The Committee would like to thank the following individuals for their contributions to this document:
Bill Druin, Mark Gilligan, Angela Jones, Chris Kavalaris, Kiran Mohanraj, Eric Swenson
December 2010
The California Council of Testing and Inspection Agencies (CCTIA) roots go back to approximately 1970 when several San Francisco Bay Area testing and inspection firms (materials engineering laboratories) decided to unite their efforts in an attempt to achieve more uniform guidelines for, and enforcement of, what was then Section 305 of the Uniform Building Code (UBC) dealing with Special Inspection. At that time, the public agencies use and enforcement of code-dictated special inspection varied from zero to total by-the-book requirements. Thus, materials engineering laboratories often faced major uncertainties as to how strictly they must adhere to UBC requirements. This, in turn, created substantial inequities in levels of effort, especially confusing to clients that built in more than one jurisdiction. Early efforts were encouraging enough that the organization, originally formed as the Association of Northern California Testing and Inspection Agencies (ANCTIA) survived many years and achieved substantial progress, as exhibited by the following achievements: Created a Tests and Inspection (T & I) checklist prototype for use on commercial/private construction projects Established inspection guidelines Established criteria for issuance of inspector identification cards, signed by Professional Engineers, and listing individuals areas of expertise. After some time, activities slowed down only to be revived again about 1987, for most of the same reasons that resulted in the original formation, i.e., lack of uniform use and enforcement of special inspection code requirements. This time ANCTIA became even more proactive, with such projects as: Updated the T & I checklist Established minimum standards for member firms Revised minimum standards for inspectors Promoted the active use of inspector identification cards Interacted with ICC (formerly ICBO) and local building officials
i
The organization subsequently grew to represent the industry throughout the State of California. In 1994, it reorganized as the California Council of Testing and Inspection Agencies (CCTIA). As with its predecessor, CCTIA is a non-profit public benefit corporation dedicated to fostering, promoting, and encouraging through education the practice and profession of materials testing and inspection services. The Council influences code development, training programs, and minimum inspector and agency qualification standards through its member firms representation in many other organizations, including: International Code Council (ICC) (including various Chapters throughout the State of California) International Accreditation Services (IAS) Structural Engineers Association of California (SEAOC) American Council of Independent Laboratories (ACIL) American Concrete Institute (ACI) American Construction Inspectors Association (ACIA) American Society for Testing and Materials (ASTM) ASTM E36 Committee on Laboratory Accreditation American Society of Foundation Engineers (ASFE) American Society of Civil Engineers (ASCE) California Division of State Architect (DSA) In its efforts to promote public safety, the Council participates in and supports many more organizations, too numerous to include within this document. Questions and inquiries concerning CCTIA membership may be made by contacting any member firm.
INTRODUCTION
Guidelines for Special Inspection in Construction has been prepared by the member firms of the California Council of Testing and Inspection Agencies (CCTIA) Standard of Practice Committee to illustrate the services available in some of the more common categories of special inspection and testing. The Guideline has been revised to bring it in compliance with the 2007 California Building Code. The model Guidelines of Special Inspection and Structural Observation, published by Structural Engineers Association of Northern California, was used with their permission as a reference to assist in the development of this Guide. A basic objective of this Council (CCTIA) is to provide information that will assist clients to better understand the relationship between testing and inspection agencies (materials engineering laboratories) and specific requirements of the various building codes. Of particular importance is the capability of such agencies to satisfy the Special Inspection requirements of the California Building Code, other local codes, and the typical requirements of project specifications. The guidelines are not meant to imply that all of these services will be required on any specific project, or that the agency has been directed to perform all of the available services within a category. It is also recognized that special requirements of specific projects or governing agencies may require more or less stringent procedures than those outlined in these guidelines. Inspection is the observation of construction for general conformance with the approved design drawings and specifications. It should not be relied upon by others as acceptance or as guarantee of work, nor should it in any manner relieve any contractor, or any other party, from their obligations and responsibilities under either the construction contract or generally accepted industry custom. It is important to note that qualified materials engineering laboratories may provide testing, inspection and materials engineering services in many fields other than those selected for this publication. In addition, a qualified laboratory should comply with state and local auditing and/or accreditation criteria.
