You are on page 1of 18

SPP

MINIMUM
BASIC FEE's
May 16, 2014
Group 1 - Simple
6% of Project Construction Cost
Sample
PCC = 2,000,000 pesos

MBF =____________
2,000,000 x 6 MBF = 2,000,000 x 0.06
100

MBF = 120,000 pesos MBF = 120,000 pesos


Group 2 - Moderate
7% of Project Construction Cost
Sample
PCC = 2,000,000 pesos

MBF =____________
2,000,000 x 7 MBF = 2,000,000 x 0.07
100

MBF = 140,000 pesos MBF = 140,000 pesos


Group 3 - Exeptional
8% of Project Construction Cost
Sample
PCC = 2,000,000 pesos

MBF =____________
2,000,000 x 8 MBF = 2,000,000 x 0.08
100

MBF = 160,000 pesos MBF = 160,000 pesos


Group 4 - Residences
10% of Project Construction Cost
Sample
PCC = 2,000,000 pesos

MBF =_____________
2,000,000 x 10 MBF = 2,000,000 x 0.10
100

MBF = 200,000 pesos MBF = 200,000 pesos


Group 5 - Monumental
12% of Project Construction Cost
Sample
PCC = 2,000,000 pesos

MBF =_____________
2,000,000 x 12 MBF = 2,000,000 x 0.12
100

MBF = 240,000 pesos MBF = 240,000 pesos


Group 6 – Repetitive Construction
1st Structure - MINIMUM BASIC FEE
2nd Structure - 80% of MBF
3rd Structure - 60% of MBF
4th Structure - 40% of MBF

Sample
Project = Mall (which is under Group 2)
PCC = 2,000,000 pesos
Group 6 – Repetitive Construction
1st Structure
MBF =____________
2,000,000 x 7 MBF = 2,000,000 x 0.07
100
MBF = 140,000 pesos MBF = 140,000 pesos

2nd Structure
MBF =____________
140,000 x 8 MBF = 140,000 x 0.80
100
MBF = 112,000 pesos MBF = 112,000 pesos
Group 6 – Repetitive Construction
3rd Structure
MBF =_____________
140,000 x 6 MBF = 1400,000 x 0.06
100
MBF = 84,000 pesos MBF = 84,000 pesos

4th Structure
MBF =_____________
140,000 x 4 MBF = 140,000 x 0.40
100
MBF = 56,000 pesos MBF = 56,000 pesos
Group 7 – Housing
1st Unit - MINIMUM BASIC FEE
2nd – 10th Units - 60% of MBF
11th and above - 30% of MBF

Sample
Subdivision
PCC = 1,000,000 pesos for 1 unit
1. Calculate how much you will get for 10 units
2. Calculate how much you will get for 15 units
Group 7 – Housing (Prob. #1)
1st Unit
MBF =_____________
1,000,000 x 10 MBF = 1,000,000 x 0.10
100
MBF = 100,000 pesos MBF = 100,000 pesos

2nd to 10th Units


MBF =________________
100,000 x 60 x 9 MBF = 100,000 x 0.60 x 9
100
MBF = 540,000 pesos MBF = 540,000 pesos
Group 7 – Housing (Prob. #1)
So For the 10 units

Total Fee = (1st unit fee) + (fee for 2nd to 10th Units)
Total Fee = 100,000 + 540,000

Total Fee = 640,000 pesos – fee for 10 units


Group 7 – Housing (Prob. #2)
1st Unit
MBF =_____________
1,000,000 x 10 MBF = 1,000,000 x 0.10
100
MBF = 100,000 pesos MBF = 100,000 pesos

2nd to 10th Units


MBF =________________
100,000 x 6 x 9 MBF = 100,000 x 0.60 x 9
100
MBF = 540,000 pesos MBF = 540,000 pesos
Group 7 – Housing (Prob. #2)
11th to 15th Units
MBF =________________
100,000 x 3 x 5 MBF = 100,000 x 0.30 x 5
100
MBF = 150,000 pesos MBF = 150,000 pesos
So For the 15 units
Total Fee = (1st unit fee) + (fee for 2nd to 10th Units)
+ (fee for 11th to 15th Units)
Total Fee = 100,000 + 540,000 + 150,000
Total Fee = 790,000 pesos – fee for 15 units
Group 8 – Extensive Details
15% of Project Construction Cost
Sample
PCC = 2,000,000 pesos

MBF =_____________
2,000,000 x 15 MBF = 2,000,000 x 0.15
100

MBF = 300,000 pesos MBF = 300,000 pesos


Group 9 – Alterations, Additions...
150% of Minimum Basic Fee
Sample
MBF = 140,000 pesos – First time you did the Project

MBF =_____________
140,000 x 150 MBF = 140,000 x 1.50
100

MBF = 210,000 pesos MBF = 210,000 pesos


Group 10 – Consultation
For Groups 1,2,3,4 & 5
= 200 pesos / hour

Appearance within 100 kilometer radius


from office
= 500 pesos / appearance
end