Professional Documents
Culture Documents
June 2008
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Table of Contents
page
1. Introduction..........................................................................................................5
1.1. Background..................................................................................................5
1.2. Purpose of this Document..........................................................................6
1.3. Scope of this Document..............................................................................7
2. The Structure of the Contract............................................................................8
2.1. The Contract Existing..................................................................................8
2.1.1. Lump Sum Contract Price vis-à-vis Scope of Works..............................8
2.1.2. Provisional Sums..................................................................................12
2.1.2.1. Tender Provisions..........................................................................12
2.1.2.2. Contract Provisions.......................................................................13
2.1.2.3. Current Situation............................................................................15
2.1.2.4. Conclusions...................................................................................16
2.2. Relevant Contract Provisions...................................................................17
2.2.1. Sub-clause 1.9 – Delayed Drawings or Instructions.............................17
2.2.2. Sub-clause 3.3 – Instructions of the Project Manager..........................18
2.2.3. Sub-clause 4.7 – Setting Out................................................................19
2.2.4. Sub-clause 4.12 – Unforeseeable Physical Conditions........................19
2.2.5. Sub-clause 8.3 – Programme...............................................................20
2.2.6. Sub-clause 8.4 – Extension of Time for Completion............................22
2.2.7. Sub-clause 8.8 – Suspension of Works................................................22
2.2.8. Sub-clause 8.9 – Consequences of Suspension..................................23
2.2.9. Sub-clause 12.1 – Works to be Measured...........................................23
2.2.10. Sub-clause 12.3 – Evaluation...........................................................24
2.2.11. Sub-clause 13.1 – Right to Vary.......................................................25
2.2.12. Sub-clause 13.3 – Variation Procedure............................................26
2.2.13. Sub-clause 20.1 – Contractor’s Claims.............................................27
2.3. Original Planning and Cash-flow..............................................................29
2.3.1. The Clause 8 Programme.....................................................................29
2.3.2. Planned versus Actual Turnover...........................................................30
2.4. First Revised Programme of Works.........................................................32
2.5. Second Revised Programme of Works....................................................32
2.6. Actual Progress..........................................................................................34
3. Valuation of Variations.....................................................................................35
3.1. Explanation of Heads of Claim.................................................................35
3.2. Specific Heads of Claim............................................................................35
3.3. Methods of Valuation of the Variations...................................................36
3.3.1. Use of Costs as Basis...........................................................................36
3.3.2. Addition for Profit..................................................................................36
3.3.3. Profit as Part of the Value of Variations................................................36
3.3.3.1. Three Types of Variations.............................................................36
3.3.3.2. Changes in Design of the Works...................................................37
page 2
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 3
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
5.2. Conclusion................................................................................................121
6. Financial Analysis...........................................................................................122
6.1. Consequences..........................................................................................122
6.1.1. Direct Cost..........................................................................................123
6.1.2. Indirect Cost........................................................................................123
6.1.3. Consequential Cost.............................................................................123
6.2. Costs in Extended Contract Period........................................................123
6.2.1. Nature of Loss and Expense..............................................................123
6.2.2. Contractor’s Entitlement to Reimbursement.......................................124
6.3. Finance Cost.............................................................................................124
6.4. Conclusions..............................................................................................125
7. Extension of Time Entitlement.......................................................................126
8. Additional Payment.........................................................................................127
8.1. Introduction..............................................................................................127
8.2. Evaluation of the Financial Consequences...........................................127
8.2.1. Wasted Costs Arising from Delay and Disruption..............................128
8.2.1.1. Staff and Labour..........................................................................128
8.2.1.2. Equipment....................................................................................129
8.2.1.3. Site and Head Office...................................................................130
8.2.1.4. Summary of Wasted Costs..........................................................132
8.2.2. Additional Costs Arising from Acceleration.........................................132
8.2.3. Additional Costs in Extended Contract Period...................................133
8.2.4. Other Costs.........................................................................................134
8.2.4.1. Procurement of Permanent Materials..........................................134
8.2.4.2. Temporary Materials including Equipment..................................135
8.2.5. Finance Costs.....................................................................................135
8.2.6. Grand Summary..................................................................................136
9. Statement of Claim..........................................................................................138
10. Appendices...................................................................................................139
10.1. Wasted Costs........................................................................................139
10.1.1. Record of Resources – Staff and Labour........................................139
10.1.2. Record of Resources – Equipment.................................................139
10.1.3. Direct and Indirect Costs.................................................................139
10.2. RFI and RFA..........................................................................................140
10.3. Correspondence.....................................................................................141
page 4
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
1. Introduction
1.1. Background
A Contract for Building and Engineering Works Designed by the
Employer was entered into on 27 April 2007 between the Polus
Investments (Seychelles) Limited (hereinafter called “the
Employer”) and Island Construction (PTY) Limited (hereinafter
called “the Contractor”).
The issues became clear from the very start of the construction
process. Once the setting out delays was over-come the
Contractor encountered hard rock in excavation at almost all
building locations. This unforeseen circumstance caused a
varied order of construction to that planned together with
numerous late instructions as design evolved.
page 5
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
The Contractor has given notice that he will have to make claims
to achieve the relief and payment to which he believes he is
entitled.
page 6
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 7
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
“As per our agreement the lump sum contract price shall
not be amended unless specifically agreed with the
Employer and the Quantity Surveyor. No additional work
(beyond the scope of the lump sum Contract Price) may
be commenced prior to reaching agreement on the price
thereof.”
page 8
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 9
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Excavation in rock;
page 10
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 11
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
2.1.2.Provisional Sums
Clause 13 empowers the Project Manager to issue instructions
to the Contractor directing him how provisional sums are to be
expended. Provisional sums are included in this Contract where
the precise cost or extent of work is not known at time of tender.
The purpose is to have the sum of money to cover the cost.
When the instruction is issued, the sum inserted is omitted and
the variation is then valued in accordance with the principles of
Clause 12 and 13.
At tender stage the value shown for Measured Work was (Bills 1
to 34 inclusive) SCR20,677,661.15, and the value of the
Preliminaries (Bill 1) has been derived from this figure.
page 12
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
(a)
or (b)
page 13
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 14
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
1 Insurance 250,000.00
2 Foreign Staff, Labour Repatriation 450,000.00
3 Facilities for Staff and Labour 170,000.00
4 Measures against Insect and Pect Nuisance 60,000.00
5 Supply of Foodstuffs 660,000.00
6 Supply of Water 80,318.00
7 Shop Drawings 10,000.00
8 As-Built Documents 5,600.00
9 Temporary Site Office for Employers Consultants 65,250.00
10 Site Signboard 3,275.00
11 Access to Site 35,000.00
12 Site to be Tidy 12,727.00
13 Co-ordination 14,727.00
14 Site Records 3,275.00
15 Site Records 29,913.00
16 Safety Procedures 5,700.00
17 Security at Site 13,426.00
18 Contractors Site Operations 7,485.00
19 Site Radio Communication 11,725.00
20 Environmental Impact Assessment 5,000.00
21 Taking Delivery from NS 50,000.00
22 Contractors Temporary Accommodation 35,000.00
23 Superintendence 15,000.00
24 Transport of People 125,475.00
25 Contractors Equipment 365,000.00
26 Scaffolding 105,000.00
page 15
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
2.1.2.4. Conclusions
page 16
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
This signifies that all the Works measured to date are under-
valued. Accordingly, the Conditions of the Contract dictate the
following actions:
page 17
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 18
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 19
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 20
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 21
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 22
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 23
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 24
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Or
page 25
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 26
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 27
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 28
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 29
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
1 SHANGRI-LA , Long Island Resort Seychelles 0%
2 General Conditions and Preliminaries 0%
17 Site establishment 0%
41 Material/equipment procurement 0%
182 Lot 1 0%
183 A3 Villas ( 6 nos) 0%
453 C311 Executive Villas ( 1 nos) 0%
497 GM Villa ( subject to receipt of GFW drawings) 0%
537 Employees Facilities ( subject to receipt of GFW drawings) 0%
581 Laundry F& B service office ( subject to receipt of GFW drawings) 0%
625 Health Club/ Medical Centre( subject to receipt of GFW drawings) 0%
666 Administration Block ( subject to receipt of GFW drawings) 0%
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings) 0%
750 Main Lobby ( subject to receipt of GFW drawings) 0%
791 Tennis Courts ( subject to receipt of GFW drawings) 0%
807 External works ( subject to receipt of GFW drawings) 0%
816 Drainage works ( subject to receipt of EME details) 0%
819 Fuel Farm ( subject to receipt of EME details) 0%
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details) 0%
827 Desalination plant( subject to receipt of EME details) 0%
831 MLV Panel( subject to receipt of EME details) 0%
835 Step Up Transformer( subject to receipt of EME details) 0%
839 Incinerator/ Garbage room( subject to receipt of EME details) 0%
843 Sewer treatement plant( subject to receipt of EME details) 0%
847 Lot 2 0%
848 A3 Villas (17 nos) 0%
1614 B223 Villas ( 7 nos) 0%
1965 B4 Villa (2 nos.) 0%
2056 Retail 1( subject to receipt of GFW drawings) 0%
2094 Retail 2( subject to receipt of GFW drawings) 0%
2132 Retail 3( subject to receipt of GFW drawings) 0%
2170 Seafood resort( subject to receipt of GFW drawings) 0%
2211 Greeting Pavillion( subject to receipt of GFW drawings) 0%
2250 External works ( subject to receipt of GFW drawings) 0%
2259 Drainage works ( subject to receipt of EME details) 0%
2262 Lot 3 0%
2263 A3 Villas ( 9 nos) 0%
2664 B223 Villas ( 3 nos) 0%
2808 B4 Standard Villas ( 2 nos) 0%
2899 BC311 Executive Villa 0%
3115 P3 Presidential suites ( 3 nos) 0%
3245 Hilltop sunset deck( subject to receipt of GFW drawings) 0%
3280 External works ( subject to receipt of GFW drawings) 0%
3289 Drainage works ( subject to receipt of EME details) 0%
3292 Lot 4 0%
3293 Couple treatment room( subject to receipt of GFW drawings) 0%
3334 Single treatment room( subject to receipt of GFW drawings) 0%
3375 Dive Centre( subject to receipt of GFW drawings) 0%
3413 Kid's club( subject to receipt of GFW drawings) 0%
3452 Recreation House( subject to receipt of GFW drawings) 0%
3491 Watersports rental( subject to receipt of GFW drawings) 0%
3529 3 Meals restaurant( subject to receipt of GFW drawings) 0%
3570 Beach Pool Bar( subject to receipt of GFW drawings) 0%
3611 Signature Pool area( subject to receipt of GFW drawings) 0%
3650 Wedding Chapel( subject to receipt of GFW drawings) 0%
3685 BOH/Admin Building( subject to receipt of GFW drawings) 0%
3726 Chi Sanctum( subject to receipt of GFW drawings) 0%
3767 Yoga Pavillion( subject to receipt of GFW drawings) 0%
3805 External works ( subject to receipt of GFW drawings) 0%
3814 Drainage works ( subject to receipt of EME details) 0%
3817 M&E Installations- External 0%
3828 Sundries 0%
3829 Site cleaning & demobilisation 0%
3830 Project Commissioning 0%
It can be seen the period through to XX, the first X-months of the
construction programme, both planned and actual cash-flow
remain reasonably constant. This is to be expected.
page 30
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
PlanCumm ActualCumm
30,000,000.00
25,000,000.00
20,000,000.00
15,000,000.00
10,000,000.00
5,000,000.00
0.00
Feb-07
Mar-07
Apr-07
May-07
Jun-07
Jul-07
Aug-07
Sep-07
Oct-07
Nov-07
Dec-07
Jan-08
Feb-08
Mar-08
Apr-08
May-08
-5,000,000.00
page 31
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 32
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 33
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
The overall effect of all the above has been to delay the
completion date for the works up to 24 March 2009 as
indicated in the attached revised programme.
page 34
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
3. Valuation of Variations
page 35
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 36
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
The Contractor confirms that costs claimed are the indirect costs
of the delays to the Works, whilst the direct costs include the
direct costs of performing the works. In other words, the
Contractor’s claim is for the time-related costs to be rolled into
the Clause 12 variation valuations.
The first of those two speaks for itself. The claim is for the time-
related costs of the variations to be included in the variation
valuations. It is unnecessary to argue the point that any such
valuation must include profit, under the valuation rules. All
valuation rules, in Clauses 12, are founded in rates and prices. It
is implicit that they already include profit. It follows that any new
rate or price will also include profit.
page 37
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
3.3.3.3. Summary
page 38
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 39
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
The schedules showing the monthly labour and plant levels are
evidence that the Contractor not only mobilised, but also
maintained, levels of each, which should have ensured outputs
page 40
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 41
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 42
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 43
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
He then draws the parallel with Hadley v. Baxendale for the type
of damage to be included in loss and expense, and what he
calls ‘wording of this kind’, in paragraph 8.215:
page 44
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 45
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
offended party back in the same position he would have been in,
but for the events complained of.
Now that the basic premise for using the criterion applicable to
common law damages for breach of contract has been
presented, the Contractor will show that the recovery of profit
comes within that criterion.
The general rule that claims for loss and expense or costs are to
be treated as claims for damages at common law is expounded
by Dr Powell-Smith on page 143 of ‘Some building Contract
Problems’:
page 46
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
The important thing is that the contractor in the case was looking
to recover the sum of money he would have recovered, but for
the event complained of. It is natural that such sum of money
included profit.
page 47
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
The extract also mentions the possibility of claiming for profit lost
on other contracts. The Contractor is not claiming for that. He is
only claiming for his profit on the Contract, which is much more
direct than that lost on other projects.
