Daily Progress Report

Project: STO PROJECT Date:


Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Tile Mason 2 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4 Ram Kumar Helper 7:30 AM
Labour/Helper 3 5 Manzoor Helper 7:30 AM
Painter 6 Chotakram Mason 7:30 AM
Driver 7
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 6 13
Equip Ment 14
Pick up 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 0 M3 0.000
Soil 0 M3 0.000
Cement 0 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative

Tiles Installation 17.5 M2 266.8 284.30

CORE Cutting 0 NO's 42 42.00


Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 16.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1.Tiles Installation work in Progress


TODAY ACTIVITY 2.Material Shifting work in progress
3.Grouting and Cleaning work in Progress
1.Tiles Installation work
TOMORROW ACTIVITY 2.Grouting and Cleaning work
3.Material Shifting work
Concern - the bathroom wall needs more pieces of tile cutting due to which its Progress is less.
11/9/2023
16

To
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM

Remarks

Remarks

Grouting and
cleaning - 24 sq.m.
Tile installation
today remains
grouting and
cleaning.
ss is less.
Daily Progress Report
Project: STO PROJECT Date:
Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Tile Mason 2 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4 Ram Kumar Helper 7:30 AM
Labour/Helper 3 5 Manzoor Helper 1:30 AM
Painter 6 Chotakram Mason 7:30 AM
Driver 7
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 6 13
Equip Ment 14
Pick up 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 0 M3 0.000
Soil 0 M3 0.000
Cement 0 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative

Tiles Installation 18 M2 248.8 266.80

CORE Cutting 0 NO's 42 42.00


Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 16.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1.Tiles Installation work in Progress


TODAY ACTIVITY 2.Corner Bead Inshtallation work in progress

1.Tiles Installation work


TOMORROW ACTIVITY 2.Grouting and Cleaning work

Concern -NIL.
10/9/2023
15

To
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM

Remarks

Remarks

Grouting and
Cleaning Work Is
Remain
Daily Progress Report
Project: STO PROJECT Date:
Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Tile Mason 2 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4 Ram Kumar Helper 7:30 AM
Labour/Helper 3 5 Manzoor Helper 7:30 AM
Painter 6 Chotakram Mason 7:30 AM
Driver 7
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 6 13
Equip Ment 14
Pick up 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 0 M3 0.000
Soil 0 M3 0.000
Cement 0 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative

Tiles Installation 22 M2 226.8 248.80

CORE Cutting 0 NO's 42 42.00


Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 16.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1.Tiles Installation work in Progress


TODAY ACTIVITY 2.Grouting and Cleaning work in progress

1.Tiles Installation work


TOMORROW ACTIVITY 2.Grouting and Cleaning work

Concern -NIL.
9/9/2023
14

To
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM

Remarks

Remarks

Grouting and
cleaning - 23 sq.m.
Tile installation
today remains
grouting and
cleaning.
Daily Progress Report
Project: STO PROJECT Date:
Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Tile Mason 2 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4 Ram Kumar Helper 7:30 AM
Labour/Helper 3 5 Manzoor Helper 7:30 AM
Painter 6 Chotakram Mason 7:30 AM
Driver 7
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 6 13
Equip Ment 14
Pick up 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 0 M3 0.000
Soil 0 M3 0.000
Cement 0 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative

Tiles Installation 15 M2 211.8 226.80

CORE Cutting 15 NO's 27 42.00


Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 16.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1.Tiles Installation work in Progress


TODAY ACTIVITY 2.Core Cutting work Is Completed

1.Tiles Installation work


SATURDAY ACTIVITY 2.Grouting and Cleaning work

Concern -NIL.
7/9/2023
13

To
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM

Remarks

Remarks

Grouting and
Cleaning Work Is
Remain
Daily Progress Report
Project: STO PROJECT Date:
Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Tile Mason 2 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4 Ram Kumar Helper 7:30 AM
Labour/Helper 3 5 Manzoor Helper 7:30 AM
Painter 6 Chotakram Mason 7:30 AM
Driver 7
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 6 13
Equip Ment 14
Pick up 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 0 M3 0.000
Soil 0 M3 0.000
Cement 0 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative

Tiles Installation 16 M2 195.8 211.80

CORE Cutting 16 NO's 11 27.00


Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 16.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1.Tiles Installation work in Progress


TODAY ACTIVITY 2.Core Cutting work In Progress

1.Tiles Installation work


TOMORROW ACTIVITY 2.Core Cutting work

Concern -NIL.
6/9/2023
12

To
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM

Remarks

Remarks

Grouting and
Cleaning Work Is
Remain
Daily Progress Report
Project: STO PROJECT Date:
Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Tile Mason 2 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4 Ram Kumar Helper 7:30 AM
Labour/Helper 3 5 Manzoor Helper 7:30 AM
Painter 6 Chotakram Mason 7:30 AM
Driver 7
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 6 13
Equip Ment 14
Pick up 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 0 M3 0.000
Soil 0 M3 0.000
Cement 0 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative

Tiles Installation 20 M2 175.8 195.80

CORE Cutting 11 NO's 11.00


Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 0.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1.Tiles Installation work in Progress


TODAY ACTIVITY 2.Core Cutting work In Progress
3.Material Shifting Work In Progress
1.Tiles Installation work
TOMORROW ACTIVITY 2.Core Cutting work

Concern -NIL.
5/9/2023
11

To
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM

Remarks

Remarks

Grouting and
Cleaning Work Is
Remain
Daily Progress Report
Project: STO PROJECT Date:
Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Tile Mason 2 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4 Ram Kumar Helper 7:30 AM
Labour/Helper 3 5 Manzoor Helper 7:30 AM
Painter 6 Chotakram Mason 7:30 AM
Driver 7
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 6 13
Equip Ment 14
Pick up 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 0 M3 0.000
Soil 0 M3 0.000
Cement 0 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative

Tiles Installation 11.5 M2 164.3 175.80

Back Filling M3 0.00


Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 0.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1.Tiles Installation work in Progress


TODAY ACTIVITY 2.Grouting and Cleaning work In Progress
3.Material Shifting Work In Progress
1.Tiles Installation work
TOMORROW ACTIVITY 2.Grouting and Cleaning work

Concern -NIL.
4/9/2023
10

To
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM

Remarks

Remarks
Grouting and
Cleaning-32 Sq mt.
Daily Progress Report
Project: STO PROJECT Date:
Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Tile Mason 2 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4 Ram Kumar Mason 7:30 AM
Labour/Helper 1 5
Painter 6
Driver 7
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 4 13
Equip Ment 14
Pick up 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 0 M3 0.000
Soil 0 M3 0.000
Cement 0 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative

Tiles Installation 12.5 M2 151.8 164.30

Back Filling M3 0.00


Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 0.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1.Tiles Installation work in Progress


TODAY ACTIVITY 2.Grouting and Cleaning work In Progress

1.Tiles Installation work


TOMORROW ACTIVITY 2.Grouting and Cleaning work

Concern -NIL.
3/9/2023
9

To
5:30 PM
5:30 PM
5:30 PM
5:30 PM

Remarks

Remarks
Grouting and
Cleaning-28 Sq mt.
Daily Progress Report
Project: STO PROJECT Date:
Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Tile Mason 2 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4 Ram Kumar helper 7:30 AM
Labour/Helper 3 5 Chotakram Mason 7:30 AM
Painter 6 Manzoor helper 7:30 AM
Driver 7
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 6 13
Equip Ment 14
Pick up 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 0 M3 0.000
Soil 0 M3 0.000
Cement 25 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative

Tiles Installation 25 M2 126.8 151.80

Back Filling M3 0.00


Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 0.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1.Tiles Installation work in Progress


TODAY ACTIVITY 2.Grouting and Cleaning work In Progress

1.Tiles Installation work


TOMORROW ACTIVITY 2.Grouting and Cleaning work

Concern -NIL.
2/9/2023
8

To
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM

Remarks

Remarks

Grouting and
Cleaning Work Is
Remain
Daily Progress Report
Project: STO PROJECT Date:
Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Tile Mason 2 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4 Ram Kumar helper 7:30 AM
Labour/Helper 4 5 Chotakram Mason 7:30 AM
Painter 6 Muheebullah Helper 7:30 AM
Driver 7 Jay Bhim Helper 7:30 AM
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 7 13
Equip Ment 14
Pick up 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 0 M3 0.000
Soil 0 M3 0.000
Cement 0 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative

Tiles Installation 15 M2 111.8 126.80

Back Filling M3 0.00


Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 0.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1.Tiles Installation work in Progress


TODAY ACTIVITY 2.Grouting and Cleaning work In Progress

1.Tiles Installation work


SATURDAY ACTIVITY 2.Grouting and Cleaning work

Concern -NIL.
31/8/2023
7

To
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM

Remarks

Remarks
Grouting and
Cleaning-40 Sq mt.
Daily Progress Report
Project: STO PROJECT Date:
Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Tile Mason 2 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4 Ram Kumar helper 7:30 AM
Labour/Helper 2 5 Chotakram Mason 7:30 AM
Painter 6
Driver 7
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 5 13
Equip Ment 14
Pick up 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 0 M3 0.000
Soil 0 M3 0.000
Cement 0 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative

Tiles Installation 20 M2 91.8 111.80

Back Filling M3 0.00


Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 0.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1.Tiles Installation work in Progress


TODAY ACTIVITY

1.Tiles Installation work


TOMORROW ACTIVITY 2.Materail Shifting

Concern -NIL.
30/8/2023
6

To
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM

Remarks

Remarks

Grouting and
Cleaning Work Is
Remain
Daily Progress Report
Project: STO PROJECT Date:
Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Tile Mason 2 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4 Ram Kumar helper 7:30 AM
Labour/Helper 2 5 Chotakram Mason 7:30 AM
Painter 6
Driver 7
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 5 13
Equip Ment 14
Pick up 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 0 M3 0.000
Soil 0 M3 0.000
Cement 0 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative

Tiles Installation 23 M2 68.8 91.80

Back Filling M3 0.00


Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 0.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1.Tiles Installation work in Progress


TODAY ACTIVITY

1.Tiles Installation work


TOMORROW ACTIVITY 2.Materail Shifting

Concern -NIL.
29/8/2023
5

To
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM

Remarks

Remarks

Grouting and
Cleaning Work Is
Remain
Daily Progress Report
Project: STO PROJECT Date:
Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Mason 2 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4 Ram Kumar Mason 7:30 AM
Labour/Helper 2 5 Muheebullah Helper 7:30 AM
Painter 6
Driver 7
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 5 13
Equip Ment 14
Pick up 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 0 M3 0.000
Soil 0 M3 0.000
Cement 0 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative

Tiles Installation 22 M2 46.8 68.80

Back Filling M3 0.00


Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 0.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1.Tiles Installation work in Progress


TODAY ACTIVITY 2.Materail Shifting Work in progress

1.Tiles Installation work


TOMORROW ACTIVITY 2.Materail Shifting

Concern -NIL.
28/8/2023
4

To
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM

Remarks

Remarks

Grouting and
Cleaning Work Is
Remain
Daily Progress Report
Project: STO PROJECT Date:
Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Mason 2 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4 Ram Kumar Mason 7:30 AM
Labour/Helper 3 5 Muheebullah Helper 7:30 AM
Painter 6 Jay Bhim Helper 7:30 AM
Driver 7
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 6 13
Equip Ment 14
Pick up 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 0 M3 0.000
Soil 0 M3 0.000
Cement 25 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative

Tiles Installation 21.2 M2 25.6 46.80

Back Filling M3 0.00


Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 0.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1.Tiles Installation work in Progress


TODAY ACTIVITY 2.Materail Shifting Work in progress

1.Tiles Installation work


TOMORROW ACTIVITY 2.Materail Shifting

Concern -NIL.
27/8/2023
3

To
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM
5:30 PM

Remarks

Remarks

Grouting and
Cleaning Work Is
Remain
Daily Progress Report
Project: STO PROJECT Date:
Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Mason 2 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4 Ram Kumar Mason 7:30 AM
Labour/Helper 1 5
Painter 6
Driver 7
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 4 13
Equip Ment 14
Pick up 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 0 M3 0.000
Soil 0 M3 0.000
Cement 0 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative
Tiles Installation 25.6 M2 25.60
Back Filling M3 0.00
Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 0.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1.Tiles Installation work in Progress


TODAY ACTIVITY

1.Tiles Installation work


SUNDAY ACTIVITY 2.Materail Shifting

Concern -NIL.
24/8/2023
2

To
5:30 PM
5:30 PM
5:30 PM
5:30 PM

Remarks

Remarks
Daily Progress Report
Project: STO PROJECT Date:
Location: SUR ( BEC Project) SL No
Name
Total Man Power QTY
SL No Name Trade From
Supervisor 1 1 MUKLESH SUPERVISOR 7:30 AM
Mason 1 2 Ram Millan Mason 7:30 AM
Carrpenter 3 Dhiraj Helper 7:30 AM
Steel Fixer 4
Labour/Helper 1 5
Painter 6
Driver 7
Plumber 8
Electrician 9
Rigger 10
JCB & sawal operator 11
12
Total Manpower 3 13
Equip Ment 14
Pick up 1 15
JCB 16
Shovel 17
Generator 18
Tipper 19
Canter-3T 20
Hiab 21
Materials Consumption
Item QTY Unit Unit Cost Amount
Cement Block No 0.000
Plaster Sand 3 M3 0.000
Soil M3 0.000
Cement 10 Bag 0.000
Water GLN 0.000
Paint-1 L 0.000
Paint-2 L 0.000
Wall Putty Kg 0.000
Wall Tiles M2 0.000
Floor Tiles-1 M2 0.000
Floor Tiles-2 M2 0.000
Polythene Sheet Roll 0.000
Shuttering Oil L 0.000
RCC M3 0.000
Steel Kg 0.000
Plywood No 0.000
Total 0.000
Progress
Item QTY Unit QTY Till Yesterday Cumulative
Tile Installation M3 0.00
Back Filling M3 0.00
Block Work M2 0.00
Rendering(Plastering) M2 0.00
Shuttering M2 0.00
PCC M3 0.00
Steel Fixing Kg 0.00
RCC M3 0.00
Shutter Removal M2 0.00
Primer M2 0.00
Painting M2 0.00
Flooring Tile M2 0.00
Bathroom Tile M2 0.00
Wall Tiles M2 0.00
0.00
0.00

1. Material Shifting to Bathroom,Store room & Dining Room Work In Progress


TODAY ACTIVITY

1.Tiles Installation work


TOMORROW ACTIVITY 2.Materail Shifting

Concern -NIL.
23/8/2023
1

To
5:30 PM
5:30 PM
5:30 PM

2hr

Remarks

Remarks
Progress