Opermgt 345

January, 2001

Project Management
Basic Concepts

1
Opermgt 345 Shannon January, 2001
What is a Project?

A Project is a series of activities and tasks


that:
Have a specific objective to be completed with
certain objectives
Have a defined start and end dates
Have funding limits (if applicable)
Consume Resources

2
Opermgt 345 Shannon January, 2001
Typical Project Structure

Project
Project
Definition
Definition
Project
Project
Monitoring
Monitoring
Project
Project
Planning
Planning

Project
Project Project
Project
Implementation
Implementation Evaluation
Evaluation

Project
Project
Adjustment
Adjustment 3
Opermgt 345 Shannon January, 2001
Resources and Effort Project Life Cycle

Phase 1 Phase 2 Phase 3 Phase 4 Phase 5


Conceptual Advanced Detailed Project Project
Design Development Design Implementation Termination

•Goals •Plan •Define •Manage •Closeout


•Scope •Budget Responsibility •Measure •Document
•Baseline •Schedule •Team •Control •Suggest
•Requirements •Management •Organization •Update and Improvements
•Feasibility Commitment Structure Modify Plan •Reassign
•Desirability •Detailed Plan •Problem Solve •Dissolve Project
•Kickoff Team
4
Opermgt 345 Shannon January, 2001
Successful Projects

A successful project is one which achieves the


following objectives:

– Completed On Time
– Completed Within Cost
– Meets Performance Criteria
– Minimum Disruption of the Main Work of the
Organization
– Effective Utilization of Resources
5
Opermgt 345 Shannon January, 2001
The Triple Play of
Project Management

Time Cost

Constraints

Performance

6
Opermgt 345 Shannon January, 2001
Triple Constraint Trade-offs
$

Budget Better

Performance
Worse Specifications

Early Schedule Late TIME


7
Opermgt 345 Shannon January, 2001
Major causes of failure

 Selection of a unsound project


 Selecting the wrong person as a project
manager
 Lack of support from upper management
 Misused management techniques
 Project termination not planned

8
Opermgt 345 Shannon January, 2001
Project Definition

Build Canoe Rental Building on


Coeur d A’lene Lake

9
Opermgt 345 Shannon January, 2001
Form Project Team

•Select Project Leader

•Identify Key People

•Gain Management Commitment

•Define Project Team Operating Rules

10
Opermgt 345 Shannon January, 2001
The Top Level Project Tasks

Brainstorm
Brainstorm
the
the
Major
MajorTasks
Tasks

C
B G
Establish
Establish A
Work
WorkFlow
Flow
D E F

11
Opermgt 345 Shannon January, 2001
Define Top Level Tasks
Canoe Example

Site Preparation

Build Dock

Build Building

Finish and Ready for Business

12
Opermgt 345 Shannon January, 2001
Sequence Top Level Tasks

Build Dock

Site Preparation Finish

Build Building

13
Opermgt 345 Shannon January, 2001
Detailed
Sub-Tasks
Tasks

C
G
B

D E F

Develop Work Sequence


Detailed
Tasks
14
Opermgt 345 Shannon January, 2001
Brainstorm Sub-Tasks
Site Preparation Build Dock Build Building Finish

Dock Site Install Pilings Foundation Order Canoes

Frame
Landscape
Building Site Build Dock
Roof

Assemble
Power
Canoes

Siding Open for


Business

Paint
15
Opermgt 345 Shannon January, 2001
Work Breakdown Structure

Top Level Task

2nd Level 2nd Level 2nd Level 2nd Level


Task Task Task Task

3rd Level 3rd Level 3rd Level 3rd Level


Task Task Task Task

3rd Level 3rd Level 3rd Level 3rd Level 3rd Level
Task Task Task Task Task

16
Opermgt 345 Shannon January, 2001 Lower Level Tasks
Sequence Sub-Tasks
Task Description Immediate Predecessor
A Prepare Dock Site -
B Prepare Hut Site -
C Install Dock Pilings A
D Foundation for Hut B
E Build Dock C
F Frame Hut D
G Power to Hut D
H Side the Hut F
I Roof the Hut F
J Order Canoes and Receive Canoes -
K Paint Hut H
L Assemble Canoes J
M Finish Landscaping L,I,K,E,G
N Open for Business M
17
Opermgt 345 Shannon January, 2001
Build Network Diagram
(PERT Chart)
(Activities on Arrows)