3.3.6.3. Summary
The Contractor’s claim is only for profit on the Contract work, not
for other work, so it is within the first rule in Hadley v.
Baxendale, and should be allowed.
page 48
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 49
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 50
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 51
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
If, at any time, the Engineer gives notice to the Contractor that
a programme fails (to the extent stated) to comply with the
Contract or to be consistent with actual progress and the
Contractor’s stated intentions, the Contractor shall submit a
revised programme to the Engineer in accordance with this
Sub-Clause.
page 52
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
(a) actual progress is too slow to complete within the Time for
Completion, and/or
(b) progress has fallen (or will fall) behind the current
programme under Sub-Clause8.3 [Programme],other than as
a result of a cause listed in Sub-Clause 8.4 [Extension of Time
for Completion], then the Engineer may instruct the Contractor
to submit, under Sub-Clause 8.3 [Programme], a revised
programme and supporting report describing the revised
methods which the Contractor proposes to adopt in order to
expedite progress and complete within the Time for
Completion. (Emphasis added)
page 53
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
The overall effect of all the above has been to delay the
completion date for the works up to 24 March 2009 as
indicated in the attached revised programme.
page 54
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Provisional Sums
page 55
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Material Procurement
Suspension of work
page 56
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 57
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Lump Sums
Tidal Movement
page 58
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Financial Considerations
Reduced Income
page 59
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Proposed Remedy
page 60
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 61
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Equipment
page 62
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
May-08 250,000.00
Jun-08 250,000.00
Jul-08 250,000.00
Aug-08 300,000.00
Sep-08 300,000.00
Oct-08 350,000.00
Nov-08 400,000.00
Dec-08 550,000.00
Jan-09 400,000.00
Feb-09 450,000.00
Total 3,500,000.00
page 63
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 64
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Equipment
Materials
Conclusion
page 65
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 66
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 67
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 68
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 69
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 70
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 71
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
4.4.3.Suspension of Works
The Contractor was instructed to suspend the works, which
suspension lasted 61 days and directly effected progress of the
villas listed. This period of suspension is considered a critical
delay.
page 72
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
4.4.4.Variations to Design
The design drawings issued for construction show all steel roof
members as stainless steel although the bill of quantities, as
priced at tender, show galvanised steel. As a result the sourcing
and procurement time consumed an additional 81 calendar
days. This delayed roof construction at the 2 Mock-up Villas and
is considered a critical delay.
page 73
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Q uantity
Des c ription of Materials Ordered Date O rdered Amount rec eived B alanc e C omments
F OR AL L 55 VIL L AS
50K G bags P ortland C ement 2,800.00 04/04/07 300.00 2,500.00 B alance on order s ubject to payment to s upplier
P lywood for S huttering/R oofing 6,000.00 14/11/07 1,800.00 4,200.00 B alance on order s ubject to payment to s upplier
C rus her D us t 6,000.00 23/06/07 1,565.13 4,434.87 B alance on order s ubject to payment to s upplier
Aggregate 8,000.00 25/06/07 1,222.64 6,777.36 B alance on order s ubject to payment to s upplier
P las tering S and 1,000.00 16/07/07 80.00 920.00 B alance on order s ubject to payment to s upplier
150mm S oild concrete B locks 125,000.00 05/07/07 31,975.00 93,025.00 B alance on order s ubject to payment to s upplier
100mm Hollow concrete B locks 15,000.00 15/07/07 2,340.00 12,660.00 B alance on order s ubject to payment to s upplier
A252 W eld Mes h (R oadworks ) 912.00 14/05/07 162.00 750.00 B alance on order s ubject to payment to s upplier
High tens ile s teel-8,10,12,16,25mm (tons ) 500.00 14/01/07 158.00 342.00 B alance on order s ubject to payment to s upplier
C edar S hingles (s qm) 12,757.64 03/05/07 3,712.00 9,045.64 B alance on order s ubject to payment to s upplier
Iroko timber (external cladding) L M 54,198.00 07/05/07 1,548.00 52,650.00 B alance on order s ubject to payment to s upplier
12mm G yps um boards (S H E E T S ) 5,600.00 03/02/07 5,600.00 0.00 Awaiting for other building from I.D
S tainles s s teel threaded rods 12,16mm 16,300.00 09/11/07 8,110.00 8,190.00 B alance on order s ubject to payment to s upplier (Not B .O .Q item)
S tainles s s teel gus s et plates (variation) 450.00 09/11/07 50.00 400.00 B alance on order s ubject to payment to s upplier (Not B .O .Q item)
B alau T imber (L M) 169,074.50 08/06/07 6,148.16 162,926.34 B alance on order s ubject to payment to s upplier
T reated P ine T imber (L M) 94,148.50 20/04/07 43,225.50 50,923.00 B alance on order s ubject to payment to s upplier
page 74
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
For all the foregoing reasons stated above, the Contractor could
not have progressed major material procurement because he
was constrained by two issues:
page 75
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
5. Time Analysis
The time analysis has been carried out in three stages for each
claimable event:
page 76
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
These three stages have been repeated for each of the events
in turn and the results are reflected in the Contractor’s two
requests made to date for an extension of time.
5.1.1.Mitigation by Contractor
The Contractor mitigated the effects of the late supply of design
information by starting work on a particular activity without
waiting for the whole of the design needed for a particular piece
of work. This was particularly noticeable at the Mock-up villas
where architectural details were constantly revised as works
progressed. The success in taking this phase-advanced
approach to work has not produced the results anticipated.
page 77
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 78
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
The order of the impacted charts that follow are in the sequence
each event occurred at Site.
page 79
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 80
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 20
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1055 Finishes 0%
1056 Wall plaster (internal & External) 0%
1057 M&E 1st fix 0%
1058 Floor finishes 0%
1059 Fix windows & doors 0%
1060 Swimming pool finishes 0%
1061 M&E final fix 0%
1062 Fix fittings and Fixtures 0%
1063 M&E Installations 0%
1064 Cable Tray, Conduit and Wiring 0%
1065 Electrical boards and connections 0%
1066 Electrical accessories 0%
1067 Light fittings and ceiling fans 0%
1068 Hot and cold water 0%
1069 Waste and sewage incl. biobox 0%
1070 Electric water heater 0%
1071 Swimming pool 0%
1072 Split unit installation 0%
1073 Toilet ventilation, grilles 0%
1074 Villa A3/12 0%
1119 Villa A3/13 0%
1164 Villa A3/18 0%
1209 Villa A3/19 0%
1254 Villa A3/20 0%
1255 substructure 0%
1256 set out 0%
1257 Excavate 0%
1258 Conc. Foundation 0%
1259 Backfill 0%
1260 termite treatment 0%
1261 DPC (where applicable) 0%
1262 M&E inlet/outlet works - first fix 0%
1263 frame 0%
1264 set kickers 0%
1265 Conc. Columns & shear walls 0%
1266 Conc. G. F Beams 0%
1267 M&E first fix 0%
1268 Conc. Plantroom 0%
1269 Conc. Floor slab & swimming pool base 0%
1270 Blockwork 0%
1271 Conc. Swimming pool sides & overflow channels 0%
1272 Conc. Ring & tie beams 0%
1273 Roof & Ceiling 0%
1274 Fix wall plate & truss 0%
1275 Fix purlins and rafters 0%
1276 Fix shingles ( subject to receipt of timber) 0%
1277 Fix ceiing battens & joists 0%
1278 Fix ceiling boards 0%
1279 M&E first fix 0%
1280 Finishes 0%
1281 Wall plaster (internal & External) 0%
1282 M&E 1st fix 0%
1283 Floor finishes 0%
1284 Fix windows & doors 0%
1285 Swimming pool finishes 0%
1286 M&E final fix 0%
1287 Fix fittings and Fixtures 0%
1288 M&E Installations 0%
1289 Cable Tray, Conduit and Wiring 0%
1290 Electrical boards and connections 0%
1291 Electrical accessories 0%
1292 Light fittings and ceiling fans 0%
1293 Hot and cold water 0%
1294 Waste and sewage incl. biobox 0%
1295 Electric water heater 0%
1296 Swimming pool 0%
1297 Split unit installation 0%
1298 Toilet ventilation, grilles 0%
1299 Villa A3/21 0%
1344 Villa A3/22 0%
1389 Villa A3/23 0%
1434 Villa A3/24 0%
1479 Villa A3/25 0%
1524 Villa A3/26 0%
1569 Villa A3/27 0%
1614 B223 Villas ( 7 nos) 0%
1615 Villa B2/01 0%
1665 Villa B2/02 0%
1715 Villa B2/04 (mock up villa) 0%
1765 Villa B2/05 0%
1815 Villa B2/06 0%
1865 Villa B2/07 0%
1915 Villa B2/08 0%
1965 B4 Villa (2 nos.) 0%
1966 Villa B4/01 0%
2011 Villa B4/02 0%
2056 Retail 1( subject to receipt of GFW drawings) 0%
2094 Retail 2( subject to receipt of GFW drawings) 0%
2132 Retail 3( subject to receipt of GFW drawings) 0%
2170 Seafood resort( subject to receipt of GFW drawings) 0%
2211 Greeting Pavillion( subject to receipt of GFW drawings) 0%
2250 External works ( subject to receipt of GFW drawings) 0%
2259 Drainage works ( subject to receipt of EME details) 0%
2262 Lot 3 0%
2263 A3 Villas ( 9 nos) 0%
2264 Villa A3/14 0%
2309 Villa A3/15 0%
2354 Villa A3/16 0%
2399 Villa A3/17 0%
2444 Villa A3/28 0%
2489 Villa A3/29 0%
2534 Villa A3/30 0%
2535 substructure 0%
2536 set out 0%
2537 Excavate 0%
2538 Conc. Foundation 0%
2539 Backfill 0%
2540 termite treatment 0%
2541 DPC (where applicable) 0%
2542 M&E inlet/outlet works - first fix 0%
page 81
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
2543 frame 0%
2544 set kickers 0%
2545 Conc. Columns & shear walls 0%
2546 Conc. G. F Beams 0%
2547 M&E first fix 0%
2548 Conc. Plantroom 0%
2549 Conc. Floor slab & swimming pool base 0%
2550 Blockwork 0%
2551 Conc. Swimming pool sides & overflow channels 0%
2552 Conc. Ring & tie beams 0%
2553 Roof & Ceiling 0%
2554 Fix wall plate & truss 0%
2555 Fix purlins and rafters 0%
2556 Fix shingles ( subject to receipt of timber) 0%
2557 Fix ceiing battens & joists 0%
2558 Fix ceiling boards 0%
2559 M&E first fix 0%
2560 Finishes 0%
2561 Wall plaster (internal & External) 0%
2562 M&E 1st fix 0%
2563 Floor finishes 0%
2564 Fix windows & doors 0%
2565 Swimming pool finishes 0%
2566 M&E final fix 0%
2567 Fix fittings and Fixtures 0%
2568 M&E Installations 0%
2569 Cable Tray, Conduit and Wiring 0%