ii
SOILS (Grading, Excavation, and Filling) FOUNDATIONS (Piles and Piers) ASPHALT CONCRETE (Hot Mix Asphalt and Rubberized Hot Mix Asphalt) REINFORCING STEEL CONCRETE BATCH PLANT CONCRETE SHOTCRETE PRE-TENSIONED CONCRETE POST-TENSIONED CONCRETE MASONRY STRUCTURAL STEEL HIGH STRENGTH BOLTING NONDESTRUCTIVE TESTING (NDT) FIRE-RESISTANT MATERIALS (Sprayed and Mastic & Intumescent) GLU LAM AND TRUSS JOISTS POST INSTALLED ANCHORS AND DOWELS (Installation and Proof Load Testing) SHEAR WALLS AND FLOOR SYSTEMS USED AS HIGH LOAD DIAPHRAGMS GUIDELINES FOR ISSUING IDENTIFICATION CARDS FOR SPECIAL INSPECTORS STATEMENT OF SPECIAL INSPECTIONS SCHEDULE OF SPECIAL INSPECTION SCHEDULE OF STRUCTURAL TESTING
1 2 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 20 24 27 34
iii
C. Testing 1 . Determine capacities of test piles and conduct additional load tests, as required (CBC Table 1704.8). D. Reports 1 . Submit written progress reports describing the tests and observations made and showing the action taken to correct nonconforming work.
B. Verification 1 . Observe drilling operations and maintain complete and accurate records for each pier. 2 . Verify locations of piers and their plumbness. Confirm pier diameters, bell diameters (if applicable), lengths, log of soil types embedment into bedrock (if applicable), and adequate end strata bearing capacity. 3. For concrete piers, perform additional inspections in accordance with Section 1704.4. 4 . For masonry piers, perform additional inspections in accordance with Section 1704.5. C. Sampling of Materials 1. Obtain samples of soil and rock if required by the geotechnical engineer of record for confirmation of classification or strength testing. D. Testing 1 . Perform testing of continuity of pier defects using geophysical methods if required by design professionals. E. Reports 1 . Submit written progress reports describing the tests and observations made and showing the action taken to correct nonconforming work.
SECTION 3
ASPHALT CONCRETE
OBJECTIVE The performance of Hot Mix Asphalt (HMA) and Rubberized Hot Mix Asphalt (RHMA) pavement is as much affected by the careful construction of the subgrade and base as it is by the control of the mix itself. Therefore, the paving inspector must also be knowledgeable in soils. The purpose of observation and testing of HMA and RHMA paving is to verify that paving contractors and their suppliers are exercising adequate quality control in their operations and are providing a finished product that complies with the project plans and specification requirements. This is also to be accompanied by adequate sampling of HMA and RHMA for acceptance testing in accordance with the Quality Assurance Plan. This objective can best be achieved by qualified special inspectors performing the following duties under the direct supervision of the materials engineering laboratory. OBSERVATION DUTIES A. Documents 1. Review the approved plans and specifications, and meet with contractor and suppliers before construction to discuss project and to verify that requirements for testing and observation are well understood. 2. Review material certificates and test reports for compliance with job specifications. 3. Review Job Mix Formula (JMF) submittals for compliance to project requirements. B. Sampling of Materials 1. Sample and perform preliminary tests on proposed aggregates and asphalt cement (virgin asphalt cement, Rubberized Asphalt Binder, or Asphalt Rubber Binder) to verify JMF (gradation, sand equivalent, abrasion, air voids, etc.) C. Subgrade and Base 1. Confirm that sources of materials have been sampled and approved. 2. Verify that materials delivered are of uniform quality. 3. Verify that control testing of subgrade materials is being performed and recorded as required. 4. Verify that subbase and base courses are of the source, type, thickness and density specified. 5. Verify that soil stabilization is provided, if required. 6. Refer to Section 1, Earthwork, for additional details. D. Plant (Drum Mix or Batch) 1. The inspector should become familiar with the appearance and physical characteristics of the mix to be used by observing visually the finished mixture so that unsatisfactory conditions may be readily recognized. 2. Check the plant facilities prior to production of HMA or RHMA. 3. Check aggregates in stockpile to verify conformance to materials utilized in the design. 4. Check the temperature and weights of the aggregate fractions and asphalt cement. Check the mixing temperature and the temperature of the mixed batches on the truck. 6. Conduct sampling of the asphalt cement and blended aggregates (and RAP, if any) to verify the (cold feed or hot-bins, whichever is applicable) job mix formula is within tolerance. 