DISTRICT MUNICIPALITY

UPGRADING OF MAIN SEWER OUTFALL


PIPELINE
PRESENTER:
VENUE:
DATE:
2 TABLE OF CONTENT
1. BACKGROUND (INCLUDE CLEAR MOTIVATION FOR PROJECT, LIST ALL STAKEHOLDERS)
2. LOCALITY MAP [ALSO CLEARLY SHOW AREA(S) GENERATING THE SEWAGE AND
DISCHARGE/ OUTFALL POINTS – USE TOOLS E.G., GOOGLE EARTH, GIS, ETC]
3. OBJECTIVE OF THE PROJECT (INCLUDE BENEFICIARY NUMBERS IN LINE WITH MIG
CONDITIONS)
4. FEASIBILITY INVESTIGATIONS MADE OR PROPOSED & ANY AVAILABLE INFORMATION
(SURVEY, GEOTECH, AS-BUILTS, SOCIAL, ENVIRONMENT, LEGAL )
5. GENERATED SEWAGE DISCHARGE QUANTITIES (CURRENT & FUTURE) (CALCULATIONS
TABLE)
6. EXISTING BULK INFRASTRUCTURE [CONDITION & CAPACITY TO CATER FOR GENERATED
SEWAGE (OUTFALL SEWERS, WWTP, PUMP STATIONS, PERMITS, ETC)]
7. SCOPE OF WORK (PIPE DIAMETERS, LENGTHS, ETC)
8. COST ESTIMATION (IN LINE WITH UNIT COSTS; OTHERWISE JUSTIFY)
9. IMPLEMENTATION PLAN 2022/23
10. RECOMMENDATION
3 1, BACKGROUND

• The project is to upgrade a 56-year-old AC sewer outfall pipe in Seweding,


Mmabatho, with a new uPVC pipeline.
• The existing sewer outfall is a deteriorated AC pipe (400mm diameter,
5.5km length) experiencing frequent blockages, collapses, and overflows.
• The project will improve the sewer outfall system’s performance and reduce
the environmental and health risk.
• Relevant stakeholders such as DWS, NMMDM, MLM & Department of
health assisted in resolving the crisis and the overall project.
• Project is recommended by DWS
4 3, OBJECTIVES OF THE
PROJECT
• Replacement and Rehabilitation: The primary objective of this project is to
replace and rehabilitate the aging Seweding Main Sewer Outfall pipeline.
• Capacity Enhancement: Enhance the sewer outfall's capacity to
accommodate current and future wastewater flows effectively.
Capital project
• Capital project essential due to severe aging-related structural issues in the
Main Sewer Outfall.
• Limited capacity and recurring blockages necessitate extensive upgrades that
go beyond the scope of O&M
• Provides a sustainable sewer system addressing issues that O&M activities
alone cannot resolve.
5 4, FEASIBILITY STUDIES

• Survey study is currently ongoing with site inspections.


• Geotechnical engineer has been appointed and will commence
with the study.
• As-builts – Surveyor
• Geotechnical, Social, Environmental and Legal studies will
follow
6 5, GENERATED SEWAGE
IPWWF
Sewer flow (Unit
Water (Allow
Stand Size PDDWF) PDDWF
Land Use Demand Unit for 15%
• (ha)
(unit AADD) %AADD
(kl/d)
Infiltration)
(kl/ha/d) kl/unit/d kl/d
Stands for low-
income housing Medium density, 270m2 to
0.5kl/unit/d 39598 92.5% 0.4625 18314.08 21061.19
(waterborne medium sized 400m2
sanitation)
Business 233.56 21 kl/ha/d 22 80% 16.8 3923.81 4512.38
Schools 22.35 20 kl/ha/d 3 80% 16 357.60 411.24
Creche 2.33 20 kl/ha/d 1 80% 16 37.28 42.87
Church 1.2 20 kl/ha/d 1 80% 16 19.20 22.08
Parks/Play areas 0.5 12 kl/ha n/a n/a n/a n/a
Cemetary 5 12 kl/ha n/a n/a n/a n/a
Community
1.3 12 kl/ha 1 80% 16 20.80 23.92
facility

Initial Wastewater Demand - Total Wastewater Demand per day (kl/day) 26073.68
Initial Wastewater Demand - Total Wastewater Demand per day (l/s) 301.78
Ultimate wastewater demand in 20 years (5%) (l/s) 371.89
Peak Wastewater Flow - Total Wastewater Demand per day (l/s) 754.45
Peak Wastewater Flow - Total Wastewater demand in 20 years (l/s) 929.73
6, EXISTING BULK INFRASTRUCTURE
• CONDITION & ADEQUACY OF EXISTING BULK
INFRASTRUCTURE TO CATER FOR PROPOSED DISCHARGES

Detection of existing services to be


completed by survey study

Existing Sewer outfall & Eskom


line to be relocated on Airport road

400 mm diameter AC pipe with 70


manholes

5.6 km in length from bulk to


WWTP
7, SUMMARY OF SCOPE OF WORK

• Conduct a comprehensive survey and geotechnical


8 investigation of the existing sewer outfall.
• Construct and install new sewer pipes with upgraded
materials (uPVC)
• Develop sustainable stormwater management practices to
prevent further contamination
• Collaboration and stakeholder engagement key to
successful implementation
9 8, COST ESTIMATES
• Summarized/Shortened BOQ indicating unit, rate and amount:

• Summary of Cost:
– Estimated Construction cost
– Health & Safety consultant
– EIA (if required)
– Social facilitation
– Geohydrological studies (if required)
– Geotechnical investigation (if required)
– Surveyors
– Professional fees (ECSA fees scale guideline)
– Full or Part-time supervision
– Travelling & Disbursement
– Total Vat Inclusive

• Unit cost per household (Motivation if exceeded unit cost guideline)


10 9,IMPLEMENTATION PLAN

• Project Initiation and Preliminary Assessments (3 months)


• R-- million

• Site Investigation and Infrastructure Upgrade (1.5 years)


• R-- million

• Project Completion
• R-- million
11