Professional Documents
Culture Documents
Outline
GLOBAL COMPANY PROFILE: BECHTEL GROUP THE IMPORTANCE OF PROJECT MANAGEMENT PROJECT PLANNING
The Project Manager Work Breakdown Structure
Outline - Continued
PROJECT MANAGEMENT TECHNIQUES: PERT AND CPM
The Framework of PERT and CPM Network Diagrams and Approaches Activity on Node Example Determining the Project Schedule
Forward Pass Backward Pass Calculating Slack Time and Identifying the Critical Path(s)
Outline - Continued
Variability in Activity Times
Three Time Estimates in PERT Probability of Project Completion
Learning Objectives
When you complete this chapter, you should be able to : Identify or Define:
Work breakdown structure Critical path AOA and AON Networks Forward and Backward Passes Variability in Activity Times
5
Bechtel
Asked by Kuwait to begin rebuilding after Desert Storm 650 wells ablaze, others uncapped No water, electricity, food or facilities Land mines! Bombs! Grenades! Many fires inaccessible because of oilcovered roads
7
Bechtel
Project required:
Storage, docking, and warehousing facilities at Dubai 125,000 tons of equipment and supplies 150 kilometers of pipeline capable of delivering 20,000,000 gallons of water per day to the fire site more than 200 lagoons with 1,000,000 gals of seawater
8
10
Project Characteristics
Single unit Many related activities Difficult production planning and inventory control General purpose equipment High labor skills
13
An Example
Building construction
14
An Example
Research project
15
20
Project Planning
Establishing objectives Defining project Creating work breakdown structure Determining resources Forming organization
21
Project Organization
Often temporary structure Uses specialists from entire company Headed by project manager
Coordinates activities Monitors schedule & costs
Eng. Acct.
Eng. Mkt.
Mgr.
1995 Corel Corp.
22
Sales
Finance
Engineering
Production
Project 1
Project 2
23
Sales
Finance
Engineering
Production
Project 1
Project Manager Propulsion Engineer Project Manager Structural Engineer Inspection Technician Technician Test Engineer Technician
Project 2
24
Matrix Organization
Mkt Project 1 Project 2 Project 3 Project 4
25
Oper
Eng
Fin
Resources
27
Project Scheduling
Identifying precedence relationships Sequencing activities Determining activity times & costs Estimating material & worker requirements Determining critical activities
1995 Corel Corp.
28
30
Gantt Chart
Activity Design Build Test Time Period J F M A M J J
31
32
Consider precedence relationships and interdependencies Each uses a different estimate of activity 34 times
37
39
Dummy Activity
H Inspect/Test
3 Pour concrete/ 5
Install frame
40
41
EF = ES + Activity time
EF is earliest finish
LS = LF - Activity time
LS is latest start
ES
EF
Earliest Finish
LS Activity Duration
LF
Latest Finish
44
45
0 H 0 Start 0 0 0 Start
H 13 H 15 15 13 2 Slack=0
B B 0 H 3 4 1 3 Slack=1
DD 3 H 7 8 4 4 Slack=1
46
1 1 1 1 2 3 4 5 6 7 8 9 0 1 2
Project Times
Expected project time (T) to obtain Used
Sum of critical path activity times, tof project probability
completion!
51
52
s =5
sZ = 1
T = 40 50
mz = 0 2.0
Z
53
sZ =1
.97725
mz = 0 2.0
Probabilities in body
Z
54
55
Using current If there is only one critical path, then select the activity on this critical path that (a) can still be crashed, and (b) has the smallest crash cost per period. Note that a single activity may be common to more than one critical path Update all activity times.
57
58
59
Advantages of PERT/CPM
Especially useful when scheduling and controlling large projects. Straightforward concept and not mathematically complex. Graphical networks aid perception of relationships among project activities. Critical path & slack time analyses help pinpoint activities that need to be closely watched. Project documentation and graphics point out who is responsible for various activities. Applicable to a wide variety of projects. Useful in monitoring schedules and costs.
60
Limitations of PERT/CPM
Assumes clearly defined, independent, & stable activities Specified precedence relationships Activity times (PERT) follow beta distribution Subjective time estimates Over-emphasis on critical path
61