2570 Electrical boards and connections 0%
2571 Electrical accessories 0%
2572 Light fittings and ceiling fans 0%
2573 Hot and cold water 0%
2574 Waste and sewage incl. biobox 0%
2575 Electric water heater 0%
2576 Swimming pool 0%
2577 Split unit installation 0%
2578 Toilet ventilation, grilles 0%
2579 Villa A3/31 0%
2624 Villa A3/32 0%
2664 B223 Villas ( 3 nos) 0%
2665 Villa B2/03 0%
2708 Villa B2/09 0%
2758 Villa B2/10 0%
2808 B4 Standard Villas ( 2 nos) 0%
2809 Villa B4/03 0%
2854 Villa B4/04 0%
2899 BC311 Executive Villa 0%
2900 Villa C3/02 0%
2943 Villa C3/03 0%
2986 Villa C3/04 0%
3029 Villa C3/05 0%
3072 Villa C3/06 0%
3115 P3 Presidential suites ( 3 nos) 0%
3116 Villa P3/01 0%
3159 Villa P3/02 0%
3202 Villa P3/03 0%
3245 Hilltop sunset deck( subject to receipt of GFW drawings) 0%
3280 External works ( subject to receipt of GFW drawings) 0%
3289 Drainage works ( subject to receipt of EME details) 0%
3292 Lot 4 0%
3293 Couple treatment room( subject to receipt of GFW drawings) 0%
3334 Single treatment room( subject to receipt of GFW drawings) 0%
3375 Dive Centre( subject to receipt of GFW drawings) 0%
3413 Kid's club( subject to receipt of GFW drawings) 0%
3452 Recreation House( subject to receipt of GFW drawings) 0%
3491 Watersports rental( subject to receipt of GFW drawings) 0%
3529 3 Meals restaurant( subject to receipt of GFW drawings) 0%
3570 Beach Pool Bar( subject to receipt of GFW drawings) 0%
3611 Signature Pool area( subject to receipt of GFW drawings) 0%
3650 Wedding Chapel( subject to receipt of GFW drawings) 0%
3685 BOH/Admin Building( subject to receipt of GFW drawings) 0%
3726 Chi Sanctum( subject to receipt of GFW drawings) 0%
3767 Yoga Pavillion( subject to receipt of GFW drawings) 0%
3805 External works ( subject to receipt of GFW drawings) 0%
3814 Drainage works ( subject to receipt of EME details) 0%
3817 M&E Installations- External 0%
3828 Sundries 0%
3829 Site cleaning & demobilisation 0%
3830 Project Commissioning 0%
page 82
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 83
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
984 Villa A3/10 0%
985 substructure 0%
986 set out 0%
987 Excavate 0%
988 Conc. Foundation 0%
989 Backfill 0%
990 termite treatment 0%
991 DPC (where applicable) 0%
992 M&E inlet/outlet works - first fix 0%
993 frame 0%
1003 Roof & Ceiling 0%
1010 Finishes 0%
1018 M&E Installations 0%
1029 Villa A3/11 0%
1030 substructure 0%
1031 set out 0%
1032 Excavate 0%
1033 Conc. Foundation 0%
1034 Backfill 0%
1035 termite treatment 0%
1036 DPC (where applicable) 0%
1037 M&E inlet/outlet works - first fix 0%
1038 frame 0%
1048 Roof & Ceiling 0%
1055 Finishes 0%
1063 M&E Installations 0%
1074 Villa A3/12 0%
1119 Villa A3/13 0%
1164 Villa A3/18 0%
1209 Villa A3/19 0%
1210 substructure 0%
1211 set out 0%
1212 Excavate 0%
1213 Conc. Foundation 0%
1214 Backfill 0%
1215 termite treatment 0%
1216 DPC (where applicable) 0%
1217 M&E inlet/outlet works - first fix 0%
1218 frame 0%
1228 Roof & Ceiling 0%
1235 Finishes 0%
1243 M&E Installations 0%
1254 Villa A3/20 0%
1255 substructure 0%
1256 set out 0%
1257 Excavate 0%
1258 Conc. Foundation 0%
1259 Backfill 0%
1260 termite treatment 0%
1261 DPC (where applicable) 0%
1262 M&E inlet/outlet works - first fix 0%
1263 frame 0%
1273 Roof & Ceiling 0%
1280 Finishes 0%
1288 M&E Installations 0%
1299 Villa A3/21 0%
1300 substructure 0%
1301 set out 0%
1302 Excavate 0%
1303 Conc. Foundation 0%
1304 Backfill 0%
1305 termite treatment 0%
1306 DPC (where applicable) 0%
1307 M&E inlet/outlet works - first fix 0%
1308 frame 0%
1318 Roof & Ceiling 0%
1325 Finishes 0%
1333 M&E Installations 0%
1344 Villa A3/22 0%
1389 Villa A3/23 0%
1434 Villa A3/24 0%
1479 Villa A3/25 0%
1524 Villa A3/26 0%
1525 substructure 0%
1526 set out 0%
1527 Excavate 0%
1528 Conc. Foundation 0%
1529 Backfill 0%
1530 termite treatment 0%
1531 DPC (where applicable) 0%
1532 M&E inlet/outlet works - first fix 0%
1533 frame 0%
1543 Roof & Ceiling 0%
1550 Finishes 0%
1558 M&E Installations 0%
1569 Villa A3/27 0%
1570 substructure 0%
1571 set out 0%
1572 Excavate 0%
1573 Conc. Foundation 0%
1574 Backfill 0%
1575 termite treatment 0%
1576 DPC (where applicable) 0%
1577 M&E inlet/outlet works - first fix 0%
1578 frame 0%
1588 Roof & Ceiling 0%
1595 Finishes 0%
1603 M&E Installations 0%
1614 B223 Villas ( 7 nos) 0%
1615 Villa B2/01 0%
1616 substructure 0%
1617 set out 0%
1618 Excavate 0%
1619 Conc. Foundation 0%
1620 Backfill 0%
1621 termite treatment 0%
1622 DPC (where applicable) 0%
1623 M&E inlet/outlet works - first fix 0%
1624 frame 0%
1640 Roof & Ceiling 0%
1647 Finishes 0%
1654 M&E Installations 0%
page 84
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1665 Villa B2/02 0%
1666 substructure 0%
1667 set out 0%
1668 Excavate 0%
1669 Conc. Foundation 0%
1670 Backfill 0%
1671 termite treatment 0%
1672 DPC (where applicable) 0%
1673 M&E inlet/outlet works - first fix 0%
1674 frame 0%
1690 Roof & Ceiling 0%
1697 Finishes 0%
1704 M&E Installations 0%
1715 Villa B2/04 0%
1716 substructure 0%
1717 set out 0%
1718 Excavate 0%
1719 Conc. Foundation 0%
1720 Backfill 0%
1721 termite treatment 0%
1722 DPC (where applicable) 0%
1723 M&E inlet/outlet works - first fix 0%
1724 frame 0%
1740 Roof & Ceiling 0%
1747 Finishes 0%
1754 M&E Installations 0%
1765 Villa B2/05 0%
1766 substructure 0%
1767 set out 0%
1768 Excavate 0%
1769 Conc. Foundation 0%
1770 Backfill 0%
1771 termite treatment 0%
1772 DPC (where applicable) 0%
1773 M&E inlet/outlet works - first fix 0%
1774 frame 0%
1790 Roof & Ceiling 0%
1797 Finishes 0%
1804 M&E Installations 0%
1815 Villa B2/06 0%
1816 substructure 0%
1817 set out 0%
1818 Excavate 0%
1819 Conc. Foundation 0%
1820 Backfill 0%
1821 termite treatment 0%
1822 DPC (where applicable) 0%
1823 M&E inlet/outlet works - first fix 0%
1824 frame 0%
1840 Roof & Ceiling 0%
1847 Finishes 0%
1854 M&E Installations 0%
1865 Villa B2/07 0%
1866 substructure 0%
1867 set out 0%
1868 Excavate 0%
1869 Conc. Foundation 0%
1870 Backfill 0%
1871 termite treatment 0%
1872 DPC (where applicable) 0%
1873 M&E inlet/outlet works - first fix 0%
1874 frame 0%
1890 Roof & Ceiling 0%
1897 Finishes 0%
1904 M&E Installations 0%
1915 Villa B2/08 0%
1916 substructure 0%
1917 set out 0%
1918 Excavate 0%
1919 Conc. Foundation 0%
1920 Backfill 0%
1921 termite treatment 0%
1922 DPC (where applicable) 0%
1923 M&E inlet/outlet works - first fix 0%
1924 frame 0%
1940 Roof & Ceiling 0%
1947 Finishes 0%
1954 M&E Installations 0%
1965 B4 Villa (2 nos.) 0%
1966 Villa B4/01 0%
1967 substructure 0%
1968 set out 0%
1969 Excavate 0%
1970 Conc. Foundation 0%
1971 Backfill 0%
1972 termite treatment 0%
1973 DPC (where applicable) 0%
1974 M&E inlet/outlet works - first fix 0%
1975 frame 0%
1976 set kickers 0%
1977 Conc. Columns & shear walls 0%
1978 Conc. G. F Beams 0%
1979 M&E first fix 0%
1980 Conc. Plantroom 0%
1981 Conc. Floor slab & swimming pool base 0%
1982 Blockwork 0%
1983 Conc. Swimming pool sides & overflow channels 0%
1984 Conc. Ring & tie beams 0%
1985 Roof & Ceiling 0%
1986 Fix wall plate & truss 0%
1987 Fix purlins and rafters 0%
1988 Fix shingles ( subject to receipt of timber) 0%
1989 Fix ceiing battens & joists 0%
1990 Fix ceiling boards 0%
1991 M&E first fix 0%
1992 Finishes 0%
1993 Wall plaster (internal & External) 0%
1994 M&E 1st fix 0%
1995 Floor finishes 0%
1996 Fix windows & doors 0%
1997 Swimming pool finishes 0%
1998 M&E final fix 0%
1999 Fix fittings and Fixtures 0%
page 85
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
2000 M&E Installations 0%
2001 Cable Tray, Conduit and Wiring 0%
2002 Electrical boards and connections 0%
2003 Electrical accessories 0%
2004 Light fittings and ceiling fans 0%
2005 Hot and cold water 0%
2006 Waste and sewage incl. biobox 0%
2007 Electric water heater 0%
2008 Swimming pool 0%
2009 Split unit installation 0%
2010 Toilet ventilation, grilles 0%
2011 Villa B4/02 0%
2012 substructure 0%
2013 set out 0%
2014 Excavate 0%
2015 Conc. Foundation 0%
2016 Backfill 0%
2017 termite treatment 0%
2018 DPC (where applicable) 0%
2019 M&E inlet/outlet works - first fix 0%
2020 frame 0%
2021 set kickers 0%
2022 Conc. Columns & shear walls 0%
2023 Conc. G. F Beams 0%
2024 M&E first fix 0%
2025 Conc. Plantroom 0%
2026 Conc. Floor slab & swimming pool base 0%
2027 Blockwork 0%
2028 Conc. Swimming pool sides & overflow channels 0%
2029 Conc. Ring & tie beams 0%
2030 Roof & Ceiling 0%
2031 Fix wall plate & truss 0%
2032 Fix purlins and rafters 0%
2033 Fix shingles ( subject to receipt of timber) 0%
2034 Fix ceiing battens & joists 0%
2035 Fix ceiling boards 0%
2036 M&E first fix 0%
2037 Finishes 0%
2038 Wall plaster (internal & External) 0%
2039 M&E 1st fix 0%
2040 Floor finishes 0%
2041 Fix windows & doors 0%
2042 Swimming pool finishes 0%
2043 M&E final fix 0%
2044 Fix fittings and Fixtures 0%
2045 M&E Installations 0%
2046 Cable Tray, Conduit and Wiring 0%
2047 Electrical boards and connections 0%
2048 Electrical accessories 0%
2049 Light fittings and ceiling fans 0%
2050 Hot and cold water 0%
2051 Waste and sewage incl. biobox 0%
2052 Electric water heater 0%
2053 Swimming pool 0%
2054 Split unit installation 0%
2055 Toilet ventilation, grilles 0%
2056 Retail 1( subject to receipt of GFW drawings) 0%
2057 substructure 0%
2058 set out 0%
2059 Excavate (Drill in rock to anchor steel rods) 0%
2060 Conc. Foundation 0%
2061 Backfill ( where applicable ) 0%
2062 termite treatment 0%
2063 DPC (where applicable) 0%
2064 M&E inlet/outlet works 0%
2065 frame 0%
2066 set kickers 0%
2067 Conc. Columns & shear walls 0%
2068 Conc. G. F Beams 0%
2069 Conc. Plantroom 0%
2070 Conc. Floor slab 0%
2071 Blockwork 0%
2072 Conc. Ring & tie beams 0%
2073 Roof & Ceiling 0%
2074 Fix wall plate & truss 0%
2075 Fix purlins and rafters 0%
2076 Fix shingles ( subject to receipt of timber) 0%
2077 Fix ceiing battens & joists 0%
2078 Fix ceiling boards 0%
2079 Finishes 0%
2080 Wall plaster (internal & External) 0%
2081 M&E 1st fix 0%
2082 Floor finishes 0%
2083 Fix windows & doors 0%
2084 M&E final fix 0%
2085 Fix fittings and Fixtures 0%
2086 M&E Installations 0%
2087 Cable Tray, Conduit and Wiring 0%
2088 Electrical boards and connections 0%
2089 Electrical accessories 0%
2090 Light fittings and ceiling fans 0%
2091 Hot and cold water 0%
2092 Waste and sewage incl. biobox 0%
2093 Fan coil unit 0%
2094 Retail 2( subject to receipt of GFW drawings) 0%
2095 substructure 0%
2096 set out 0%
2097 Excavate (Drill in rock to anchor steel rods) 0%
2098 Conc. Foundation 0%
2099 Backfill ( where applicable ) 0%
2100 termite treatment 0%
2101 DPC (where applicable) 0%
2102 M&E inlet/outlet works 0%
2103 frame 0%
2104 set kickers 0%
2105 Conc. Columns & shear walls 0%
2106 Conc. G. F Beams 0%
2107 Conc. Plantroom 0%
2108 Conc. Floor slab 0%
2109 Blockwork 0%
2110 Conc. Ring & tie beams 0%
page 86
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
2111 Roof & Ceiling 0%
2112 Fix wall plate & truss 0%
2113 Fix purlins and rafters 0%
2114 Fix shingles ( subject to receipt of timber) 0%
2115 Fix ceiing battens & joists 0%
2116 Fix ceiling boards 0%
2117 Finishes 0%
2118 Wall plaster (internal & External) 0%
2119 M&E 1st fix 0%
2120 Floor finishes 0%
2121 Fix windows & doors 0%