7. Before loading, truck beds should be checked for cleanliness and absence of materials that might be detrimental to the mix (such as cleaning solvents). Ensure the trucks are tarped after loading. 8. Coordinate with the job site inspector to obtain a uniform and consistent HMA. E. Spreading and Paving 1. The field inspector should contact the plant inspector promptly should the observed conditions during placement and spreading operations suggest a need for change at the plant. The following items should be addressed prior to and during placement operations: a) Area to be paved, cleaned, crack sealed and properly primed, or tack coated. b) Leveling course installed where required. c) Suitability of spreading and paving equipment. d) Ambient and Base temperature to be noted. e) Mix temperature when delivered, during placement, and after final rolling is within limits required. f) Density tests by nuclear gauge during rolling (when applicable). g) Thickness control by adequate placement and compaction. h) Sampling of HMA or RHMA at jobsite during placement for laboratory testing (asphalt content, air voids, etc.). i) Core samples taken for verification of thickness and in-place density of the mat. j) Application of seal coat and curing in accordance with specification requirements, if required. F. Verification Tests 1. Stability and air voids. 2. Asphalt content and gradation by extraction (solvent or ignition oven). 3. Physical properties of the asphalt cement: penetration, viscosity, softening point, resilience, ductility, and specific gravity (when applicable). 4. Aggregate quality: gradation, LA abrasion, and equivalent, fractured faces, uncompacted voids, etc. 5. Thickness and Field density of core samples. 6. Smoothness tolerance. G. Reports 1. Submit written reports describing the observations made and showing the action taken to correct nonconforming work. Itemize any changes authorized by architect/engineer. Report all deviations from plans o r specifications. 5.
SECTION 6 CONCRETE
OBJECTIVE Many factors interact to affect the ultimate quality of concrete. To deal properly with these factors, quality assurance is divided into two recognized phases. The first involves collecting evidence from standard tests to verify that the delivered concrete was produced to the standards specified. The second involves verifying that proper construction practices are followed during placement, finishing, and curing. The Statement of Special Inspections, prepared by the responsible design professional, will define the special inspection task(s) required. Qualified special inspectors who diligently perform the duties listed below while under the direct supervision of the materials engineering laboratory can best achieve this objective. OBSERVATION DUTIES A. Documents 1. Review the approved plans and specifications. 2. Verify that the class of concrete ordered is being delivered and conforms to specifications, drawings, and/or code requirements and approved mix design. B. Observation Procedures 1. Verify formwork is of proper size and shape. 2 . Verify that the location and preparation of construction joints comply to approved plans, specifications, and building code requirements. 3. Check forms for cleanliness and proper treatment prior to placement. 4 . Visually estimate the slump of each batch delivered and perform slump tests regularly. 5 . Determine concrete temperature, number of mixing revolutions, and/or length of time since batching. 6 . Observe placement procedures for evidence of segregation, possible cold joints, displacement of reinforcing or forms, and proper support of embedded items, anchor bolts, etc. 7 .O b s e r v e methods used for compaction/consolidation. 8. When specified, verify that concrete is protected from temperature extremes, and that proper curing is initiated. 9 . When specified, verify maintenance of cure temperature and techniques. C. Sampling and Testing Duties 1. Sample and test fresh concrete for the following (or as stipulated by plans and specifications): a) Slump b) Temperature c) Entrained air, when required d) Wet unit weight, when required 2 . Sample concrete and prepare test cylinders in accordance with ASTM C31. 3. Field sampling and testing of concrete should be performed by a qualified technician, certified by ACI as a Concrete Field Testing Technician Grade 1 (or approved equal) D. Reports 1 . Submit written progress reports describing the tests and observations made and showing the action taken to correct nonconforming work. Itemize any changes authorized by architect/engineer. Report all uncorrected deviations from plans or specifications.