Task Predecessor
A Prepare Dock Site -
B Prepare Hut Site -
C Install Dock Pilings A
D Foundation for Hut B
E Build Dock C
F Frame Hut D
G Power to Hut D
H Side the Hut F
I Roof the Hut F
J Order Canoes and Receive Canes -
K Paint Hut H
L Assemble Canoes J
M Finish Landscaping L,I,K,E,G
N Open for Business M
18
Opermgt 345 Shannon January, 2001
Build Network Diagram
(PERT Chart)

A
1 3
Prep Dock
Site

Task Predecessor
A Prepare Dock Site -
B Prepare Hut Site -
C Install Dock Pilings A
D Foundation for Hut B
E Build Dock C
F Frame Hut D
G Power to Hut D
H Side the Hut F
I Roof the Hut F
J Order Canoes and Receive Canes -
K Paint Hut H
L Assemble Canoes J
M Finish Landscaping L,I,K,E,G
N Open for Business M
19
Opermgt 345 Shannon January, 2001
Build Network Diagram
(PERT Chart)
2

J es
a no
derC
Or
A
1 3
Prep Dock
Site

Task Predecessor
A Prepare Dock Site -
B Prepare Hut Site -
C Install Dock Pilings A
D Foundation for Hut B
E Build Dock C
F Frame Hut D
G Power to Hut D
H Side the Hut F
I Roof the Hut F
J Order Canoes and Receive Canes -
K Paint Hut H
L Assemble Canoes J
M Finish Landscaping L,I,K,E,G
N Open for Business M
20
Opermgt 345 Shannon January, 2001
Build Network Diagram
(PERT Chart)
2

J es
a no
derC
Or
A
1 3
Prep Dock
Site

B Task Predecessor
Prep te
Hut S

A Prepare Dock Site -


B Prepare Hut Site -
are

C Install Dock Pilings A


i

D Foundation for Hut B


4 E Build Dock
F Frame Hut
C
D
D G Power to Hut D
H Side the Hut F
Hut I Roof the Hut F
Foundation 6 J Order Canoes and Receive Canes -
K Paint Hut H
L Assemble Canoes J
M Finish Landscaping L,I,K,E,G
N Open for Business M
21
Opermgt 345 Shannon January, 2001
Build Network Diagram
(PERT Chart)
2

J es
a no
derC
Or
A C E
1 3 5 9
Prep Dock Install Pilings Build Dock
Site

B Task Predecessor
Prep te
Hut S

A Prepare Dock Site -


B Prepare Hut Site -
are

C Install Dock Pilings A


i

D Foundation for Hut B


4 E Build Dock
F Frame Hut
C
D
D G Power to Hut D
H Side the Hut F
Hut I Roof the Hut F
Foundation 6 J Order Canoes and Receive Canes -
K Paint Hut H
L Assemble Canoes J
M Finish Landscaping L,I,K,E,G
N Open for Business M
22
Opermgt 345 Shannon January, 2001
Build Network Diagram
(PERT Chart)
2

J es
a no
derC
Or
A C E
1 3 5 9
Prep Dock Install Pilings Build Dock
Site

B Task Predecessor
Prep te
Hut S

G Hut A Prepare Dock Site


B Prepare Hut Site
-
-
o
are

rT C Install Dock Pilings A


i

o we D Foundation for Hut B


4 P E Build Dock C
F Frame Hut D
D G Power to Hut D
H Side the Hut F
Hut I Roof the Hut F
Foundation 6 J Order Canoes and Receive Canes -
K Paint Hut H
L Assemble Canoes J
M Finish Landscaping L,I,K,E,G
N Open for Business M
23
Opermgt 345 Shannon January, 2001
Build Network Diagram
(PERT Chart)
2
Ass L
J oe s e mb
Can le C
r der ano
es
O
A C E
1 3 5 9
Prep Dock Install Pilings Build Dock
Site

B Task Predecessor
Prep te
Hut S

G Hut A Prepare Dock Site


B Prepare Hut Site
-
-
o
are

rT C Install Dock Pilings A


i

o we D Foundation for Hut B


4 P E Build Dock C
F Frame Hut D
D G Power to Hut D
H Side the Hut F
Hut I Roof the Hut F
Foundation 6 J Order Canoes and Receive Canes -
K Paint Hut H
L Assemble Canoes J
M Finish Landscaping L,I,K,E,G
N Open for Business M
24
Opermgt 345 Shannon January, 2001
Build Network Diagram
(PERT Chart)
2
Ass L
J oe s e mb
Can le C
r der ano
es
O
A C E
1 3 5 9
Prep Dock Install Pilings Build Dock
Site