2122 M&E final fix 0%
2123 Fix fittings and Fixtures 0%
2124 M&E Installations 0%
2125 Cable Tray, Conduit and Wiring 0%
2126 Electrical boards and connections 0%
2127 Electrical accessories 0%
2128 Light fittings and ceiling fans 0%
2129 Hot and cold water 0%
2130 Waste and sewage incl. biobox 0%
2131 Fan coil unit 0%
2132 Retail 3( subject to receipt of GFW drawings) 0%
2133 substructure 0%
2134 set out 0%
2135 Excavate (Drill in rock to anchor steel rods) 0%
2136 Conc. Foundation 0%
2137 Backfill ( where applicable ) 0%
2138 termite treatment 0%
2139 DPC (where applicable) 0%
2140 M&E inlet/outlet works 0%
2141 frame 0%
2142 set kickers 0%
2143 Conc. Columns & shear walls 0%
2144 Conc. G. F Beams 0%
2145 Conc. Plantroom 0%
2146 Conc. Floor slab 0%
2147 Blockwork 0%
2148 Conc. Ring & tie beams 0%
2149 Roof & Ceiling 0%
2150 Fix wall plate & truss 0%
2151 Fix purlins and rafters 0%
2152 Fix shingles ( subject to receipt of timber) 0%
2153 Fix ceiing battens & joists 0%
2154 Fix ceiling boards 0%
2155 Finishes 0%
2156 Wall plaster (internal & External) 0%
2157 M&E 1st fix 0%
2158 Floor finishes 0%
2159 Fix windows & doors 0%
2160 M&E final fix 0%
2161 Fix fittings and Fixtures 0%
2162 M&E Installations 0%
2163 Cable Tray, Conduit and Wiring 0%
2164 Electrical boards and connections 0%
2165 Electrical accessories 0%
2166 Light fittings and ceiling fans 0%
2167 Hot and cold water 0%
2168 Waste and sewage incl. biobox 0%
2169 Fan coil unit 0%
2170 Seafood resort( subject to receipt of GFW drawings) 0%
2171 substructure 0%
2172 set out 0%
2173 Excavate (Drill in rock to anchor steel rods) 0%
2174 Conc. Foundation 0%
2175 Backfill ( where applicable ) 0%
2176 termite treatment 0%
2177 DPC (where applicable) 0%
2178 M&E inlet/outlet works 0%
2179 frame 0%
2180 set kickers 0%
2181 Conc. Columns & shear walls 0%
2182 Conc. G. F Beams 0%
2183 Conc. Plantroom 0%
2184 Conc. Floor slab 0%
2185 Blockwork 0%
2186 Conc. Ring & tie beams 0%
2187 Roof & Ceiling 0%
2188 Fix wall plate & truss 0%
2189 Fix purlins and rafters 0%
2190 Fix shingles ( subject to receipt of timber) 0%
2191 Fix ceiing battens & joists 0%
2192 Fix ceiling boards 0%
2193 Finishes 0%
2194 Wall plaster (internal & External) 0%
2195 M&E 1st fix 0%
2196 Floor finishes 0%
2197 Fix windows & doors 0%
2198 M&E final fix 0%
2199 Fix fittings and Fixtures 0%
2200 M&E Installations 0%
2201 Cable Tray, Conduit and Wiring 0%
2202 Electrical boards and connections 0%
2203 Electrical accessories 0%
2204 Light fittings and ceiling fans 0%
2205 Hot and cold water 0%
2206 Waste and sewage incl. biobox 0%
2207 Kitchen extraction duct 0%
2208 Chilled water piping 0%
2209 Fan coil unit 0%
2210 Toilet ventilation, grilles 0%
2211 Greeting Pavillion( subject to receipt of GFW drawings) 0%
2212 substructure 0%
2213 set out 0%
2214 Excavate (Drill in rock to anchor steel rods) 0%
2215 Conc. Foundation 0%
2216 Backfill ( where applicable ) 0%
2217 termite treatment 0%
2218 DPC (where applicable) 0%
2219 M&E inlet/outlet works 0%
2220 frame 0%
2221 set kickers 0%
2222 Conc. Columns & shear walls 0%
2223 Conc. G. F Beams 0%
2224 Conc. Plantroom 0%
2225 Conc. Floor slab 0%
2226 Blockwork 0%
2227 Conc. Ring & tie beams 0%
page 87
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
2228 Roof & Ceiling 0%
2229 Fix wall plate & truss 0%
2230 Fix purlins and rafters 0%
2231 Fix shingles ( subject to receipt of timber) 0%
2232 Fix ceiing battens & joists 0%
2233 Fix ceiling boards 0%
2234 Finishes 0%
2235 Wall plaster (internal & External) 0%
2236 M&E 1st fix 0%
2237 Floor finishes 0%
2238 Fix windows & doors 0%
2239 M&E final fix 0%
2240 Fix fittings and Fixtures 0%
2241 M&E Installations 0%
2242 Cable Tray, Conduit and Wiring 0%
2243 Electrical boards and connections 0%
2244 Electrical accessories 0%
2245 Light fittings and ceiling fans 0%
2246 Hot and cold water 0%
2247 Waste and sewage incl. biobox 0%
2248 Fan coil unit 0%
2249 Toilet ventilation, grilles 0%
2250 External works ( subject to receipt of GFW drawings) 0%
2251 Infrastructures 0%
2252 Set out road (cabbies), vehicular 0%
2253 Set out Pedestrian walkways 0%
2254 Set out main water pipe alignment 0%
2255 Set out main electricity network 0%
2256 landscaping 0%
2257 Villas milieu 0%
2258 Main access road milieu 0%
2259 Drainage works ( subject to receipt of EME details) 0%
2260 Set out/implement main sewerage network 0%
2261 Set out/implement main rain water drainage alignment 0%
2262 Lot 3 0%
2263 A3 Villas ( 9 nos) 0%
2264 Villa A3/14 0%
2309 Villa A3/15 0%
2354 Villa A3/16 0%
2399 Villa A3/17 0%
2444 Villa A3/28 0%
2445 substructure 0%
2446 set out 0%
2447 Excavate 0%
2448 Conc. Foundation 0%
2449 Backfill 0%
2450 termite treatment 0%
2451 DPC (where applicable) 0%
2452 M&E inlet/outlet works - first fix 0%
2453 frame 0%
2463 Roof & Ceiling 0%
2470 Finishes 0%
2478 M&E Installations 0%
2489 Villa A3/29 0%
2490 substructure 0%
2491 set out 0%
2492 Excavate 0%
2493 Conc. Foundation 0%
2494 Backfill 0%
2495 termite treatment 0%
2496 DPC (where applicable) 0%
2497 M&E inlet/outlet works - first fix 0%
2498 frame 0%
2508 Roof & Ceiling 0%
2515 Finishes 0%
2523 M&E Installations 0%
2534 Villa A3/30 0%
2535 substructure 0%
2536 set out 0%
2537 Excavate 0%
2538 Conc. Foundation 0%
2539 Backfill 0%
2540 termite treatment 0%
2541 DPC (where applicable) 0%
2542 M&E inlet/outlet works - first fix 0%
2543 frame 0%
2553 Roof & Ceiling 0%
2560 Finishes 0%
2568 M&E Installations 0%
2579 Villa A3/31 0%
2624 Villa A3/32 0%
2625 substructure 0%
2626 set out 0%
2627 Excavate 0%
2628 Conc. Foundation 0%
2629 Backfill 0%
2630 termite treatment 0%
2631 DPC (where applicable) 0%
2632 frame 0%
2641 Roof & Ceiling 0%
2647 Finishes 0%
2653 M&E Installations 0%
2664 B223 Villas ( 3 nos) 0%
2665 Villa B2/03 0%
2666 substructure 0%
2667 set out 0%
2668 Excavate 0%
2669 Conc. Foundation 0%
2670 Backfill 0%
2671 termite treatment 0%
2672 DPC (where applicable) 0%
2673 frame 0%
2686 Roof & Ceiling 0%
2692 Finishes 0%
2697 M&E Installations 0%
2708 Villa B2/09 0%
2709 substructure 0%
2710 set out 0%
2711 Excavate 0%
2712 Conc. Foundation 0%
2713 Backfill 0%
2714 termite treatment 0%
2715 DPC (where applicable) 0%
2716 M&E inlet/outlet works - first fix 0%
2717 frame 0%
2733 Roof & Ceiling 0%
page 88
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
2740 Finishes 0%
2747 M&E Installations 0%
2758 Villa B2/10 0%
2759 substructure 0%
2760 set out 0%
2761 Excavate 0%
2762 Conc. Foundation 0%
2763 Backfill 0%
2764 termite treatment 0%
2765 DPC (where applicable) 0%
2766 M&E inlet/outlet works - first fix 0%
2767 frame 0%
2783 Roof & Ceiling 0%
2790 Finishes 0%
2797 M&E Installations 0%
2808 B4 Standard Villas ( 2 nos) 0%
2809 Villa B4/03 0%
2810 substructure 0%
2811 set out 0%
2812 Excavate 0%
2813 Conc. Foundation 0%
2814 Backfill 0%
2815 termite treatment 0%
2816 DPC (where applicable) 0%
2817 M&E inlet/outlet works - first fix 0%
2818 frame 0%
2819 set kickers 0%
2820 Conc. Columns & shear walls 0%
2821 Conc. G. F Beams 0%
2822 M&E first fix 0%
2823 Conc. Plantroom 0%
2824 Conc. Floor slab & swimming pool base 0%
2825 Blockwork 0%
2826 Conc. Swimming pool sides & overflow channels 0%
2827 Conc. Ring & tie beams 0%
2828 Roof & Ceiling 0%
2829 Fix wall plate & truss 0%
2830 Fix purlins and rafters 0%
2831 Fix shingles ( subject to receipt of timber) 0%
2832 Fix ceiing battens & joists 0%
2833 Fix ceiling boards 0%
2834 M&E first fix 0%
2835 Finishes 0%
2836 Wall plaster (internal & External) 0%
2837 M&E 1st fix 0%
2838 Floor finishes 0%
2839 Fix windows & doors 0%
2840 Swimming pool finishes 0%
2841 M&E final fix 0%
2842 Fix fittings and Fixtures 0%
2843 M&E Installations 0%
2844 Cable Tray, Conduit and Wiring 0%
2845 Electrical boards and connections 0%
2846 Electrical accessories 0%
2847 Light fittings and ceiling fans 0%
2848 Hot and cold water 0%
2849 Waste and sewage incl. biobox 0%
2850 Electric water heater 0%
2851 Swimming pool 0%
2852 Split unit installation 0%
2853 Toilet ventilation, grilles 0%
2854 Villa B4/04 0%
2855 substructure 0%
2856 set out 0%
2857 Excavate 0%
2858 Conc. Foundation 0%
2859 Backfill 0%
2860 termite treatment 0%
2861 DPC (where applicable) 0%
2862 M&E inlet/outlet works - first fix 0%
2863 frame 0%
2864 set kickers 0%
2865 Conc. Columns & shear walls 0%
2866 Conc. G. F Beams 0%
2867 M&E first fix 0%
2868 Conc. Plantroom 0%
2869 Conc. Floor slab & swimming pool base 0%
2870 Blockwork 0%
2871 Conc. Swimming pool sides & overflow channels 0%
2872 Conc. Ring & tie beams 0%
2873 Roof & Ceiling 0%
2874 Fix wall plate & truss 0%
2875 Fix purlins and rafters 0%
2876 Fix shingles ( subject to receipt of timber) 0%
2877 Fix ceiing battens & joists 0%
2878 Fix ceiling boards 0%
2879 M&E first fix 0%
2880 Finishes 0%
2881 Wall plaster (internal & External) 0%
2882 M&E 1st fix 0%
2883 Floor finishes 0%
2884 Fix windows & doors 0%
2885 Swimming pool finishes 0%
2886 M&E final fix 0%
2887 Fix fittings and Fixtures 0%
2888 M&E Installations 0%
2889 Cable Tray, Conduit and Wiring 0%
2890 Electrical boards and connections 0%
2891 Electrical accessories 0%
2892 Light fittings and ceiling fans 0%
2893 Hot and cold water 0%
2894 Waste and sewage incl. biobox 0%
2895 Electric water heater 0%
2896 Swimming pool 0%
2897 Split unit installation 0%
2898 Toilet ventilation, grilles 0%
2899 BC311 Executive Villa 0%
2900 Villa C3/02 0%
2943 Villa C3/03 0%
2986 Villa C3/04 0%
3029 Villa C3/05 0%
3072 Villa C3/06 0%
page 89
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
3115 P3 Presidential suites ( 3 nos) 0%
3116 Villa P3/01 0%
3159 Villa P3/02 0%
3202 Villa P3/03 0%
3245 Hilltop sunset deck( subject to receipt of GFW drawings) 0%
3280 External works ( subject to receipt of GFW drawings) 0%
3289 Drainage works ( subject to receipt of EME details) 0%
3290 Set out/implement main sewerage network 0%
3291 Set out/implement main rain water drainage alignment 0%
3292 Lot 4 0%
3293 Couple treatment room( subject to receipt of GFW drawings) 0%
3334 Single treatment room( subject to receipt of GFW drawings) 0%
3375 Dive Centre( subject to receipt of GFW drawings) 0%
3413 Kid's club( subject to receipt of GFW drawings) 0%
3452 Recreation House( subject to receipt of GFW drawings) 0%
3491 Watersports rental( subject to receipt of GFW drawings) 0%
3529 3 Meals restaurant( subject to receipt of GFW drawings) 0%
3570 Beach Pool Bar( subject to receipt of GFW drawings) 0%
3611 Signature Pool area( subject to receipt of GFW drawings) 0%
3650 Wedding Chapel( subject to receipt of GFW drawings) 0%
3685 BOH/Admin Building( subject to receipt of GFW drawings) 0%
3726 Chi Sanctum( subject to receipt of GFW drawings) 0%
3767 Yoga Pavillion( subject to receipt of GFW drawings) 0%
3805 External works ( subject to receipt of GFW drawings) 0%
3814 Drainage works ( subject to receipt of EME details) 0%
3817 M&E Installations- External 0%
3828 Sundries 0%
3829 Site cleaning & demobilisation 0%
3830 Project Commissioning 0%
page 90
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
As a result of the current delay caused by this event the time for
completion has been further extended from 9 August 2008 to 9
September 2009, a period of 396 calendar days.