SECTION 7 SHOTCRETE
OBJECTIVE The purpose of special observation for shotcrete is to verify that the materials, processes, and the particularly unique application techniques conform to the project documents. The process moves rapidly in often noisy and congested environments; it relies heavily on experienced working crews. The Statement of Special Inspections, prepared by the responsible design professional, will define the special inspection task(s) required. Qualified special inspectors who diligently perform the duties listed below while under the direct supervision of the materials engineering laboratory can best achieve this objective. OBSERVATION DUTIES A. Documents 1 . Review the approved plans, specifications, and contractor submittals for applications process used. 2. Verify crew qualifications. 3 . Verify material sources and approved mix design. 4. Verify test methods and sample procedure. B. Observation Procedures 1 . Verify main and auxiliary equipment for compliance, capacity, pressures, and proper functioning. 2 . Check for hot or cold weather limitations and precautions. 3. Verify reinforcing is proper type, grade, and size; free of oil, dirt, and rust; properly coated and/or sheathed as specified; located within acceptable tolerances and adequately supported; and will allow for minimum shotcrete cover. 4 . Verify that placement of reinforcing steel (or ducts) complies with spacing, profile, and quantity requirements. 5 . Verify hooks, bends, ties, stirrups, and supplemental reinforcement are fabricated and placed as specified. 6. Verify required non-contact lap lengths. 7 . Verify proper installation of approved mechanical connections and/or bolts. 8. Ensure all welds of reinforcing steel and other weldments are as specified and have been inspected and approved by welding inspector. 9 . Verify formwork is proper size and shape; location of all construction joints; and penetrations and embeds are correct and adequately supported. 10. Check for ground wires or other thickness gauging control method. 11. Verify the nozzleman has suitable shooting positions and access to achieve placement with minimal rebound. 12. Review mixing and placing procedures with crew before commencement of application. 13. Verify that batch tickets indicate delivery of the approved mix as specified. 14. Observe placement for: a) Consistency b) Consolidation c) Coverage d) Rebound e) Finish 15. Check completed job for defects and corrective action. 16. Verify protection from temperature extremes and determine proper curing is initiated. C. Sampling and Testing 1. Determine required type, quantity, and frequency of tests on fresh and hardened shotcrete. 2 . When required, observe preparation of preconstruction test panel(s), simulating job conditions as closely as possible. The panel(s) thickness and reinforcing should represent: a ) Most congested area specified in the structural design. b) Shot at the same angle, using the same nozzleman, and with the same mix design that will be used. c ) Same equipment to be used during construction, unless substitution has been approved by the Building Official. 3. During construction, observe preparation of a test panel (either 18 x 18 or 12 x 12 based on aggregate size), or as otherwise specified, to obtain suitable cores for testing. Arrange correct positioning of sample panel to represent job shotcrete. Prearrange with nozzleman the correct timing of the test sample preparation and verify that it is representative of job placement, finish, and cure. Refer to ACI 506 for further guidance. 4 . Strength testing requires not less than three specimens from each panel. Specimens shall be either 3 diameter cores or 3 cubes when maximum-size aggregate is larger than 3/8. Specimens shall be at least 2 diameter cores or 2 cubes when maximum-size aggregate is 3/8 or smaller. 5. Mark panel with specimen identification, protect for curing period, and arrange for transportation to the testing laboratory. D. Reports 1 . Submit written progress reports describing the tests and observations made and showing the action taken to correct nonconforming work. Itemize any changes authorized by architect/engineer. Report all uncorrected deviations from plans or specifications.
