Professional Documents
Culture Documents
COST LIMIT
(PRE AND POST CONTRACT)
INTRODUCTION
2
Maximum expenditure. Is a statement of the limit of cost for clearly defined client requirement beyond which a client is not prepared to enter into a building contract. It is that part of the clients brief which having specified the quantity of the requirement, direct the architect to obtain an acceptable tender within the limit of certain sum money.
2
INTRIDUCTION (CONTD)
3
The cost limit will be very much influenced by:i) The floor space required ii) The standard of accommodation iii) The function of the building / use iv) Either client type:Client prescribed accommodation requirement but unaware of cost implication Client determines both the accommodation requirement and cost limit through past experience Client prescribed a cost limit, design team to produced standard accommodation that can be provided for this sum
3
a)
b)
c)
1.
Financial method Developer equation. Established by means of the developer budget. Is depends on the finance available for the project. This method is used only in the private sector where profit making is the sole motive of any development and this consideration determines the permissible cost of a building
4
2.
Interpolation method Comparison with cost of similar buildings by cost/m2 GFA adjusted for space, standard and use. Assessed from a comparative study of known costs of similar building.
No. of Buildings
Common range
Cost/m2 GFA
Result: GFA
PROCEDURE OF INTERPOLATION METHOD (CONTD) closest to proposed building in QUALITY. Select/choose ONE cost analysis
Isolate major difference between proposed building and cost analysis chosen. Difference: GFA Tender date Items shown in analysis but NOT REQUIRED in proposed building Item REQUIRED in proposed building but not provided in cost analysis Significant differences in preliminaries and contingencies.
1. 2. 3. 4. 5.
1.
A range of Cost analysis of the same type of building as the proposed building is assembled. This range is examined to find the cost analysis of the building whose quality approximates most closely to that desired by the client. The initial brief of the proposed building and all of the information given in the cost analysis are studied in order to isolate the major differences between the two building. Allowances are made for each of these major differences (including, of course, differences in floor area and general market level). Finally, an allowance is made as a reserve against price rises between the general market price level at the date of preparation of the first estimate and the contractors price level of the tender.
8
2.
3.
4.
5.
In preparing cost limit and/or outline cost plan, an allowance should be made for unforeseen difficulties, which may come to light later in the design process, and price rises between the preparation of the cost limit and the receipt of tender and between receipt of tender to the completion of project.
1. Design contingencies A percentage allowance should be allowed for changes that can occur for unforeseen problems during the design period and the construction period. Normally a well thought design scheme would carry a small percentage than one where many problems have to be solved by the design team. As the scheme progresses through the various stages of design development, it can be expected that the percentage will fall to reflect the greater certainty of the design decisions.
9
10
11
12
Adjustments of the cost analysis figure by multiplying the appropriate figure by an index. Related to market condition Example: High inflation of 24% per annum Costs are rising at 2% per annum An estimate prepared in January for tender in May will need to add 10% just to cover for inflation.
12
13
An allowance must be made for uncertainties in the proposed design from finished design. Larger % of design needs to be added to cover design risk at inception than at much later stages during design process. % depends on: i) Client ii) Type of project iii) General familiarity of each consultant Almost negligible to some project but at certain circumstances may represent 30 40% of estimates cost.
13
14
Price and design risk is allowed to take account: Type and complexity of design Nature of client Price trends Delay prior to receipt of tenders Percentage adjustments on price and design risk depend on the experience of the designer and the QS familiarity with the cost planning procedure.
14
15
THE END