B Task Predecessor
Prep te
Hut S

G Hut A Prepare Dock Site


B Prepare Hut Site
-
-
o
are

rT C Install Dock Pilings A


i

we D Foundation for Hut B

of
Po
4
Ro
E Build Dock C
D I F Frame Hut D
G Power to Hut D
H Side the Hut F
Hut F I Roof the Hut F
Foundation 6 7 J Order Canoes and Receive Canes -
Frame Hut K Paint Hut H
L Assemble Canoes J
M Finish Landscaping L,I,K,E,G
N Open for Business M
25
Opermgt 345 Shannon January, 2001
Task Predecessor
A Prepare Dock Site -
B Prepare Hut Site -

Build Network Diagram C Install Dock Pilings


D Foundation for Hut
E Build Dock
A
B
C

(PERT Chart) F Frame Hut


G Power to Hut
D
D
H Side the Hut F
I Roof the Hut F
J Order Canoes and Receive Canes -
2 K Paint Hut H
L Assemble Canoes J
M Finish Landscaping L,I,K,E,G
Ass L
oe s
N Open for Business M
J e mb
Can le C
r der ano
es
O
A C E
1 3 5 9
Prep Dock Install Pilings Build Dock
Site

B
Prep te
Hut S

G Hut
o
are

rT
i

we

of
Po K Paint
4
Ro
D I Hut
Hut F H
Foundation 6 7 8
Frame Hut Side Hut

26
Opermgt 345 Shannon January, 2001
Task Predecessor

Build Network A Prepare Dock Site


B Prepare Hut Site
C Install Dock Pilings
D Foundation for Hut
-
-
A
B

Diagram
E Build Dock C
F Frame Hut D
G Power to Hut D
H Side the Hut F
I Roof the Hut F

(PERT Chart)
2
J Order Canoes and Receive Canes
K Paint Hut
L Assemble Canoes
M Finish Landscaping
-
H
J
L,I,K,E,G
Ass L
oe s
N Open for Business M
J e mb
Can le C
r der ano
es
O
A C E M N
1 3 5 9 10 11
Prep Dock Install Pilings Build Dock Finish Open for
Site Landscape Business

B
Prep te
Hut S

G Hut
o
are

rT
i

we

of
Po K Paint
4
Ro
D I Hut
Hut F H
Foundation 6 7 8
Frame Hut Side Hut

27
Opermgt 345 Shannon January, 2001
Build Network Diagram Task Description Time

(PERT Chart) Canoe Example A Prepare Dock Site


B Prepare Hut Site
3d
4d
C Install Dock Pilings 6d
Add Times D Foundation for Hut
E Build Dock
3d
4d
F Frame Hut 3d
G Power to Hut 2d
2 H Side the Hut
I Roof the Hut
2d
3d
J Order Canoes 2d
Ass L (10) K Paint Hut 4d
J (2) oe s e mb L Assemble Canoes 10 d
Can le C M Finish Landscaping 4d

r der ano
es
NOpen for Business 2d
O
A (3) C (6) E (4) M (4) N (2)
1 3 5 9 10 11
Prep Dock Install Pilings Build Dock Finish Open for
Site Landscape Business

B (4)
Prep te
Hut S

G (2) Hut
o
are

rT
i

we

of
Po Paint
4
Ro
I (2) K (4) Hut
D (3)
Hut F (3) H (2)
Foundation 6 7 8
Frame Hut Side Hut

28
Opermgt 345 Shannon January, 2001
Build Network
Task Predecessor
A Prepare Dock Site -
B Prepare Hut Site -
C Install Dock Pilings A

Diagram D Foundation for Hut


E Build Dock
F Frame Hut
G Power to Hut
B
C
D
D

(PERT Chart)
H Side the Hut F
I Roof the Hut F
J Order Canoes and Receive Canes -
2 K Paint Hut H
L Assemble Canoes J
M Finish Landscaping L,I,K,E,G
Ass L
oe s
N Open for Business M
J e mb
Can le C
r der ano
es
O
A C E M N
1 3 5 9 10 11
Prep Dock Install Pilings Build Dock Finish Open for
Site Landscape Business

B
Prep te
Hut S

G Hut
o
are

rT
i

we

of
Po K Paint
4
Ro
D I Hut
Hut F H
Foundation 6 7 8
Frame Hut Side Hut

29
Opermgt 345 Shannon January, 2001
Build Network Diagram Task Description Time

(PERT Chart) Canoe Example A Prepare Dock Site


B Prepare Hut Site
3d
4d
C Install Dock Pilings 6d
Add Times D Foundation for Hut
E Build Dock
3d
4d
F Frame Hut 3d
G Power to Hut 2d
2 H Side the Hut
I Roof the Hut
2d
3d
J Order Canoes 2d
Ass L (10) K Paint Hut 4d
J (2) oe s e mb L Assemble Canoes 10 d
Can le C M Finish Landscaping 4d

r der ano
es
NOpen for Business 2d
O
A (3) C (6) E (4) M (4) N (2)
1 3 5 9 10 11
Prep Dock Install Pilings Build Dock Finish Open for
Site Landscape Business