10
SECTION 10 MASONRY
OBJECTIVE The purpose of special observation (level 1 or 2) for masonry is to verify that the workmanship and materials meet the minimum standards required by code and by the approved project plans and specifications. This is particularly difficult in masonry work where so much is dependent upon the capabilities of the individual mason. This requires the inspector to rely on knowledge, experience and judgment while applying the requirements of the applicable code to the particular condition. The Statement of Special Inspections, prepared by the responsible design professional, will define the special inspection task(s) required. Qualified special inspectors who diligently perform the duties listed below while under the direct supervision of the materials engineering laboratory can best achieve this objective. OBSERVATION DUTIES A. Documents 1. Review the approved plans, specifications, and Statement of Special Inspections with the masonry contractor and architects representative in a preconstruction meeting. 2. Verify whether high lift or low lift procedures have been approved and documented for use. B. Mill Test Reports 1 . Verify that mill test certifications for unit masonry, cement, reinforcing steel, and embedded anchors have been furnished by supplier and are acceptable to the architect/engineer. C. Sampling of Materials 1 . Sample and verify that the following materials are delivered to laboratory for testing when required: a) Concrete block or brick b) Aggregates and cement for mortar and grout c) Reinforcing steel as delivered D. Storage of Materials 1. Verify cement, lime, block, and brick are supported on pallets and covered to protect from exposure to excessive moisture or drying. 2 . Verify aggregates for mortar and grout are stored free from contamination and in such a manner as to minimize segregation. 3 . Verify reinforcement, ties, and metal accessories are stored off the ground and in a manner to prevent permanent distortions. E. Preparation for Lay-Up 1. Verify size and spacing of reinforcing dowels. 2 . Verify length of dowel protruding from footing is of sufficient length to allow for the splicing of vertical reinforcing steel as required. 3. Verify that foundation concrete is clean and prepared as required by specifications. F. Lay-Up or Placing of Masonry Units 1. Verify that cleanouts are provided for first course of each pour, if high lift method is used. 2. Verify plumb and lay-up configuration. 3. Verify moisture condition of masonry units. 4 . Verify that proper mortar ingredients and batching techniques are being used and prepare mortar compression test specimens. 5. Verify mortar time on board. Verify that head joints are the same thickness as face shells or that full head joints are used when specified. 7. Verify that mortar extrusions (fins) are cleaned off inside. 8. Verify whether joints are tooled as specified. 9. Verify required frequency of masonry wall prisms and observe construction of same as specified. 10. Observe horizontal and vertical reinforcing steel to verify: a) Reinforcing steel is of specified size and grade. b) Reinforcing steel is located and spliced as specified. c) Lap splices are staggered in bond beams and corners as required. d) Hooks are specified size and bent as required. e ) Ties are specified size, spacing, and bent as required. f) Reinforcing steel is properly secured and minimum clearances are as required. 11. Verify embedded items are: a) Placed at proper location and secured. b) Proper size and clearances are as required. 12. Verify masonry is protected from weather: a ) When ambient or CMU temperature falls below 40F. b) When ambient temperature exceeds 100F or 90F (wind velocity greater than 8 mph). G. Pre-grouting Tasks 1. Verify that cells and starting beds are clean. 2. Verify dowels, anchor bolts, and inserts are all in place, particularly at rooflines, floor lines, and intersecting wall lines. 3. Verify installation of cleanout closures. H. Grouting Observations 1 . Verify grout mix for conformance to approved mix design. 2. Verify slump is in accordance with the specifications. 3. If low lift grouting, verify maximum masonry height is in accordance with the code before grouting. 4. Verify consolidation (mechanical vibrating or puddling) during placement, and later during reconsolidation. 5. Monitor time since batching of grout. 6. Monitor flow of grout throughout wall and each grout pour height for conformance to specifications. 7 . Preparation of any required grout specimens and/or prisms shall be observed. Note mortar specimens are no longer required. 8 . Verify grout is stopped below top for keying where required. 9. Verify curing requirements are being followed. I. Reports 1. Submit written progress reports describing the tests and observations made and showing the action taken to correct nonconforming work. Itemize any changes authorized by architect/engineer. Report all uncorrected deviations from plans or specifications. 6.
