Facility Project

Build the facility for 3,502,000$


Start By : November 8 1995
End By : September 24 1996
Three divisions
Building : Consists of facility design and construction
Equipment : Requires design, installation, tryout and launch of
equipment
Training : Preparing training manuals and selecting and training
qualified personnel to operate the new facility
A Facility Project : Measuring
Project Performance
Chapter No 10
Preparing WBS: Three divisions are
bifurcated at the very top level i.e Building,
equipment and training
Network diagram is developed for each
division i.e Separate network diagram
(Sub-diagram) for
Building
Equipment
Training
Design and construct building
Design Building :
User requirement, Site requirement, building design,
site design, building specifications, bid processing,
contract and award
Prepare Site :
Earthwork , grading, underground installations
(electrical, water and sewer lines) roadways
Construct Building-Phase I
Foundations, structural steel framing, roofing and
floor construction
Construct Building-Phase II
Interior Work, mechanical and electrical systems,
lighting, painting and approvals
Design and try out equipment
Design and procure
Design equipment
Prepare equipment installation drawings
Procure special equipment
Install and try out
Install Equipment Phase I : Install assisting equipment
Install Equipment Phase II : Electrical & Mechanical
connections
Try out system : individual and total system try out
Controls
Design Controls
Select controls suppliers
Fabricate and assemble controls
Training
Developing Operating procedures
Selecting and training personnel
Planning & Scheduling Project
All subdiagrams are further developed to
form schedule
Scheduling can also be done with the help
of computers
Measuring Project Performance
Monitor
Assess
Resolve
Communicate
The cause and effect diagram can help in
assessment and resolution phase of the
project performance measurement

Project Status Report
Project Status reports are prepared and
communicated in timely manner