B (4)
Prep te
Hut S

G (2) Hut
o
are

rT
i

we

of
Po Paint
4
Ro
I (2) K (4) Hut
D (3)
Hut F (3) H (2)
Foundation 6 7 8
Frame Hut Side Hut

30
Opermgt 345 Shannon January, 2001
Determining Project Length

Option 1: Sum all the task durations:


A Prepare Dock Site - 3d
B Prepare Hut Site - 4d
C Install Dock Pilings A 6d
D Foundation for Hut B 3d
E Build Dock C 4d
F Frame Hut D 3d
G Power to Hut D 2d
H Side the Hut F 2d
I Roof the Hut F 3d
J Order Canoes and Receive Canoes - 2d
K Paint Hut H 4d
L Assemble Canoes J 10 d
M Finish Landscaping L,I,K,E,G 4d
N Open for Business M 2d

Sum = 52 days
Anything wrong with this approach?
31
Opermgt 345 Shannon January, 2001
Determining Project Length

Option 2: Determine duration of each network path

32
Opermgt 345 Shannon January, 2001
Paths:
Network Diagram
A-C-E-M-N = 19 days
Project Paths

2
Ass L (10)
J (2) oe s e mb
Can le C
r der ano
es
O
A (3) C (6) E (4) M (4) N (2)
1 3 5 9 10 11
Prep Dock Install Pilings Build Dock Finish Open for
Site Landscape Business

B (4)
Prep te
Hut S

G (2) Hut
o
are

rT
i

we

of
Po Paint
4
Ro
I (2) K (4) Hut
D (3)
Hut F (3) H (2)
Foundation 6 7 8
Frame Hut Side Hut

33
Opermgt 345 Shannon January, 2001
Paths:
Network Diagram
A-C-E-M-N = 19 days
B-D-F-H-K-M-N = 22 days Project Paths

2
Ass L (10)
J (2) oe s e mb
Can le C
r der ano
es
O
A (3) C (6) E (4) M (4) N (2)
1 3 5 9 10 11
Prep Dock Install Pilings Build Dock Finish Open for
Site Landscape Business

B (4)
Prep te
Hut S

G (2) Hut
o
are

rT
i

we

of
Po Paint
4
Ro
I (2) K (4) Hut
D (3)
Hut F (3) H (2)
Foundation 6 7 8
Frame Hut Side Hut

34
Opermgt 345 Shannon January, 2001
Paths:
Network Diagram
A-C-E-M-N
B-D-F-H-K-M-N
= 19 days
= 22 days Project Paths
B-D-F-I-M-N = 18 days

2
Ass L (10)
J (2) oe s e mb
Can le C
r der ano
es
O
A (3) C (6) E (4) M (4) N (2)
1 3 5 9 10 11
Prep Dock Install Pilings Build Dock Finish Open for
Site Landscape Business

B (4)
Prep te
Hut S

G (2) Hut
o
are

rT
i

we

of
Po Paint
4
Ro
I (2) K (4) Hut
D (3)
Hut F (3) H (2)
Foundation 6 7 8
Frame Hut Side Hut

35
Opermgt 345 Shannon January, 2001
Paths:
Network Diagram
A-C-E-M-N
B-D-F-H-K-M-N
= 19 days
= 22 days Project Paths
B-D-F-J-M-N = 18 days
B-D-G-M-N = 15 days
2
Ass L (10)
J (2) oe s e mb
Can le C
r der ano
es
O
A (3) C (6) E (4) M (4) N (2)
1 3 5 9 10 11
Prep Dock Install Pilings Build Dock Finish Open for
Site Landscape Business

B (4)
Prep te
Hut S

G (2) Hut
o
are

rT
i

we

of
Po Paint
4
Ro
I (2) K (4) Hut
D (3)
Hut F (3) H (2)
Foundation 6 7 8
Frame Hut Side Hut

36
Opermgt 345 Shannon January, 2001
Paths:
Network Diagram
A-C-E-M-N
B-D-F-H-K-M-N
= 19 days
= 22 days Project Paths
B-D-F-J-M-N = 18 days
B-D-G-M-N = 15 days
J-L-M-N = 18 days 2
Ass L (10)
J (2) oe s e mb
Can le C
r der ano
es
O
A (3) C (6) E (4) M (4) N (2)
1 3 5 9 10 11
Prep Dock Install Pilings Build Dock Finish Open for
Site Landscape Business

B (4)
Prep te
Hut S

G (2) Hut
o
are

rT
i

we

of
Po Paint
4
Ro
J (2) K (4) Hut
D (3)
Hut F (3) H (2)
Foundation 6 7 8
Frame Hut Side Hut

37
Opermgt 345 Shannon January, 2001
Critical Path

The Critical Path is the Longest Path


Through the Network.