11
13
14
15
16
17
SECTION 17 SHEAR WALLS AND FLOOR SYSTEMS USED AS HIGH LOAD DIAPHRAGMS
OBJECTIVE The California Building Code is now requiring special inspection during the construction of the wood structural panel sheathing (plywood) shear walls and floor systems used as high load (shear) diaphragms. These are critically important elements to the structural integrity of the building, and are therefore considered appropriate for special inspection. This guideline is intended for use in site-built structural wood assemblies. Prefabricated wood structural elements and assemblies require special inspection as specified in CBC Section 1704.2. The Statement of Special Inspections, prepared by the responsible design professional, will define the special inspection task(s) required. Qualified special inspectors who diligently perform the duties listed below while under the direct supervision of the materials engineering laboratory can best achieve this objective. OBSERVATION DUTIES A. Documents 1 . Review the approved plans, specifications, and other appropriate project documents. 2. Review applicable sections of referenced codes and standards, particularly the Timber Construction Manual by the American Institute of Timber Construction (AITC) and the California Building Code (CBC). B. Materials 1. Verify material grades. 2. Verify nail type and size. C. Sampling of Materials 1. Sample and deliver to the laboratory for testing the following materials when required by project specifications: a ) Structural panel sheathing (i.e., plywood, gypsum, fiberboard, or particleboard) b) Framing lumber c ) Fasteners used in attaching the sheathing including nails and screws. E. Observation Procedures 1 . Check nail spacing, penetration, and edge distance, and verify nail size. 2. Check for proper plywood thickness and grade. 3. Check for installation of blocking, when blocked edges are required. 4. Check the receiving members for spacing, size, and resistance to splitting. 5 . Check for proper plywood layout per project requirements. 6. Check for shiners (nails penetrating structural panel sheathing only). 7 . Verify that critical members have received the nail specified. F. Gluing Operations 1. Materials a ) Verify certifications on lumber grading, adhesives, and preservatives. b) Verify lumber grade marks on the pieces being used. 2. Observation Requirements - Preliminary a) Verify that spacing of joints meets job and code requirements. b) Measure moisture content of lumber and verify with acceptance range specified. c) Check appearance grade requirements. d) Verify preservative treatment requirements. 3. Observation of Sub-Assemblies a) Verify lumber grade at end joints. b) Gluing and curing procedure, verification of following: Lumber moisture, temperature, and crosssection Workroom humidity and temperature Adhesive certification, lot, and temperature Joint match and separation Assembly temperature, pressure, and time 4. Laminating (Gluing) a ) Recheck lumber grades, combinations and faces, moisture, and temperature. b) Record workroom temperature and humidity. c ) Adhesive certification, lot verification, and temperature. d) Gluing and curing: Observe glue spread and check for skips. Record open time prior to clamping. Record clamping pressure. Record curing temperature and time. G. Reports 1 . Submit written progress reports describing the tests and observations made and showing the action taken to correct nonconforming work. Itemize any changes authorized by architect/engineer. Report all uncorrected deviations from plans or specifications.
