…
4 million
Hence, 10 million is the best,
16 million
The best overall pay-off is the 16 million
(c) For the Laplace criterion, first find the row totals, and
then divide each of those amounts by the number of states of
nature (three in this case). Then
Raw total Raw average
Small facility 30 10
Medium facility 31 10.33
Large facility 14 4.67
For instance, in the first column, the best pay-off is 10, so each of
the three numbers in that column must be subtracted from 10.
Going down the column, the regrets will be 10 – 10 = 0, 10 – 7 = 3,
and 10 – (– 4) = 14. In the second column, the best pay-off is 12.
Subtracting each pay-off from 12 yields 2, 0, and 10. In the third
column, 16 is the best pay-off. The regrets are 6, 4, and 0.
Conti…
Alternatives Regrets
Small facility 0 2 6 6
Medium facility 3 0 4 4
Large facility 14 10 0 14
Conti…
Regrets
Alternatives Low Medium High Worst
Small facility 0 2 6 6
Medium facility 3 0 4 4
Large facility 14 10 0 14
The second step is to identify the worst regret for each alternative.
For the first alternative, the worst is 6; for the second, the worst is
4; and for the third, the worst is 14. The best of these worst regrets
would be chosen using Minimax regret. The lowest regret is 4.
• A Visual Representation of
Choices, Consequences,
Probabilities, and Opportunities.
• A Way of Breaking Down
Complicated Situations Down to
Easier-to-Understand Scenarios.
Decision Tree
Conti…
Go to Graduate School to
get my master in CS.
The correct choice depends largely upon demand, which may be low,
medium, or high.
A
B
C
Step 2. Add our possible states of nature, probabilities,
and payoffs
High
Highdemand
demand(0.4)
(0.4) Br
Br90
90
Medium
Mediumdemand
demand(0.5)
(0.5) Br
Br50
50
Br
Br62
62
Low
Lowdemand
demand(0.1)
(0.1) Br
Br10
10
AA
EV
EVAA=0.4(90)+0.5(50)+0.1(10)=Br
=0.4(90)+0.5(50)+0.1(10)=Br 62
62
Conti…
High
Highdemand
demand(0.4)
(0.4) Br
Br200
200
Medium
Mediumdemand
demand(0.5)
(0.5) Br
Br 25
25
Br
Br80.5
80.5
Low
Lowdemand
demand(0.1)
(0.1) Br
Br-120
-120
BB
EV
EVBB=0.4(200)+0.5(25)+0.1(-120)=Br
=0.4(200)+0.5(25)+0.1(-120)=Br 80.5
80.5
Conti…
High
Highdemand
demand(0.4)
(0.4) Br
Br60
60
Medium
Mediumdemand
demand(0.5)
(0.5) Br
Br40
40
Br
Br46
46
Low
Lowdemand
demand(0.1)
(0.1) Br
Br20
20
CC
EV
EVCC=0.4(60)+0.5(40)+0.1(20)=Br
=0.4(60)+0.5(40)+0.1(20)=Br 46
46
Step 4. Make decision
Productivity measurement
Introduction to operations strategy
Rare
Core Competencies
Costly to imitate
Non -substitutable
Core Competencies are the basis for a firm’s
Competitive
advantage
Value creation
Core Competencies
Ability to earn
above-average
returns
Organizational Core Competencies
Order winners and order qualifiers
Competing on Cost
Positioning
Competing on Speed
Competing on Quality
Competing on Flexibility
Productivity measurement
Example 1. BGI Ethiopia is compiling the monthly productivity report for its Board of Directors.
From the following data, calculate (a) labor productivity, (b) machine productivity, and (c) the
multifactor productivity of dollars spent on labor, machine, materials, and energy. The average
labor rate is $15 an hour, and the average machine usage rate is $10 an hour.
Units produced 100,000, Labor hours 10,000, Machine hours
5,000, Cost of materials $35,000
Cost of energy $15,000
Conti…
End of Chapter 2
Chapter Three
Types of processes
All processes can be grouped into two broad categories:
intermittent operations and repetitive operations.
Intermittent Operations
Intermittent operations are used to produce a variety of
products with different processing requirements in lower
volumes.