page 91
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 92
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
642 Roof & Ceiling 0%
643 Fix wall plate & truss 0%
644 Fix purlins and rafters 0%
645 Fix shingles ( subject to receipt of timber) 0%
646 Fix ceiing battens & joists 0%
647 Fix ceiling boards 0%
648 Finishes 0%
649 Wall plaster (internal & External) 0%
650 M&E 1st fix 0%
651 Floor finishes 0%
652 Fix windows & doors 0%
653 M&E final fix 0%
654 Fix fittings and Fixtures 0%
655 M&E Installations 0%
656 Cable Tray, Conduit and Wiring 0%
657 Electrical boards and connections 0%
658 Electrical accessories 0%
659 Light fittings and ceiling fans 0%
660 Hot and cold water 0%
661 Waste and sewage incl. biobox 0%
662 Boiler 0%
663 Chiller 0%
664 Fan coil unit 0%
665 Toilet ventilation, grilles 0%
666 Administration Block ( subject to receipt of GFW drawings) 0%
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings) 0%
708 substructure 0%
709 set out 0%
710 Excavate 0%
711 Conc. Foundation 0%
712 Backfill ( where applicable ) 0%
713 termite treatment 0%
714 DPC (where applicable) 0%
715 M&E inlet/outlet works 0%
716 frame 0%
717 set kickers 0%
718 Conc. Columns & shear walls upto GF floor level 0%
719 Conc. G. F Beams 0%
720 Conc. G.F Floor slab 0%
721 Conc. Columns & shear walls upto FF level 0%
722 Blockwork upto FF level 0%
723 Conc. F. Floor slab 0%
724 Conc. Columns & shear walls upto roof level 0%
725 Blockwork upto roof 0%
726 Conc. Ring & tie beams 0%
727 Roof & Ceiling 0%
728 Fix wall plate & truss 0%
729 Fix purlins and rafters 0%
730 Fix shingles ( subject to receipt of timber) 0%
731 Fix ceiing battens & joists 0%
732 Fix ceiling boards 0%
733 Finishes 0%
734 Wall plaster (internal & External) 0%
735 M&E 1st fix 0%
736 Floor finishes 0%
737 Fix windows & doors 0%
738 M&E final fix 0%
739 Fix fittings and Fixtures 0%
740 M&E Installations 0%
741 Cable Tray, Conduit and Wiring 0%
742 Electrical boards and connections 0%
743 Electrical accessories 0%
744 Light fittings and ceiling fans 0%
745 Hot and cold water 0%
746 Waste and sewage incl. biobox 0%
747 Electric water heater 0%
748 Split unit installation 0%
749 Toilet ventilation, grilles 0%
750 Main Lobby ( subject to receipt of GFW drawings) 0%
791 Tennis Courts ( subject to receipt of GFW drawings) 0%
807 External works ( subject to receipt of GFW drawings) 0%
816 Drainage works ( subject to receipt of EME details) 0%
819 Fuel Farm ( subject to receipt of EME details) 0%
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details) 0%
827 Desalination plant( subject to receipt of EME details) 0%
831 MLV Panel( subject to receipt of EME details) 0%
835 Step Up Transformer( subject to receipt of EME details) 0%
839 Incinerator/ Garbage room( subject to receipt of EME details) 0%
843 Sewer treatement plant( subject to receipt of EME details) 0%
847 Lot 2 0%
848 A3 Villas (17 nos) 0%
1614 B223 Villas ( 7 nos) 0%
1965 B4 Villa (2 nos.) 0%
2056 Retail 1( subject to receipt of GFW drawings) 0%
2057 substructure 0%
2058 set out 0%
2059 Excavate (Drill in rock to anchor steel rods) 0%
2060 Conc. Foundation 0%
2061 Backfill ( where applicable ) 0%
2062 termite treatment 0%
2063 DPC (where applicable) 0%
2064 M&E inlet/outlet works 0%
2065 frame 0%
2066 set kickers 0%
2067 Conc. Columns & shear walls 0%
2068 Conc. G. F Beams 0%
2069 Conc. Plantroom 0%
2070 Conc. Floor slab 0%
2071 Blockwork 0%
2072 Conc. Ring & tie beams 0%
2073 Roof & Ceiling 0%
2074 Fix wall plate & truss 0%
2075 Fix purlins and rafters 0%
2076 Fix shingles ( subject to receipt of timber) 0%
2077 Fix ceiing battens & joists 0%
2078 Fix ceiling boards 0%
2079 Finishes 0%
2080 Wall plaster (internal & External) 0%
2081 M&E 1st fix 0%
2082 Floor finishes 0%
2083 Fix windows & doors 0%
2084 M&E final fix 0%
2085 Fix fittings and Fixtures 0%
page 93
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
2086 M&E Installations 0%
2087 Cable Tray, Conduit and Wiring 0%
2088 Electrical boards and connections 0%
2089 Electrical accessories 0%
2090 Light fittings and ceiling fans 0%
2091 Hot and cold water 0%
2092 Waste and sewage incl. biobox 0%
2093 Fan coil unit 0%
2094 Retail 2( subject to receipt of GFW drawings) 0%
2095 substructure 0%
2096 set out 0%
2097 Excavate (Drill in rock to anchor steel rods) 0%
2098 Conc. Foundation 0%
2099 Backfill ( where applicable ) 0%
2100 termite treatment 0%
2101 DPC (where applicable) 0%
2102 M&E inlet/outlet works 0%
2103 frame 0%
2104 set kickers 0%
2105 Conc. Columns & shear walls 0%
2106 Conc. G. F Beams 0%
2107 Conc. Plantroom 0%
2108 Conc. Floor slab 0%
2109 Blockwork 0%
2110 Conc. Ring & tie beams 0%
2111 Roof & Ceiling 0%
2112 Fix wall plate & truss 0%
2113 Fix purlins and rafters 0%
2114 Fix shingles ( subject to receipt of timber) 0%
2115 Fix ceiing battens & joists 0%
2116 Fix ceiling boards 0%
2117 Finishes 0%
2118 Wall plaster (internal & External) 0%
2119 M&E 1st fix 0%
2120 Floor finishes 0%
2121 Fix windows & doors 0%
2122 M&E final fix 0%
2123 Fix fittings and Fixtures 0%
2124 M&E Installations 0%
2125 Cable Tray, Conduit and Wiring 0%
2126 Electrical boards and connections 0%
2127 Electrical accessories 0%
2128 Light fittings and ceiling fans 0%
2129 Hot and cold water 0%
2130 Waste and sewage incl. biobox 0%
2131 Fan coil unit 0%
2132 Retail 3( subject to receipt of GFW drawings) 0%
2133 substructure 0%
2134 set out 0%
2135 Excavate (Drill in rock to anchor steel rods) 0%
2136 Conc. Foundation 0%
2137 Backfill ( where applicable ) 0%
2138 termite treatment 0%
2139 DPC (where applicable) 0%
2140 M&E inlet/outlet works 0%
2141 frame 0%
2142 set kickers 0%
2143 Conc. Columns & shear walls 0%
2144 Conc. G. F Beams 0%
2145 Conc. Plantroom 0%
2146 Conc. Floor slab 0%
2147 Blockwork 0%
2148 Conc. Ring & tie beams 0%
2149 Roof & Ceiling 0%
2150 Fix wall plate & truss 0%
2151 Fix purlins and rafters 0%
2152 Fix shingles ( subject to receipt of timber) 0%
2153 Fix ceiing battens & joists 0%
2154 Fix ceiling boards 0%
2155 Finishes 0%
2156 Wall plaster (internal & External) 0%
2157 M&E 1st fix 0%
2158 Floor finishes 0%
2159 Fix windows & doors 0%
2160 M&E final fix 0%
2161 Fix fittings and Fixtures 0%
2162 M&E Installations 0%
2163 Cable Tray, Conduit and Wiring 0%
2164 Electrical boards and connections 0%
2165 Electrical accessories 0%
2166 Light fittings and ceiling fans 0%
2167 Hot and cold water 0%
2168 Waste and sewage incl. biobox 0%
2169 Fan coil unit 0%
2170 Seafood resort( subject to receipt of GFW drawings) 0%
2171 substructure 0%
2172 set out 0%
2173 Excavate (Drill in rock to anchor steel rods) 0%
2174 Conc. Foundation 0%
2175 Backfill ( where applicable ) 0%
2176 termite treatment 0%
2177 DPC (where applicable) 0%
2178 M&E inlet/outlet works 0%
2179 frame 0%
2180 set kickers 0%
2181 Conc. Columns & shear walls 0%
2182 Conc. G. F Beams 0%
2183 Conc. Plantroom 0%
2184 Conc. Floor slab 0%
2185 Blockwork 0%
2186 Conc. Ring & tie beams 0%
2187 Roof & Ceiling 0%
2188 Fix wall plate & truss 0%
2189 Fix purlins and rafters 0%
2190 Fix shingles ( subject to receipt of timber) 0%
2191 Fix ceiing battens & joists 0%
2192 Fix ceiling boards 0%
2193 Finishes 0%
2194 Wall plaster (internal & External) 0%
2195 M&E 1st fix 0%
2196 Floor finishes 0%
2197 Fix windows & doors 0%
2198 M&E final fix 0%
2199 Fix fittings and Fixtures 0%
page 94
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
2200 M&E Installations 0%
2201 Cable Tray, Conduit and Wiring 0%
2202 Electrical boards and connections 0%
2203 Electrical accessories 0%
2204 Light fittings and ceiling fans 0%
2205 Hot and cold water 0%
2206 Waste and sewage incl. biobox 0%
2207 Kitchen extraction duct 0%
2208 Chilled water piping 0%
2209 Fan coil unit 0%
2210 Toilet ventilation, grilles 0%
2211 Greeting Pavillion( subject to receipt of GFW drawings) 0%
2250 External works ( subject to receipt of GFW drawings) 0%
2259 Drainage works ( subject to receipt of EME details) 0%
2262 Lot 3 0%
2263 A3 Villas ( 9 nos) 0%
2664 B223 Villas ( 3 nos) 0%
2808 B4 Standard Villas ( 2 nos) 0%
2899 BC311 Executive Villa 0%
3115 P3 Presidential suites ( 3 nos) 0%
3116 Villa P3/01 0%
3117 substructure 0%
3118 set out 0%
3119 Excavate 0%
3120 Conc. Foundation 0%
3121 Backfill ( where applicable ) 0%
3122 termite treatment 0%
3123 DPC (where applicable) 0%
3124 M&E inlet/outlet works 0%
3125 frame 0%
3126 set kickers 0%
3127 Conc. Columns & shear walls 0%
3128 Conc. G. F Beams 0%
3129 Conc. Plantroom 0%
3130 Conc. Floor slab & swimming pool base 0%
3131 Blockwork 0%
3132 Conc. Swimming pool sides & overflow channels 0%
3133 Conc. Ring & tie beams 0%
3134 Roof & Ceiling 0%
3135 Fix wall plate & truss 0%
3136 Fix purlins and rafters 0%
3137 Fix shingles ( subject to receipt of timber) 0%
3138 Fix ceiing battens & joists 0%
3139 Fix ceiling boards 0%
3140 Finishes 0%
3141 Wall plaster (internal & External) 0%
3142 M&E 1st fix 0%
3143 Floor finishes 0%
3144 Fix windows & doors 0%
3145 Swimming pool finishes 0%
3146 M&E final fix 0%
3147 Fix fittings and Fixtures 0%
3148 M&E Installations 0%
3149 Cable Tray, Conduit and Wiring 0%
3150 Electrical boards and connections 0%
3151 Electrical accessories 0%
3152 Light fittings and ceiling fans 0%
3153 Hot and cold water 0%
3154 Waste and sewage incl. biobox 0%
3155 Electric water heater 0%
3156 Swimming pool 0%
3157 Split unit installation 0%
3158 Toilet ventilation, grilles 0%
3159 Villa P3/02 0%
3160 substructure 0%
3161 set out 0%
3162 Excavate 0%
3163 Conc. Foundation 0%
3164 Backfill ( where applicable ) 0%