18
19
designated persons. All discrepancies shall be brought to the immediate attention of the contractor for correction; then, if uncorrected, to the proper design authority and to the building official. 6. Special Inspector shall report whether the work requiring special inspection was, to the best of his/her knowledge, in conformance with the approved plans and specifications and the applicable workmanship provision of CBC. 7 . Special inspection shall not be relied upon by others as acceptance of work, nor shall it in any manner relieve any contractor, or any other party, from their obligations and responsibilities under the construction contract, or generally accepted industry custom. B. Experience 1 . In order for experience to count toward qualification, it must be based on verifiable work directly related to the category or type of inspection involved. 2. An engineering degree (BS) plus appropriate inhouse training may be substituted for not more than one year of experience. An engineering technology degree (AA) plus appropriate inhouse training may be substituted for not more than six months experience. 3 . Five or more years experience as a qualified Special Inspector in one or more categories of work may fulfill up to half of the experience requirements in any category, at the discretion of the Responsible Professional Engineer. C. Certification 1. Certification, when specified, is intended to mean successful completion of an examination appropriate to the category of work involved and in accordance with the requirements of the certifying agency. D. Special Inspector in Training 1. The intent of this provision is to provide practical opportunities for an inspector to gain the needed experience to qualify as a Special Inspector. 2 . An inspector who does not meet the qualifications for Special Inspector may be allowed to perform Special Inspection, at the discretion of the Responsible Professional Engineer, provided one or more of the following conditions are met: a ) Individual is working under direct and continuous supervision of a Special Inspector fully qualified for the type of work involved.
b) Individual is working under indirect or periodic supervision of a Special Inspector and the scope of work is minor and/or routine and within the capabilities of the individual.
17. Field Sampling and Field Testing in Any Category a) Minimum three months experience, b) Certification by ACI (Field Tech Grade 1 required for concrete. 18. Special Inspector in Training a) In training for experience, and b) No certifications required. F. Reference Abbreviations & Recognized Certifying Agencies 1. AA Associate of Arts 2. AASHTO American Association of State Highway and Transportation Officials 3. ACI American Concrete Institute 4. ACIA American Construction Inspectors Association 5. ASTM American Society for Testing and Materials 6. ASNT American Society for Nondestructive Testing 7. AWS/ACWI American Welding Society/Associate Certified Welding Inspector 8. AWS/CWI American Welding Society/Certified Welding Inspector 9. BS Bachelor of Science 10. CBC California Building Code 11. DSA Division of the State Architect 12. IAS International Accreditation Service 13. ICC International Code Council 14. NICET National Institute for Certification of Engineering Technologists 15. NRCA National Roofing Contractors Association 16. OSHPD Office of Statewide Health Planning and Development 17. PCI Precast Concrete Institute 18. PTI Post-Tensioning Institute
SAMPLE ID CARD
Front
EMPLOYEE IDENTIFICATION CARD Company Logo Control No. This is to certify that
Member of CCTIA
is duly qualified to perform the duties of special inspector as indicated on the reverse side of this card. Issued date or Expiration date:
Employees Photo
Authorized Professional Engineers Signature Company Address/Phone
Back
CONCRETE Reinforcing/Embeds Placement Batch Plant Prestressing Ductile Moment Shotcrete Proofloading Anchor Post-Installed Anchor Sample/Test MASONRY Reinforcing Placement/Grouting Sample/Test ASPHALT CONCRETE Placement Batch Plant Sample/Test ROOFING Placement Sample/Test OTHER (specify) STRUCTURAL STEEL Fabrication/Erection Visual Welding High Strength Bolting Sample/Test Nondestructive Testing
MT PT UT RT
Back (simplified)
ICC
_____RC_____PC_____SM_____SSW_____HSB_____FP
AWS___________CWI_____________
FIREPROOFING Placement Sample/Test STRUCTURAL WOOD Plant Fabrication Truss Joist Fabrication Glu Lam Fabrication Shear Diaphragms Sample/Test SOILS Excavation, Grading, Piling Drilled Piers, Caissons Pile Placement Nuclear Density Sample/Test
NDT
_____MT_____UT_____RT_____DP_____AWS/CWI _____ DSA Mas _____ DSA Shot _____ Fire/Life Safety _____ CalTrans _____ Haz/Mat _____ ICC E/M/P _____ ICC Bldg. _____ Nuc. Gauge
NOTE: On the line to the left, mark applicable special inspection and/or testing items based on the employees conformance with the experience and certification criteria noted above. An X should be used to indicate the employee is qualified; SIIT should be used to indicate in-training status. The ID Card format is only a sample and is not intended to be mandatory.