38
Opermgt 345 Shannon January, 2001
Paths:
Network Diagram Canoe Example
A-C-E-M-N = 19 days
B-D-F-H-K-M-N = 22 days
Critical Path
B-D-F-J-M-N = 18 days
B-D-G-M-N = 15 days
J-L-M-N = 18 days
2
Ass L (10)
J (2) oe s e mb
Can le C
r der ano
es
O
A (3) C (6) E (4) M (4) N (2)
1 3 5 9 10 11
Prep Dock Install Pilings Build Dock Finish Open for
Site Landscape Business

B (4)
Prep te
Hut S

G (2) Hut
o
are

rT
i

we

of
Po Paint
4
Ro
I (2) K (4) Hut
D (3)
Hut F (3) H (2)
Foundation 6 7 8
Frame Hut Side Hut

39
Opermgt 345 Shannon January, 2001
Completed
Task Timetable
Task Description Immediate Predecessor Time ES LS EF LF

A Prepare Dock Site - 3d 0 3 3 6


B Prepare Hut Site - 4d 0 0 4 4
C Install Dock Pilings A 6d 3 6 9 12
D Foundation for Hut B 3d 4 4 7 7
E Build Dock C 4d 9 12 13 16
F Frame Hut D 3d 7 7 10 10
G Power to Hut D 2d 7 14 9 16
H Side the Hut F 2d 10 10 12 12
I Roof the Hut F 3d 10 13 13 16
J Order Canoes and Receive Canoes - 2d 0 4 2 6
K Paint Hut H 4d 12 12 16 16
L Assemble Canoes J 10 d 2 6 12 16
M Finish Landscaping L,I,K,E,G 4d 16 16 20 20
N Open for Business M 2d 20 20 22 22

40
Opermgt 345 Shannon January, 2001
Slack Time

Total Slack = The length of time an activity can be


delayed without affecting the project
completion time.

Total Slack = Late Start - Early Start


For Critical
Activities
Total Slack = Late Finish - Early Finish

Free Slack = The time a task can be delayed without


delaying another task. 41
Opermgt 345 Shannon January, 2001
Slack Time
Task Description Immediate Predecessor Time ES LS EF LF Slack

A Prepare Dock Site - 3d 0 3 3 6 3


B Prepare Hut Site - 4d 0 0 4 4 0
C Install Dock Pilings A 6d 3 6 9 12 3
D Foundation for Hut B 3d 4 4 7 7 0
E Build Dock C 4d 9 12 13 16 3
F Frame Hut D 3d 7 7 10 10 0
G Power to Hut D 2d 7 14 9 16 7
H Side the Hut F 2d 10 10 12 12 0
I Roof the Hut F 3d 10 13 13 16 3
J Order Canoes and Receive Canoes - 2d 0 4 2 6 4
K Paint Hut H 4d 12 12 16 16 0
L Assemble Canoes J 10 d 2 6 12 16 4
M Finish Landscaping L,I,K,E,G 4d 16 16 20 20 0
N Open for Business M 2d 20 20 22 22 0

42
Opermgt 345 Shannon January, 2001
Critical Path Tasks

Critical Path = All tasks with slack = zero

43
Opermgt 345 Shannon January, 2001
Critical Path Tasks
Task Description Immediate Predecessor Time ES LS EF LF Slack

A Prepare Dock Site - 3d 0 3 3 6 3


B Prepare Hut Site - 4d 0 0 4 4 0 ***
C Install Dock Pilings A 6d 3 6 9 12 3
D Foundation for Hut B 3d 4 4 7 7 0 ***
E Build Dock C 4d 9 12 13 16 3
F Frame Hut D 3d 7 7 10 10 0 ***
G Power to Hut D 2d 7 14 9 16 7
H Side the Hut F 2d 10 10 12 12 0 ***
I Roof the Hut F 3d 10 13 13 16 3
J Order Canoes and Receive Canoes - 2d 0 4 2 6 4
K Paint Hut H 4d 12 12 16 16 0 ***
L Assemble Canoes J 10 d 2 6 12 16
M Finish Landscaping L,I,K,E,G 4d 16 16 20 20 0 ***
N Open for Business M 2d 20 20 22 22 0 ***

Critical Path = B - D - F - H - K - M - N