3165 termite treatment 0%
3166 DPC (where applicable) 0%
3167 M&E inlet/outlet works 0%
3168 frame 0%
3169 set kickers 0%
3170 Conc. Columns & shear walls 0%
3171 Conc. G. F Beams 0%
3172 Conc. Plantroom 0%
3173 Conc. Floor slab & swimming pool base 0%
3174 Blockwork 0%
3175 Conc. Swimming pool sides & overflow channels 0%
3176 Conc. Ring & tie beams 0%
3177 Roof & Ceiling 0%
3178 Fix wall plate & truss 0%
3179 Fix purlins and rafters 0%
3180 Fix shingles ( subject to receipt of timber) 0%
3181 Fix ceiing battens & joists 0%
3182 Fix ceiling boards 0%
3183 Finishes 0%
3184 Wall plaster (internal & External) 0%
3185 M&E 1st fix 0%
3186 Floor finishes 0%
3187 Fix windows & doors 0%
3188 Swimming pool finishes 0%
3189 M&E final fix 0%
3190 Fix fittings and Fixtures 0%
3191 M&E Installations 0%
3192 Cable Tray, Conduit and Wiring 0%
3193 Electrical boards and connections 0%
3194 Electrical accessories 0%
3195 Light fittings and ceiling fans 0%
3196 Hot and cold water 0%
3197 Waste and sewage incl. biobox 0%
3198 Electric water heater 0%
3199 Swimming pool 0%
3200 Split unit installation 0%
3201 Toilet ventilation, grilles 0%
3202 Villa P3/03 0%
3203 substructure 0%
3204 set out 0%
3205 Excavate 0%
3206 Conc. Foundation 0%
3207 Backfill ( where applicable ) 0%
3208 termite treatment 0%
3209 DPC (where applicable) 0%
3210 M&E inlet/outlet works 0%
page 95
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
3211 frame 0%
3220 Roof & Ceiling 0%
3226 Finishes 0%
3234 M&E Installations 0%
3235 Cable Tray, Conduit and Wiring 0%
3236 Electrical boards and connections 0%
3237 Electrical accessories 0%
3238 Light fittings and ceiling fans 0%
3239 Hot and cold water 0%
3240 Waste and sewage incl. biobox 0%
3241 Electric water heater 0%
3242 Swimming pool 0%
3243 Split unit installation 0%
3244 Toilet ventilation, grilles 0%
3245 Hilltop sunset deck( subject to receipt of GFW drawings) 0%
3246 substructure 0%
3247 set out 0%
3248 Excavate 0%
3249 Conc. Foundation 0%
3250 Backfill ( where applicable ) 0%
3251 termite treatment 0%
3252 DPC (where applicable) 0%
3253 M&E inlet/outlet works 0%
3254 frame 0%
3255 set kickers 0%
3256 Conc. Columns & shear walls 0%
3257 Conc. G. F Beams 0%
3258 Conc. Plantroom 0%
3259 Conc. Floor slab 0%
3260 Blockwork 0%
3261 Conc. Ring & tie beams 0%
3262 Roof & Ceiling 0%
3263 Fix wall plate & truss 0%
3264 Fix purlins and rafters 0%
3265 Fix shingles ( subject to receipt of timber) 0%
3266 Fix ceiing battens & joists 0%
3267 Fix ceiling boards 0%
3268 Finishes 0%
3269 Wall plaster (internal & External) 0%
3270 M&E 1st fix 0%
3271 Floor finishes 0%
3272 Fix windows & doors 0%
3273 M&E final fix 0%
3274 Fix fittings and Fixtures 0%
3275 M&E Installations 0%
3276 Cable Tray, Conduit and Wiring 0%
3277 Electrical boards and connections 0%
3278 Electrical accessories 0%
3279 Light fittings and ceiling fans 0%
3280 External works ( subject to receipt of GFW drawings) 0%
3289 Drainage works ( subject to receipt of EME details) 0%
3292 Lot 4 0%
3293 Couple treatment room( subject to receipt of GFW drawings) 0%
3294 substructure 0%
3295 set out 0%
3296 Excavate 0%
3297 Conc. Foundation 0%
3298 Backfill ( where applicable ) 0%
3299 termite treatment 0%
3300 DPC (where applicable) 0%
3301 M&E inlet/outlet works 0%
3302 frame 0%
3303 set kickers 0%
3304 Conc. Columns & shear walls 0%
3305 Conc. G. F Beams 0%
3306 Conc. Plantroom 0%
3307 Conc. Floor slab 0%
3308 Blockwork 0%
3309 Conc. Ring & tie beams 0%
3310 Roof & Ceiling 0%
3311 Fix wall plate & truss 0%
3312 Fix purlins and rafters 0%
3313 Fix shingles ( subject to receipt of timber) 0%
3314 Fix ceiing battens & joists 0%
3315 Fix ceiling boards 0%
3316 Finishes 0%
3317 Wall plaster (internal & External) 0%
3318 M&E 1st fix 0%
3319 Floor finishes 0%
3320 Fix windows & doors 0%
3321 M&E final fix 0%
3322 Fix fittings and Fixtures 0%
3323 M&E Installations 0%
3324 Cable Tray, Conduit and Wiring 0%
3325 Electrical boards and connections 0%
3326 Electrical accessories 0%
3327 Light fittings and ceiling fans 0%
3328 Hot and cold water 0%
3329 Waste and sewage incl. biobox 0%
3330 Electric water heater 0%
3331 Water feature 0%
3332 Split unit installation 0%
3333 Toilet ventilation, grilles 0%
3334 Single treatment room( subject to receipt of GFW drawings) 0%
3335 substructure 0%
3336 set out 0%
3337 Excavate 0%
3338 Conc. Foundation 0%
3339 Backfill ( where applicable ) 0%
3340 termite treatment 0%
3341 DPC (where applicable) 0%
3342 M&E inlet/outlet works 0%
3343 frame 0%
3344 set kickers 0%
3345 Conc. Columns & shear walls 0%
3346 Conc. G. F Beams 0%
3347 Conc. Plantroom 0%
3348 Conc. Floor slab 0%
3349 Blockwork 0%
3350 Conc. Ring & tie beams 0%
3351 Roof & Ceiling 0%
3352 Fix wall plate & truss 0%
3353 Fix purlins and rafters 0%
3354 Fix shingles ( subject to receipt of timber) 0%
3355 Fix ceiing battens & joists 0%
3356 Fix ceiling boards 0%
page 96
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
3357 Finishes 0%
3358 Wall plaster (internal & External) 0%
3359 M&E 1st fix 0%
3360 Floor finishes 0%
3361 Fix windows & doors 0%
3362 M&E final fix 0%
3363 Fix fittings and Fixtures 0%
3364 M&E Installations 0%
3365 Cable Tray, Conduit and Wiring 0%
3366 Electrical boards and connections 0%
3367 Electrical accessories 0%
3368 Light fittings and ceiling fans 0%
3369 Hot and cold water 0%
3370 Waste and sewage incl. biobox 0%
3371 Electric water heater 0%
3372 Water feature 0%
3373 Split unit installation 0%
3374 Toilet ventilation, grilles 0%
3375 Dive Centre( subject to receipt of GFW drawings) 0%
3376 substructure 0%
3377 set out 0%
3378 Excavate 0%
3379 Conc. Foundation 0%
3380 Backfill ( where applicable ) 0%
3381 termite treatment 0%
3382 DPC (where applicable) 0%
3383 M&E inlet/outlet works 0%
3384 frame 0%
3385 set kickers 0%
3386 Conc. Columns & shear walls 0%
3387 Conc. G. F Beams 0%
3388 Conc. Plantroom 0%
3389 Conc. Floor slab 0%
3390 Blockwork 0%
3391 Conc. Ring & tie beams 0%
3392 Roof & Ceiling 0%
3393 Fix wall plate & truss 0%
3394 Fix purlins and rafters 0%
3395 Fix shingles ( subject to receipt of timber) 0%
3396 Fix ceiing battens & joists 0%
3397 Fix ceiling boards 0%
3398 Finishes 0%
3399 Wall plaster (internal & External) 0%
3400 M&E 1st fix 0%
3401 Floor finishes 0%
3402 Fix windows & doors 0%
3403 M&E final fix 0%
3404 Fix fittings and Fixtures 0%
3405 M&E Installations 0%
3406 Cable Tray, Conduit and Wiring 0%
3407 Electrical boards and connections 0%
3408 Electrical accessories 0%
3409 Light fittings and ceiling fans 0%
3410 Hot and cold water 0%
3411 Waste and sewage incl. biobox 0%
3412 Toilet ventilation, grilles 0%
3413 Kid's club( subject to receipt of GFW drawings) 0%
3414 substructure 0%
3415 set out 0%
3416 Excavate 0%
3417 Conc. Foundation 0%
3418 Backfill ( where applicable ) 0%
3419 termite treatment 0%
3420 DPC (where applicable) 0%
3421 M&E inlet/outlet works 0%
3422 frame 0%
3423 set kickers 0%
3424 Conc. Columns & shear walls 0%
3425 Conc. G. F Beams 0%
3426 Conc. Plantroom 0%
3427 Conc. Floor slab 0%
3428 Blockwork 0%
3429 Conc. Ring & tie beams 0%
3430 Roof & Ceiling 0%
3431 Fix wall plate & truss 0%
3432 Fix purlins and rafters 0%
3433 Fix shingles ( subject to receipt of timber) 0%
3434 Fix ceiing battens & joists 0%
3435 Fix ceiling boards 0%
3436 Finishes 0%
3437 Wall plaster (internal & External) 0%
3438 M&E 1st fix 0%
3439 Floor finishes 0%
3440 Fix windows & doors 0%
3441 M&E final fix 0%
3442 Fix fittings and Fixtures 0%
3443 M&E Installations 0%
3444 Cable Tray, Conduit and Wiring 0%
3445 Electrical boards and connections 0%
3446 Electrical accessories 0%
3447 Light fittings and ceiling fans 0%
3448 Hot and cold water 0%
3449 Waste and sewage incl. biobox 0%
3450 Electric water heater 0%
3451 Toilet ventilation, grilles 0%
3452 Recreation House( subject to receipt of GFW drawings) 0%
3453 substructure 0%
3454 set out 0%
3455 Excavate 0%
3456 Conc. Foundation 0%
3457 Backfill ( where applicable ) 0%
3458 termite treatment 0%
3459 DPC (where applicable) 0%
3460 M&E inlet/outlet works 0%
3461 frame 0%
3462 set kickers 0%
3463 Conc. Columns & shear walls 0%
3464 Conc. G. F Beams 0%
3465 Conc. Plantroom 0%
3466 Conc. Floor slab 0%
3467 Blockwork 0%
3468 Conc. Ring & tie beams 0%
3469 Roof & Ceiling 0%
3470 Fix wall plate & truss 0%
3471 Fix purlins and rafters 0%
3472 Fix shingles ( subject to receipt of timber) 0%
page 97
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
3473 Fix ceiing battens & joists 0%
3474 Fix ceiling boards 0%
3475 Finishes 0%
3476 Wall plaster (internal & External) 0%
3477 M&E 1st fix 0%
3478 Floor finishes 0%
3479 Fix windows & doors 0%
3480 M&E final fix 0%
3481 Fix fittings and Fixtures 0%
3482 M&E Installations 0%
3483 Cable Tray, Conduit and Wiring 0%
3484 Electrical boards and connections 0%
3485 Electrical accessories 0%
3486 Light fittings and ceiling fans 0%
3487 Hot and cold water 0%
3488 Waste and sewage incl. biobox 0%
3489 Electric water heater 0%
3490 Toilet ventilation, grilles 0%
3491 Watersports rental( subject to receipt of GFW drawings) 0%
3492 substructure 0%
3493 set out 0%
3494 Excavate 0%
3495 Conc. Foundation 0%
3496 Backfill ( where applicable ) 0%
3497 termite treatment 0%
3498 DPC (where applicable) 0%
3499 M&E inlet/outlet works 0%
3500 frame 0%
3501 set kickers 0%
3502 Conc. Columns & shear walls 0%
3503 Conc. G. F Beams 0%
3504 Conc. Plantroom 0%
3505 Conc. Floor slab 0%
3506 Blockwork 0%
3507 Conc. Ring & tie beams 0%
3508 Roof & Ceiling 0%
3509 Fix wall plate & truss 0%
3510 Fix purlins and rafters 0%