22
23
STATEMENT
OF
SPECIAL INSPECTIONS
AND
24
Owner
Building Official
Signature
Date
Signature
Date
To Be Determined
2. Material Testing
To Be Determined
3. Geotechnical Inspections
To Be Determined
4.
To Be Determined
Seismic Requirements
(Section 1705.3.1)
Description of seismic-force-resisting system and designated seismic systems subject to special inspections as per Section 1705.3:
The extent of the seismic-force-resisting system is defined in more detail in the construction documents.
Wind Requirements
(Section 1705.4.1)
Description of main wind-force-resisting system and designated wind resisting components subject to special inspections in accordance with Section 1705.4.2:
The extent of the main wind-force-resisting system and wind resisting components is defined in more detail in the construction documents.
Is placed in the appropriate column to denote either C continuous or P periodic inspections. Denotes an activity tha t is either a one-time activity or one whose frequency is defined in some other manner.
Additional detail regarding inspections and tests are provided in the project specifications or notes on the drawings.
C
---
P
---
Notes
X ---
X X ---
-------
-------
X X X X
P
X X
Notes
X X X
X X X
X --X ---
X X
X X
X X X X
P
X
Notes
X X X X X
X X
X X X
X X
X X X
X X X
P
X
Notes
X X
X X X X X
X X X
X X
---
---
---------
---------
X X X
C
X
Notes
X X X X
-----
-----
---
---
X X
---
---
---
--X
---
---
C
---
P
---
Notes
-----------
-----------
---
---
-------
-------
---
---
-----
-----
X X
X X
P
X
Notes
X X
X X
X X X
X X -----
-----
----X
-----
-----
-------
-------
Test
Structural Steel 1. Non-destructive testing of weld s (CBC Section 1708.4, AISC 341 Appendix Q, AWS D1.1): a. Ultrasonic testing (UT) b. Magnetic particle testing (MT) 2. Ultrasonic testing of base metal greater than 1.5 inches in thickness (CBC Section 1708.4) 3. Coupon tests for material v erification of unidentified steel (CBC Section 2203): a. Structural steel sections b. High-strength bolts b. Welded studs 4. Special moment-resisting frame connections that are not prequalified per AISC (AISC 341 Appendix S). Concrete & Shotcrete 1. Compressive tests of specimens taken during concrete placement (CBC Section 1905.6, ACI 318 Section 5.6). 2. Shrinkage tests of specimens taken during concrete placement. 3. Shotcrete preconstruction test panels (CBC Section 1913.5). 4. Shotcrete core specimens taken from production test panels (CBC Section 1913.10). 5. Chemical tests of ASTM A615 reinforcing bars that are to be welded. (CBC Table 1704.3, Item 5.b.1) 6. Tension/torque testing of post-installed anchors in concrete. Masonry 1. Test masonry units to verify compressive strength fm (CBC Section 2105.2). 2. Compressive tests of grout and mortar specimens taken during placement(CBC Section 2105.2) . 3. Test masonry prisms (CBC Section 2105.3). 4. Chemical tests of ASTM A615 reinforcing bars that are to be welded. (CBC Table 1704.3, Item 5.b.1) 5. Testing of unidentified reinforcing steel (CBC Section 2103.13.8).
Notes
Test
6. Tension/torque testing of post-installed anchors in masonry. Soils 1. Perform classification and testing of controlled fill materials (CBC Table 1704.7). Pile Foundations 1. Determine capacities of test piles and conduct additional load tests, as required (CBC Table 1704.8).
Notes
36
37
Additional copies of the Guideline may be requested at no cost from any CCTIA member agency