Sl Qty Description Rate Per Amount

No.
01 36.23 Earth work excavation and depositing on bank within initial 50.00 1 1811.50
m3 lead and initial lift in hard stiff clay, stiff black cotton, hard red m3
earth slabs etc as per Ss 20B & SI 62 for foundation
02 29.28 Sand filling with filling sand including water etc. 322.30 1 9436.94
m3 m3
03 9.88 m3 CC 1:5:10 using 40mm HBGS Metal 1531.42 1 15130.42
m3
04 23.05 R.R. Masonry in CM 1:5 1379.69 1 31801.85
m3 m3
05 22.70 CC 1:4:8 using 40mm HBGS metal 1656.37 1 37599.59
m3 m3
06 18.43 C.C. 1:2:4 using 20mm HBGS metal 2456.63 1 45275.69
m3 m3
07 40.54 Brick work in CM 1:3 1964.61 1 79645.28
m3 m3
08 203.64 Plastering in CM 1:3 113.16 1 23043.90
m2 m2
09 L.S. Provision for inlet & Out let pipes and necessary Gate valves L.S. 500.00

10 L.S. Labour welfare fund 735.00

11 L.S. Unforeseen items L.S. 19.83

Total 2,45,000.00

Sl Description of Work Nos. L B D Contents


No.
01 Earth work excavation and depositing on bank within initial
lead and initial lift in hard stiff clay, stiff black cotton, hard
red earth slabs etc as per Ss 20B & SI 62 for foundation
1x1 36.60 0.90 1.10 36.23m3

02 Sand filling with filling sand including watering etc. for

Foundation 1x1 36.60 0.90 0.20 6.58


Basement 1x1 8.70 8.70 0.30 22.70
29.28 m3
03 CC 1:5:10 using 40mm HBGS metal
1x1 36.60 0.90 0.30 9.88
9.88 m3
04 R.R. Masonry in CM 1:5 for

Ist Footing 1x1 36.60 0.60 0.60 13.17


IInd Footing 1x1 36.60 0.45 0.60 9.88
23.05 m3
05 CC 1:4:8 using 40mm HBGS metal for Basement
1x1 8.70 8.70 0.30 22.70
22.70 m3
06 CC 1:2:4 using 40mm HBGS metal for base slab
1x1 9.60 9.60 0.20 18.43
18.43 m3

07 Brick work in CM 1:3 using II Class Bricks of size 22cm x


11cm x 7.5cm for super structures.
Step-I 1x1 35.20 0.80 1.00 28.16
Step – II 1x1 34.40 0.60 0.60 12.38
40.54 m3
08 Plastering in CM 1:3- 20mm thick for
Step-I
Tank inner side 1x1 32.00 - 1.00 32.00
Tank Outer Side 1x1 38.40 - 1.00 38.40
Top surface of Step-I 1x1 36.60 0.20 - 7.32
Step-II
Tank Inner Side 1x1 32.00 - 0.60 19.20
Outer side 1x1 36.80 - 0.60 22.08
Top face of Tank 1x1 34.40 0.60 - 20.64
Bed Plastering 1x1 8.00 8.00 - 64.00
203.64m2

09 Provision for Inlet and outlet pipes and necessary gate L.S.
valves

10 Unforeseen items L.S.