Professional Documents
Culture Documents
1
CONSTRUCTION TEAM
For any civil engineering project, a construction team is composed of owner, engineers/architects and
contractor.
Owner: The owner may be an individual or a group of individuals, private or public sector company. The
owner holds all the decision making powers regarding managerial, financial and administrative aspects of a
project. He is responsible for the fund and other resources of the project.
Duties of the owner:
1) He appoints an engineer and other staff.
2) He obtains clearance for construction from competent authority.
3) He provides the engineer the estimated cost and the required time.
4) He makes payment to the contractor on the production of proper bill from the engineer.
Engineer: It includes the construction engineer who is responsible for project management, store control,
inspection and quality assurance, construction supervision, cost control, etc. It also includes architects,
structural engineers, quantity surveyor, mechanical and electrical engineer, specialists such as structural
consultants, safety and maintenance planners, soil investigators, etc. He gets prepared the necessary drawings,
specifications, and estimates, checks soil conditions and supervises the entire work.
Architects assess the owner’s functional requirements and prepare plans and specifications for the purpose.
Structural engineers prepare design as per loads and prepare working drawings which is handed over to the
construction engineer.
Mechanical engineer is responsible for the mechanical devices required during and after construction.
Electrical engineer prepares working drawings for electrical powers and distribution systems during and after
construction.
Quantity surveyor:
a. Estimates cost of work
b. Prepares bill of quantities
c. Assess extra cost due to special features
d. Prepare cash flow statement during construction.
e. Prepare final accounts on project completion,
Contractor:
The contractor may be an individual or a large construction company. The contractor has to do a number of
works and has to make all necessary arrangements for labour, equipment, materials, etc. in order to complete
the project within given time and cost. His duties are:
a. He undertakes execution of work or services concerned.
b. He has to visit worksite, study soil conditions and ensure proper facilities for construction purposes.
c. He should safeguard his own men and materials.
d. He should obtain all building permits.
2
STAGES IN CONSTRUCTION:
1. Project reporting stage: In this stage, ideas of the project are originated by individual or group of
individuals or a public sector or private sector company. Ideas of the project are properly studied with respect to
the cost and benefits so that the project is economically and socially utilizable.
Activities:
2. Project planning stage: In this stage, a detailed cost estimate of the chosen project is made. The
purpose of this stage is to prepare project summary, detailed drawings, detailed structural design and finally get
the estimated cost of the project. The type of construction and methodology is also worked out.
3. Project tendering stage: In this stage, tenders are invited and the contract is awarded. The purpose of
this stage is to award a contract to the contractor selected for the purpose on suitable terms and conditions
ensuring proper quality, cost and completion time.
Functions:
ii. Service and facilities must be provided before starting the work.
iii. Supervision of construction work
iv. Coordination of sub-contractors and various sections
v. Inspection, quality control and work progress
vi. Final checking of the completed work is made and final payment is made to the contractor.
5. Project commissioning stage: In this stage, performance of the structure is evaluated and type of
maintenance and repair is proposed.
The purpose of this stage is to ensure that the construction work has been completed as specified in the contract
documents.
Functions:
i. Keeps various records of the actual work
ii. Quality inspection to remove the defects if found
iii. Prepare operating and maintenance manual
iv. Carryout performance test of the structure
v. Appointment of staff for commissioning schedule
4
FUNCTIONS OF CONSTRUCTION MANAGEMENT
i. Specifying project objectives and plans
ii. Maximizing the resource efficiency through use of labour, materials and equipment.
iii. Implementing various operations through proper coordination and control of planning, design,
estimating, contracting and construction in the entire process
iv. Developing effective mechanisms for resolving conflicts.
CONSTRUCTION SCHEDULING
By using CPM network of a project, various construction schedules/calendars are prepared such as –
i.Activity Schedule/calendar
ii.Material Schedule/calendar
iii.Labour Schedule/calendar
iv.Equipment Schedule/calendar
v.Financial Schedule/calendar
If we want to run a project smoothly and at given budget, we need to know beforehand the types and quantities
of various resources (men, materials, machinery and money) that will be needed. Critical path study helps us to
know in advance what resources will be needed and when they will be needed and also the exact dates on which
they will be released for use on the project.
i.Activity Schedule/calendar: It is a tool to manage time and perform activities in a proper sequence. The
following are the steps to prepare an activity schedule:
a) The project’s construction methodology is studied in detail and a list of activities that constitute the
project is prepared. A time duration is also fixed for each activity.
b) A logical relationship among the activities is formed.
c) The logical relationship is converted in the form of an arrow diagram.
d) Duration, symbolic name and node-numbering is done after removing all errors.
e) Critical path, project duration, activity name and associated floats are calculated which is called
scheduling.
f) Earliest start and latest start, earliest finish and latest finish of each activity associated with floats is used
for optimum use of resources.
g) Finally a calendar or table is prepared in which the exact working date excluding the holiday is
mentioned for each activity in the following form-
Name of project…………………………….
Place of worksite……………………………
Starting date………………………………..
Finishing date……………………………..
Table 1: Activity Schedule
CONSTRUCTION PLANNING:
It is a process of documenting action based plans for completion of project in time. It includes defining the work
task, sequence of work, construction methods, roles and responsibilities and planning of resources to complete
the project as per schedule.
The documents for construction planning are designs and drawings, quantity estimates, construction methods to
be adopted, contract documents, site conditions, market survey, local resources, project environment and the
client’s requirements.
Objectives:
1. Planning of each activity: Each activity should be identified and included in a sequential way. Every
activity should be scheduled in a timeline for tracking of construction project.
2. Construction methods: plans should include construction methods to be adopted for different activities
and tools so that they can be made available whenever required.
3. Planning for construction equipments and machinery: Cost of a construction varies greatly with the
use of construction equipments and heavy machinery as their renting cost may be very high per day. So
planning for each equipment should be done in advance so that project activities go on smoothly without
waiting for these equipments.
4. Procurement of materials: It is not good to keep the material unused at the site for a long time. This
will degrade the material, thereby increasing the material cost. So proper planning of material also helps to
complete the project within given budget.
7
5. Planning for employee skills: Some of the activities require skilled labours to complete the work. It is
not necessary to employ such persons for the entire project. So proper planning of such activities will reduce the
cost of operations.
6. Planning for required documents and drawings: Construction activities are completed based on the
drawings and detailing. It is necessary to make these drawings available at site on time so that construction
activities are not stopped.
7. Financial planning: Financial planning is the most important aspect. Different amounts are required at
different stages. Proper planning of funds helps to run the project smoothly.