Professional Documents
Culture Documents
A D E F
C
Project Scheduling Terms
• Merge activities
• Burst activities
• Node
• Path
• Critical Path
A D E F
C
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-3
Network Diagrams
Show Help
interdependence schedule
resources
Show
Facilitate start &
communication finish
dates
Determine project Identify
completion critical
activities
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-4
AOA vs. AON
The same mini-project is shown with activities on
arrow…
D E
B F
C
C
Node Labels
Early ID Early
Start Number Finish
Activity
Float Activity Descriptor
Late Activity Late
Start Duration Finish
Duration Estimation Methods
• Past experience
• Expert opinion
• Mathematical derivation – Beta distribution
– Most likely (m)
2
– Most pessimistic (b) ba
– Most optimistic (a)
Activity Variance = s
2
6
a 4m b
Activity Duration = TE
6
1. Sketch the network described in the table.
2. Determine the expected duration and variance of each
activity.
Task Predecessor a m b
A -- 7 8 15
B A 13 16 19
C A 14 18 22
D B, C 12 14 16
E D 1 4 13
F D 6 10 14
G F, E 11 14 19
Constructing the Critical Path
• Forward pass – an additive move through the
network from start to finish
0 A 6 6 B 11 Lag 4 15 C 22
Spec Design Design Check Blueprinting
6 5 7
This lag is not
the same as
activity slack
Finish to Finish Lag
Two activities share a similar completion point
– The mechanical inspection cannot happen until
wiring, plumbing, and HVAC installation are complete
15 A 21
Lag 3
Wiring
6
10 B 16 16 C 24 24 D 25
Plumbing HVAC Inspection
6 5 1
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-17
Start to Start Lag
Logic must be
maintained by both
forward and backward
30 A 36 pass
Wiring
6
Lag 3
33 C 36 36 D 37
31 B 32 HVAC Inspection
Plumbing 5 1
1
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-18
Start to Finish Lag
22 B 28 28 C 33 33 D 34
Plumbing HVAC Inspection
6 5 1
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-19
Gantt Charts
Establish a time-phased network
Can be used as a tracking tool
B D I
A H
E F
C
G