BIM Professional Course | M8 | Live Session 1

Student guide for


Module 8 Live session 1

4D Phase Planning
BIM Professional Course | M8 | Live Session 1

⚽ Activity 01
NAVISWORKS
Creating a 4D Simulation
BIM Professional Course | M8 | Live Session 1

✍🏻
Activity 01
Creating a 4D Simulation
1. Open “WFP-NVS2015-09-Timeliner3” Navisworks file.
2. View>Window>Select: Set - Check the sets
3. Home>TimeLiner>Data Source>Add>Microsoft Project MPX
4. Select “WFP-NVS2015-09-Timeliner.mpx”
5. Select the following fields
6. Select Data Source, right click
7. Rebuild Task Hierarchy
BIM Professional Course | M8 | Live Session 1

✍🏻
Activity 01
Creating a 4D Simulation
8. Go to “Task” Tab
9. Update all “Task Type” as “Construct”.
10. Go to “Auto-Attach Using Rules”
11. “New” and update
12. Select your new role and apply rules
13. Go to “Simulate” and play
BIM Professional Course | M8 | Live Session 1

⚽ Activity 02
NAVISWORKS
Exporting the Simulation
BIM Professional Course | M8 | Live Session 1

✍🏻
Activity 02
Exporting Simulation
1. Timeliner>Configure>Construct: Change this as “Green”
2. Timeliner>Simulate>Settings
3. Click “Overlay Text”>Edit - Delete
4. Add “Date” (Date and time representation) and “Extras” (Current Active Tasks)
5. “Font”-Arial, Narrow, 10
BIM Professional Course | M8 | Live Session 1

✍🏻
Activity 02
Exporting Simulation