3511 Fix shingles ( subject to receipt of timber) 0%
3512 Fix ceiing battens & joists 0%
3513 Fix ceiling boards 0%
3514 Finishes 0%
3515 Wall plaster (internal & External) 0%
3516 M&E 1st fix 0%
3517 Floor finishes 0%
3518 Fix windows & doors 0%
3519 M&E final fix 0%
3520 Fix fittings and Fixtures 0%
3521 M&E Installations 0%
3522 Cable Tray, Conduit and Wiring 0%
3523 Electrical boards and connections 0%
3524 Electrical accessories 0%
3525 Light fittings and ceiling fans 0%
3526 Hot and cold water 0%
3527 Waste and sewage incl. biobox 0%
3528 Toilet ventilation, grilles 0%
3529 3 Meals restaurant( subject to receipt of GFW drawings) 0%
3530 substructure 0%
3531 set out 0%
3532 Excavate 0%
3533 Conc. Foundation 0%
3534 Backfill ( where applicable ) 0%
3535 termite treatment 0%
3536 DPC (where applicable) 0%
3537 M&E inlet/outlet works 0%
3538 frame 0%
3539 set kickers 0%
3540 Conc. Columns & shear walls 0%
3541 Conc. G. F Beams 0%
3542 Conc. Plantroom 0%
3543 Conc. Floor slab 0%
3544 Blockwork 0%
3545 Conc. Ring & tie beams 0%
3546 Roof & Ceiling 0%
3547 Fix wall plate & truss 0%
3548 Fix purlins and rafters 0%
3549 Fix shingles ( subject to receipt of timber) 0%
3550 Fix ceiing battens & joists 0%
3551 Fix ceiling boards 0%
3552 Finishes 0%
3553 Wall plaster (internal & External) 0%
3554 M&E 1st fix 0%
3555 Floor finishes 0%
3556 Fix windows & doors 0%
3557 M&E final fix 0%
3558 Fix fittings and Fixtures 0%
3559 M&E Installations 0%
3560 Cable Tray, Conduit and Wiring 0%
3561 Electrical boards and connections 0%
3562 Electrical accessories 0%
3563 Light fittings and ceiling fans 0%
3564 Hot and cold water 0%
3565 Waste and sewage incl. biobox 0%
3566 Boiler 0%
3567 Chiller 0%
3568 Fan coil unit 0%
3569 Ducting and fans 0%
3570 Beach Pool Bar( subject to receipt of GFW drawings) 0%
3571 substructure 0%
3572 set out 0%
3573 Excavate 0%
3574 Conc. Foundation 0%
3575 Backfill ( where applicable ) 0%
3576 termite treatment 0%
3577 DPC (where applicable) 0%
3578 M&E inlet/outlet works 0%
3579 frame 0%
3580 set kickers 0%
3581 Conc. Columns & shear walls 0%
3582 Conc. G. F Beams 0%
3583 Conc. Plantroom 0%
3584 Conc. Floor slab 0%
3585 Blockwork 0%
3586 Conc. Ring & tie beams 0%
page 98
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
3587 Roof & Ceiling 0%
3588 Fix wall plate & truss 0%
3589 Fix purlins and rafters 0%
3590 Fix shingles ( subject to receipt of timber) 0%
3591 Fix ceiing battens & joists 0%
3592 Fix ceiling boards 0%
3593 Finishes 0%
3594 Wall plaster (internal & External) 0%
3595 M&E 1st fix 0%
3596 Floor finishes 0%
3597 Fix windows & doors 0%
3598 M&E final fix 0%
3599 Fix fittings and Fixtures 0%
3600 M&E Installations 0%
3601 Cable Tray, Conduit and Wiring 0%
3602 Electrical boards and connections 0%
3603 Electrical accessories 0%
3604 Light fittings and ceiling fans 0%
3605 Hot and cold water 0%
3606 Waste and sewage incl. biobox 0%
3607 Electric water heater 0%
3608 Beach Pool 0%
3609 Split unit installation 0%
3610 Toilet ventilation, grilles 0%
3611 Signature Pool area( subject to receipt of GFW drawings) 0%
3612 substructure 0%
3613 set out 0%
3614 Excavate 0%
3615 Conc. Foundation 0%
3616 Backfill ( where applicable ) 0%
3617 termite treatment 0%
3618 DPC (where applicable) 0%
3619 M&E inlet/outlet works 0%
3620 frame 0%
3621 set kickers 0%
3622 Conc. Columns & shear walls 0%
3623 Conc. G. F Beams 0%
3624 Conc. Plantroom 0%
3625 Conc. Floor slab 0%
3626 Blockwork 0%
3627 Conc. Ring & tie beams 0%
3628 Roof & Ceiling 0%
3629 Fix wall plate & truss 0%
3630 Fix purlins and rafters 0%
3631 Fix shingles ( subject to receipt of timber) 0%
3632 Fix ceiing battens & joists 0%
3633 Fix ceiling boards 0%
3634 Finishes 0%
3635 Wall plaster (internal & External) 0%
3636 M&E 1st fix 0%
3637 Floor finishes 0%
3638 Fix windows & doors 0%
3639 M&E final fix 0%
3640 Fix fittings and Fixtures 0%
3641 M&E Installations 0%
3642 Cable Tray, Conduit and Wiring 0%
3643 Electrical boards and connections 0%
3644 Electrical accessories 0%
3645 Light fittings and ceiling fans 0%
3646 Hot and cold water 0%
3647 Waste and sewage incl. biobox 0%
3648 Electric water heater 0%
3649 Signature Pool 0%
3650 Wedding Chapel( subject to receipt of GFW drawings) 0%
3651 substructure 0%
3652 set out 0%
3653 Excavate 0%
3654 Conc. Foundation 0%
3655 Backfill ( where applicable ) 0%
3656 termite treatment 0%
3657 DPC (where applicable) 0%
3658 M&E inlet/outlet works 0%
3659 frame 0%
3660 set kickers 0%
3661 Conc. Columns & shear walls 0%
3662 Conc. G. F Beams 0%
3663 Conc. Plantroom 0%
3664 Conc. Floor slab 0%
3665 Blockwork 0%
3666 Conc. Ring & tie beams 0%
3667 Roof & Ceiling 0%
3668 Fix wall plate & truss 0%
3669 Fix purlins and rafters 0%
3670 Fix shingles ( subject to receipt of timber) 0%
3671 Fix ceiing battens & joists 0%
3672 Fix ceiling boards 0%
3673 Finishes 0%
3674 Wall plaster (internal & External) 0%
3675 M&E 1st fix 0%
3676 Floor finishes 0%
3677 Fix windows & doors 0%
3678 M&E final fix 0%
3679 Fix fittings and Fixtures 0%
3680 M&E Installations 0%
3681 Cable Tray, Conduit and Wiring 0%
3682 Electrical boards and connections 0%
3683 Electrical accessories 0%
3684 Light fittings and ceiling fans 0%
3685 BOH/Admin Building( subject to receipt of GFW drawings) 0%
3686 substructure 0%
3687 set out 0%
3688 Excavate 0%
3689 Conc. Foundation 0%
3690 Backfill ( where applicable ) 0%
3691 termite treatment 0%
3692 DPC (where applicable) 0%
3693 M&E inlet/outlet works 0%
3694 frame 0%
3695 set kickers 0%
3696 Conc. Columns & shear walls 0%
3697 Conc. G. F Beams 0%
3698 Conc. Plantroom 0%
3699 Conc. Floor slab 0%
3700 Blockwork 0%
3701 Conc. Ring & tie beams 0%
page 99
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
3702 Roof & Ceiling 0%
3703 Fix wall plate & truss 0%
3704 Fix purlins and rafters 0%
3705 Fix shingles ( subject to receipt of timber) 0%
3706 Fix ceiing battens & joists 0%
3707 Fix ceiling boards 0%
3708 Finishes 0%
3709 Wall plaster (internal & External) 0%
3710 M&E 1st fix 0%
3711 Floor finishes 0%
3712 Fix windows & doors 0%
3713 M&E final fix 0%
3714 Fix fittings and Fixtures 0%
3715 M&E Installations 0%
3716 Cable Tray, Conduit and Wiring 0%
3717 Electrical boards and connections 0%
3718 Electrical accessories 0%
3719 Light fittings and ceiling fans 0%
3720 Hot and cold water 0%
3721 Waste and sewage incl. biobox 0%
3722 Electric water heater 0%
3723 Pond 0%
3724 Split unit installation 0%
3725 Toilet ventilation, grilles 0%
3726 Chi Sanctum( subject to receipt of GFW drawings) 0%
3727 substructure 0%
3728 set out 0%
3729 Excavate 0%
3730 Conc. Foundation 0%
3731 Backfill ( where applicable ) 0%
3732 termite treatment 0%
3733 DPC (where applicable) 0%
3734 M&E inlet/outlet works 0%
3735 frame 0%
3736 set kickers 0%
3737 Conc. Columns & shear walls 0%
3738 Conc. G. F Beams 0%
3739 Conc. Plantroom 0%
3740 Conc. Floor slab 0%
3741 Blockwork 0%
3742 Conc. Ring & tie beams 0%
3743 Roof & Ceiling 0%
3744 Fix wall plate & truss 0%
3745 Fix purlins and rafters 0%
3746 Fix shingles ( subject to receipt of timber) 0%
3747 Fix ceiing battens & joists 0%
3748 Fix ceiling boards 0%
3749 Finishes 0%
3750 Wall plaster (internal & External) 0%
3751 M&E 1st fix 0%
3752 Floor finishes 0%
3753 Fix windows & doors 0%
3754 M&E final fix 0%
3755 Fix fittings and Fixtures 0%
3756 M&E Installations 0%
3757 Cable Tray, Conduit and Wiring 0%
3758 Electrical boards and connections 0%
3759 Electrical accessories 0%
3760 Light fittings and ceiling fans 0%
3761 Hot and cold water 0%
3762 Waste and sewage incl. biobox 0%
3763 Electric water heater 0%
3764 Pond 0%
3765 Split unit installation 0%
3766 Toilet ventilation, grilles 0%
3767 Yoga Pavillion( subject to receipt of GFW drawings) 0%
3768 substructure 0%
3769 set out 0%
3770 Excavate 0%
3771 Conc. Foundation 0%
3772 Backfill ( where applicable ) 0%
3773 termite treatment 0%
3774 DPC (where applicable) 0%
3775 M&E inlet/outlet works 0%
3776 frame 0%
3777 set kickers 0%
3778 Conc. Columns & shear walls 0%
3779 Conc. G. F Beams 0%
3780 Conc. Plantroom 0%
3781 Conc. Floor slab 0%
3782 Blockwork 0%
3783 Conc. Ring & tie beams 0%
3784 Roof & Ceiling 0%
3785 Fix wall plate & truss 0%
3786 Fix purlins and rafters 0%
3787 Fix shingles ( subject to receipt of timber) 0%
3788 Fix ceiing battens & joists 0%
3789 Fix ceiling boards 0%
3790 Finishes 0%
3791 Wall plaster (internal & External) 0%
3792 M&E 1st fix 0%
3793 Floor finishes 0%
3794 Fix windows & doors 0%
3795 M&E final fix 0%
3796 Fix fittings and Fixtures 0%
3797 M&E Installations 0%
3798 Cable Tray, Conduit and Wiring 0%
3799 Electrical boards and connections 0%
3800 Electrical accessories 0%
3801 Light fittings and ceiling fans 0%
3802 Hot and cold water 0%
3803 Waste and sewage incl. biobox 0%
3804 Electric water heater 0%
3805 External works ( subject to receipt of GFW drawings) 0%
3814 Drainage works ( subject to receipt of EME details) 0%
3817 M&E Installations- External 0%
3828 Sundries 0%
3829 Site cleaning & demobilisation 0%
3830 Project Commissioning 0%
page 100
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
The reason for this is the earlier delays caused by setting out
and unforeseen ground conditions extended and revised the
original start dates of many activities. Consequently, as the
buildings revised schedule start date is much later than originally
planned drawings issued for construction had no impact.
As a result of the current delay caused by this event the time for
completion has not extended the current revised date of 9
September 2009.
