PROJECT
Presented by: Mustafa Almandouh
Belts Actual Data For
Forcasting
Month Exponential Error Error Squared
Belts
EMA(choosen) 2
3
29000
29500
30000
29400
1000
100
1000000
10000
4 31000 29460 1540 2371600
5 27000 30384 3384 11451456
6 28000 28353.6 353.6 125032.96
7 30000 28141.44 1858.56 3454245.274
8 30300 29256.576 1043.424 1088733.644
9 26400 29882.6304 3482.63 12128714.5
10 25700 27793.0522 2093.052 4380867.344
11 24800 26537.2209 1737.221 3017936.33
12 26000 25494.8883 505.1117 255137.7834
13 25797.9553
MAD MSE
1554.327 3571247.622
Month Actual Data For Fabrics Exponential Error Error Squared
EMA
6 16700 16183.68 516 266586.3424
(choosen)
10 18800 17680.38221 1120 1253544
13 18104.34446
MAD MSE
598 501711.4553
Month Belt Fabrics
1 30,000 15,000
2 29,000 15,200
3 29,500 16,000
4 31,000 16,500
5 27,000 16,200
INVENTOR
6 28,000 16,700
7 30,000 17,550
8 30,300 18,000
9 26,400 17,700
Y AND EPQ
10 25,700 18,800
11 24,800 17,650
12 26,000 18,220
Total 337,700 203,520
Belt
Holding cost 16
Ordering cost 70
Demand for Belts 337700
Usage (U) 500
Production (P) 1500
Fabrics
Holding cost 10
Ordering cost 50
Demand for Fabrics 203520
Usage (U) 500
Production (P) 1500
U = D/ 365 = 365*500= 182500
(EPQ) method = QP* = √2DS/H √p/(p-u) = √(2*182500*50)/10 EPQ method Usage (U) = D/ 365 = 337700/365 = 925.2055
√1500/(1500-500) = 1654.539211 Fabrics
Cycle time = (QP*)/u = 1654.539211/500 = 3.309078422
days Since P>U, it’s economic production quantity (EPQ)
TC = (Imax/2) H + D/(QP*) S = [1/2* (QP*)/p (p-u)] H + QP* = √2DS/H √p/(p-u) = √(2*337700*70)/16 √1500/(1500-
D/(QP*) S 925.2055) = 2776.891 Belts
= [1/2* 1654.539211/1500 (1500-500)] (10) +
182500/1654.539211 * 50
= $11030.26141 Cycle time = (QP*)/u = 2776.891 / 925.2055 = 3.001378 days
S Near To
Customer
Infrastructure
5%
5%
25
12
10
8
12
15
1
Output-
0 0 1000 1000 -2000 0 0 0
Forecast
Calculate Cost
Period 1 2 3 4 5 6 7 8Total
Regular 39000 39000 39000 39000 39000 39000 39000 39000 312000
Output Parttime
Overtime 0 0 2000 3000 3000 0 0 0 8000
Aggregate Hire/Layoff
JOB FLOW DUE TRADY JOB FLOW DUE TRADY JOB FLOW DUE TRADY
JOB JOB JOB
TIME TIME DATE DAYS TIME TIME DATE DAYS TIME TIME DATE DAYS
A 5 5 8 0 A 5 5 8 0 B 6 6 5 1 Rule AFT AT AJWC Utilization
B 6 11 5 6 B 6 11 5 6 A 5 11 8 3 FSFS 19.6 11.2 2.8 0.357142857
C 9 20 10 10 D 7 18 12 6 C 9 20 10 10 SPT 19 10.6 2.714285714 0.368421053
D 7 27 12 15 E 8 26 10 16 E 8 28 10 18 EDD 20 11 2.857142857 0.35
E 8 35 10 25 C 9 35 10 25 D 7 35 12 23
TOTAL 35 98 56 TOTAL 35 95 53 TOTAL 35 100 55