Conti…
Make-to-order
Only activated in response to an actual order
to a minimum
Make-to-stock
Process activated to meet expected or forecast demand
Solution
Process velocity = Throughput time ÷ value added time
= 0.786 or 78.6%
Efficiency = 25 shirts/day ÷ 28 shirts/day
= 0.89 or 89%
1) Multiple products
2) Phasing in capacity
3) Phasing out capacity
Conti…
Solution
Solution
The factors that can influence the plant location can be:
Capital
Specific Locational Factors for Manufacturing Organization
Dominant factors
1 Facility utilization 8 3 5
2 Total patient per month 5 4 3
3 Average time per emergency 6 4 5
trip
1 Facility utilization 8 3 24 5 40
2 Total patient per month 5 4 20 3 15
3 Average time per 6 4 24 5 30
emergency trip
4 Land and construction 3 1 3 2 6
costs
5 Employee preferences 5 5 25 3 15
Total 96 106
Location 1 Location 2
1 Facility utilization 25 3 5
2 Total patient per month 25 4 3
3 Average time per 25 3 3
emergency trip
5 Employee preferences 10 5 3
Conti…
A (10, 15)
Y
B (30, 10)
X
Distance between point A and point B
Conti…
Decision: Summing the scores for all tracts gives a total load-
distance score of 239 when the facility is located at (5.5, 4.5)
versus a load-distance score of 168 at location (7, 2).
Cx = 453.5/68 = 6.67
Cy = 205.5/68 = 3.02
Process layout
Product layout
Combination layout
Fixed position and
Group layout
Objectives of layout
Organizational
Mental and Geographic
Time of day; rationale for Method of
physical locale of the
Tasks to be time of the job; object- performance
characteristics organization;
performed occurrence in ives and mot- and
of the location of
the work flow ivation of the motivation
work force work areas
worker
Ultimate
Job
Structure
The job design principles
The harder the work, the more the need for rest
periods.
Fit the work to the body rather than forcing the body
to conform to the work.
Work methods
A Production
Process
Job
Design
Worker Interacting
with Equipment
Work Measurement
Standard
Standard time
time == Normal
Normal time
time
++ (Allowances
(Allowances xx Normal
Normal times)
times)
Standard
Standard time
time == NT(1
NT(1 ++Allowances)
Allowances)
Standard
Standard time
time == NT______
NT______
11 --Allowances
Allowances
Time Study Example
= 26.4 minutes
= (26.4)/(1- 0.25)
= 35.2 minutes
Group Assignment (15%)
Long range
Intermediate
range
Short
range
Long-range planning
Greater than one year planning horizon
Usually performed in annual increments
Medium-range planning
Six to eighteen months
Usually with weekly, monthly or quarterly increments
Short-range planning
One day to less than six months
Usually with weekly or daily increments
The Aggregate Operations Plan
Subcontracting
In addition to these strategies, managers also may
choose to subcontract some portion of production.
This strategy is similar to the chase strategy, but
hiring and laying off are translated in to
subcontracting and not subcontracting.
Conti…
Infinite loading
Finite loading
Forward scheduling
Backward scheduling
Conti…
Comparing the due date of each job with its flow time, we
observe that only Job A will be on time. Jobs B,C and D
will be late by 1,8 and 11 days, respectively.
Time-Cost Models
ES=4
Slack=(7-4)=(9-6)= 3 Wks
EF=6
Immediate
Task Predecesors Optimistic Most Likely Pessimistic
A None 3 6 15
B None 2 4 14
C A 6 12 30
D A 2 5 8
E C 5 11 17
F D 3 6 15
G B 3 9 27
H E,F 1 4 7
I G,H 4 19 28
Example 2. Expected Time Calculations
Example 2. Expected Time Calculations
Example 2. Expected Time Calculations
Example 2. Network
Duration = 54 Days
C(14) E(11)
A(7) H(4)
D(5) F(7)
I(18)
B G(11)
(5.333)
End of Chapter 4
Chapter Five
Where:
Conti…
Solution
Since p is not known, it can be estimated from the total
sample:
Conti…
Solution
Because c, the population process average, is not known,
the sample estimate, , can be used instead:
Conti…
Where:
Example 5.3
Solution
is computed by first determining the range for each
sample by computing the difference between the highest
and lowest values as shown in the last column in our table
of sample observations. These ranges are summed and
then divided by the number of samples, k, as follows:
Conti…
Using the value of A2 = 0.58 for n =5 from Table 5.1 and = 0.115,
we compute the control limits as
Where