page 101
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 102
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
378 Conc. Floor slab & swimming pool base 0%
379 Blockwork 0%
380 Conc. Swimming pool sides & overflow channels 0%
381 Conc. Ring & tie beams 0%
382 Roof & Ceiling 0%
383 Fix wall plate & truss 0%
384 Fix purlins and rafters 0%
385 Fix shingles ( subject to receipt of timber) 0%
386 Fix ceiing battens & joists 0%
387 Fix ceiling boards 0%
388 M&E first fix 0%
389 Finishes 0%
390 Wall plaster (internal & External) 0%
391 M&E 1st fix 0%
392 Floor finishes 0%
393 Fix windows & doors 0%
394 Swimming pool finishes 0%
395 M&E final fix 0%
396 Fix fittings and Fixtures 0%
397 M&E Installations 0%
398 Cable Tray, Conduit and Wiring 0%
399 Electrical boards and connections 0%
400 Electrical accessories 0%
401 Light fittings and ceiling fans 0%
402 Hot and cold water 0%
403 Waste and sewage incl. biobox 0%
404 Electric water heater 0%
405 Swimming pool 0%
406 Split unit installation 0%
407 Toilet ventilation, grilles 0%
408 Villa A3/06 0%
409 substructure 0%
410 set out 0%
411 Excavate 0%
412 Conc. Foundation 0%
413 Backfill 0%
414 termite treatment 0%
415 DPC (where applicable) 0%
416 M&E inlet/outlet works - first fix 0%
417 frame 0%
418 set kickers 0%
419 Conc. Columns & shear walls 0%
420 Conc. G. F Beams 0%
421 M&E first fix 0%
422 Conc. Plantroom 0%
423 Conc. Floor slab & swimming pool base 0%
424 Blockwork 0%
425 Conc. Swimming pool sides & overflow channels 0%
426 Conc. Ring & tie beams 0%
427 Roof & Ceiling 0%
434 Finishes 0%
442 M&E Installations 0%
453 C311 Executive Villas ( 1 nos) 0%
497 GM Villa ( subject to receipt of GFW drawings) 0%
537 Employees Facilities ( subject to receipt of GFW drawings) 0%
581 Laundry F& B service office ( subject to receipt of GFW drawings) 0%
625 Health Club/ Medical Centre( subject to receipt of GFW drawings) 0%
666 Administration Block ( subject to receipt of GFW drawings) 0%
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings) 0%
750 Main Lobby ( subject to receipt of GFW drawings) 0%
791 Tennis Courts ( subject to receipt of GFW drawings) 0%
807 External works ( subject to receipt of GFW drawings) 0%
816 Drainage works ( subject to receipt of EME details) 0%
819 Fuel Farm ( subject to receipt of EME details) 0%
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details) 0%
827 Desalination plant( subject to receipt of EME details) 0%
831 MLV Panel( subject to receipt of EME details) 0%
835 Step Up Transformer( subject to receipt of EME details) 0%
839 Incinerator/ Garbage room( subject to receipt of EME details) 0%
843 Sewer treatement plant( subject to receipt of EME details) 0%
847 Lot 2 0%
848 A3 Villas (17 nos) 0%
849 Villa A3/07 0%
850 substructure 0%
851 set out 0%
852 Excavate 0%
853 Conc. Foundation 0%
854 Backfill 0%
855 termite treatment 0%
856 DPC (where applicable) 0%
857 M&E inlet/outlet works - first fix 0%
858 frame 0%
859 set kickers 0%
860 Conc. Columns & shear walls 0%
861 Conc. G. F Beams 0%
862 M&E first fix 0%
863 Conc. Plantroom 0%
864 Conc. Floor slab & swimming pool base 0%
865 Blockwork 0%
866 Conc. Swimming pool sides & overflow channels 0%
867 Conc. Ring & tie beams 0%
868 Roof & Ceiling 0%
869 Fix wall plate & truss 0%
870 Fix purlins and rafters 0%
871 Fix shingles ( subject to receipt of timber) 0%
872 Fix ceiing battens & joists 0%
873 Fix ceiling boards 0%
874 M&E first fix 0%
875 Finishes 0%
876 Wall plaster (internal & External) 0%
877 M&E 1st fix 0%
878 Floor finishes 0%
879 Fix windows & doors 0%
880 Swimming pool finishes 0%
881 M&E final fix 0%
882 Fix fittings and Fixtures 0%
883 M&E Installations 0%
884 Cable Tray, Conduit and Wiring 0%
885 Electrical boards and connections 0%
886 Electrical accessories 0%
887 Light fittings and ceiling fans 0%
888 Hot and cold water 0%
889 Waste and sewage incl. biobox 0%
890 Electric water heater 0%
891 Swimming pool 0%
892 Split unit installation 0%
893 Toilet ventilation, grilles 0%
page 103
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
894 Villa A3/08 0%
895 substructure 0%
896 set out 0%
897 Excavate 0%
898 Conc. Foundation 0%
899 Backfill 0%
900 termite treatment 0%
901 DPC (where applicable) 0%
902 M&E inlet/outlet works - first fix 0%
903 frame 0%
904 set kickers 0%
905 Conc. Columns & shear walls 0%
906 Conc. G. F Beams 0%
907 M&E first fix 0%
908 Conc. Plantroom 0%
909 Conc. Floor slab & swimming pool base 0%
910 Blockwork 0%
911 Conc. Swimming pool sides & overflow channels 0%
912 Conc. Ring & tie beams 0%
913 Roof & Ceiling 0%
920 Finishes 0%
928 M&E Installations 0%
939 Villa A3/09 0%
940 substructure 0%
941 set out 0%
942 Excavate 0%
943 Conc. Foundation 0%
944 Backfill 0%
945 termite treatment 0%
946 DPC (where applicable) 0%
947 M&E inlet/outlet works - first fix 0%
948 frame 0%
949 set kickers 0%
950 Conc. Columns & shear walls 0%
951 Conc. G. F Beams 0%
952 M&E first fix 0%
953 Conc. Plantroom 0%
954 Conc. Floor slab & swimming pool base 0%
955 Blockwork 0%
956 Conc. Swimming pool sides & overflow channels 0%
957 Conc. Ring & tie beams 0%
958 Roof & Ceiling 0%
965 Finishes 0%
973 M&E Installations 0%
984 Villa A3/10 0%
985 substructure 0%
986 set out 0%
987 Excavate 0%
988 Conc. Foundation 0%
989 Backfill 0%
990 termite treatment 0%
991 DPC (where applicable) 0%
992 M&E inlet/outlet works - first fix 0%
993 frame 0%
994 set kickers 0%
995 Conc. Columns & shear walls 0%
996 Conc. G. F Beams 0%
997 M&E first fix 0%
998 Conc. Plantroom 0%
999 Conc. Floor slab & swimming pool base 0%
1000 Blockwork 0%
1001 Conc. Swimming pool sides & overflow channels 0%
1002 Conc. Ring & tie beams 0%
1003 Roof & Ceiling 0%
1010 Finishes 0%
1018 M&E Installations 0%
1029 Villa A3/11 0%
1030 substructure 0%
1031 set out 0%
1032 Excavate 0%
1033 Conc. Foundation 0%
1034 Backfill 0%
1035 termite treatment 0%
1036 DPC (where applicable) 0%
1037 M&E inlet/outlet works - first fix 0%
1038 frame 0%
1039 set kickers 0%
1040 Conc. Columns & shear walls 0%
1041 Conc. G. F Beams 0%
1042 M&E first fix 0%
1043 Conc. Plantroom 0%
1044 Conc. Floor slab & swimming pool base 0%
1045 Blockwork 0%
1046 Conc. Swimming pool sides & overflow channels 0%
1047 Conc. Ring & tie beams 0%
1048 Roof & Ceiling 0%
1055 Finishes 0%
1063 M&E Installations 0%
1074 Villa A3/12 0%
1075 substructure 0%
1076 set out 0%
1077 Excavate 0%
1078 Conc. Foundation 0%
1079 Backfill 0%
1080 termite treatment 0%
1081 DPC (where applicable) 0%
1082 M&E inlet/outlet works - first fix 0%
1083 frame 0%
1084 set kickers 0%
1085 Conc. Columns & shear walls 0%
1086 Conc. G. F Beams 0%
1087 M&E first fix 0%
1088 Conc. Plantroom 0%
1089 Conc. Floor slab & swimming pool base 0%
1090 Blockwork 0%
1091 Conc. Swimming pool sides & overflow channels 0%
1092 Conc. Ring & tie beams 0%
1093 Roof & Ceiling 0%
1094 Fix wall plate & truss 0%
1095 Fix purlins and rafters 0%
1096 Fix shingles ( subject to receipt of timber) 0%
1097 Fix ceiing battens & joists 0%
1098 Fix ceiling boards 0%
1099 M&E first fix 0%
page 104
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1100 Finishes 0%
1101 Wall plaster (internal & External) 0%
1102 M&E 1st fix 0%
1103 Floor finishes 0%
1104 Fix windows & doors 0%
1105 Swimming pool finishes 0%
1106 M&E final fix 0%
1107 Fix fittings and Fixtures 0%
1108 M&E Installations 0%
1109 Cable Tray, Conduit and Wiring 0%
1110 Electrical boards and connections 0%
1111 Electrical accessories 0%
1112 Light fittings and ceiling fans 0%
1113 Hot and cold water 0%
1114 Waste and sewage incl. biobox 0%
1115 Electric water heater 0%
1116 Swimming pool 0%
1117 Split unit installation 0%
1118 Toilet ventilation, grilles 0%
1119 Villa A3/13 0%
1120 substructure 0%
1121 set out 0%
1122 Excavate 0%
1123 Conc. Foundation 0%
1124 Backfill 0%
1125 termite treatment 0%
1126 DPC (where applicable) 0%
1127 M&E inlet/outlet works - first fix 0%
1128 frame 0%
1129 set kickers 0%
1130 Conc. Columns & shear walls 0%
1131 Conc. G. F Beams 0%
1132 M&E first fix 0%
1133 Conc. Plantroom 0%
1134 Conc. Floor slab & swimming pool base 0%
1135 Blockwork 0%
1136 Conc. Swimming pool sides & overflow channels 0%
1137 Conc. Ring & tie beams 0%
1138 Roof & Ceiling 0%
1139 Fix wall plate & truss 0%
1140 Fix purlins and rafters 0%
1141 Fix shingles ( subject to receipt of timber) 0%
1142 Fix ceiing battens & joists 0%
1143 Fix ceiling boards 0%
1144 M&E first fix 0%
1145 Finishes 0%
1146 Wall plaster (internal & External) 0%
1147 M&E 1st fix 0%
1148 Floor finishes 0%
1149 Fix windows & doors 0%
1150 Swimming pool finishes 0%
1151 M&E final fix 0%
1152 Fix fittings and Fixtures 0%
1153 M&E Installations 0%
1154 Cable Tray, Conduit and Wiring 0%
1155 Electrical boards and connections 0%
1156 Electrical accessories 0%
1157 Light fittings and ceiling fans 0%
1158 Hot and cold water 0%
1159 Waste and sewage incl. biobox 0%
1160 Electric water heater 0%
1161 Swimming pool 0%
1162 Split unit installation 0%
1163 Toilet ventilation, grilles 0%
1164 Villa A3/18 0%
1165 substructure 0%
1166 set out 0%
1167 Excavate 0%
1168 Conc. Foundation 0%
1169 Backfill 0%
1170 termite treatment 0%
1171 DPC (where applicable) 0%
1172 M&E inlet/outlet works - first fix 0%
1173 frame 0%
1174 set kickers 0%
1175 Conc. Columns & shear walls 0%
1176 Conc. G. F Beams 0%
1177 M&E first fix 0%
1178 Conc. Plantroom 0%
1179 Conc. Floor slab & swimming pool base 0%
1180 Blockwork 0%
1181 Conc. Swimming pool sides & overflow channels 0%
1182 Conc. Ring & tie beams 0%
1183 Roof & Ceiling 0%
1184 Fix wall plate & truss 0%
1185 Fix purlins and rafters 0%
1186 Fix shingles ( subject to receipt of timber) 0%
1187 Fix ceiing battens & joists 0%
1188 Fix ceiling boards 0%
1189 M&E first fix 0%
1190 Finishes 0%
1191 Wall plaster (internal & External) 0%
1192 M&E 1st fix 0%
1193 Floor finishes 0%
1194 Fix windows & doors 0%
1195 Swimming pool finishes 0%
1196 M&E final fix 0%
1197 Fix fittings and Fixtures 0%
1198 M&E Installations 0%
1199 Cable Tray, Conduit and Wiring 0%
1200 Electrical boards and connections 0%
1201 Electrical accessories 0%
1202 Light fittings and ceiling fans 0%
1203 Hot and cold water 0%
1204 Waste and sewage incl. biobox 0%
1205 Electric water heater 0%
1206 Swimming pool 0%
1207 Split unit installation 0%
1208 Toilet ventilation, grilles 0%
1209 Villa A3/19 0%
1210 substructure 0%
1211 set out 0%
page 105
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1212 Excavate 0%
1213 Conc. Foundation 0%
1214 Backfill 0%
1215 termite treatment 0%
1216 DPC (where applicable) 0%
1217 M&E inlet/outlet works - first fix 0%
1218 frame 0%
1219 set kickers 0%
1220 Conc. Columns & shear walls 0%
1221 Conc. G. F Beams 0%
1222 M&E first fix 0%
1223 Conc. Plantroom 0%
1224 Conc. Floor slab & swimming pool base 0%
1225 Blockwork 0%
1226 Conc. Swimming pool sides & overflow channels 0%
1227 Conc. Ring & tie beams 0%
1228 Roof & Ceiling 0%
1235 Finishes 0%
1243 M&E Installations 0%
1254 Villa A3/20 0%
1255 substructure 0%
1256 set out 0%
1257 Excavate 0%
1258 Conc. Foundation 0%
1259 Backfill 0%
1260 termite treatment 0%
1261 DPC (where applicable) 0%
1262 M&E inlet/outlet works - first fix 0%
1263 frame 0%
1264 set kickers 0%
1265 Conc. Columns & shear walls 0%
1266 Conc. G. F Beams 0%
1267 M&E first fix 0%
1268 Conc. Plantroom 0%
1269 Conc. Floor slab & swimming pool base 0%
1270 Blockwork 0%
1271 Conc. Swimming pool sides & overflow channels 0%
1272 Conc. Ring & tie beams 0%
1273 Roof & Ceiling 0%
1280 Finishes 0%
1288 M&E Installations 0%
1299 Villa A3/21 0%
1300 substructure 0%
1301 set out 0%
1302 Excavate 0%
1303 Conc. Foundation 0%
1304 Backfill 0%
1305 termite treatment 0%
1306 DPC (where applicable) 0%
1307 M&E inlet/outlet works - first fix 0%
1308 frame 0%
1309 set kickers 0%
1310 Conc. Columns & shear walls 0%
1311 Conc. G. F Beams 0%
1312 M&E first fix 0%
1313 Conc. Plantroom 0%
1314 Conc. Floor slab & swimming pool base 0%
1315 Blockwork 0%
1316 Conc. Swimming pool sides & overflow channels 0%
1317 Conc. Ring & tie beams 0%
1318 Roof & Ceiling 0%
1325 Finishes 0%
1333 M&E Installations 0%
1344 Villa A3/22 0%
1345 substructure 0%
1346 set out 0%
1347 Excavate 0%
1348 Conc. Foundation 0%
1349 Backfill 0%
1350 termite treatment 0%
1351 DPC (where applicable) 0%
1352 M&E inlet/outlet works - first fix 0%
1353 frame 0%
1354 set kickers 0%
1355 Conc. Columns & shear walls 0%
1356 Conc. G. F Beams 0%
1357 M&E first fix 0%
1358 Conc. Plantroom 0%
1359 Conc. Floor slab & swimming pool base 0%
1360 Blockwork 0%
1361 Conc. Swimming pool sides & overflow channels 0%
1362 Conc. Ring & tie beams 0%
1363 Roof & Ceiling 0%
1364 Fix wall plate & truss 0%
1365 Fix purlins and rafters 0%
1366 Fix shingles ( subject to receipt of timber) 0%
1367 Fix ceiing battens & joists 0%
1368 Fix ceiling boards 0%
1369 M&E first fix 0%
1370 Finishes 0%
1371 Wall plaster (internal & External) 0%
1372 M&E 1st fix 0%
1373 Floor finishes 0%
1374 Fix windows & doors 0%
1375 Swimming pool finishes 0%
1376 M&E final fix 0%
1377 Fix fittings and Fixtures 0%
1378 M&E Installations 0%
1379 Cable Tray, Conduit and Wiring 0%
1380 Electrical boards and connections 0%
1381 Electrical accessories 0%
1382 Light fittings and ceiling fans 0%
1383 Hot and cold water 0%
1384 Waste and sewage incl. biobox 0%
1385 Electric water heater 0%
1386 Swimming pool 0%
1387 Split unit installation 0%
1388 Toilet ventilation, grilles 0%
1389 Villa A3/23 0%
1390 substructure 0%
1391 set out 0%
1392 Excavate 0%
1393 Conc. Foundation 0%
1394 Backfill 0%
1395 termite treatment 0%
1396 DPC (where applicable) 0%
1397 M&E inlet/outlet works - first fix 0%
page 106
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1398 frame 0%
1399 set kickers 0%
1400 Conc. Columns & shear walls 0%
1401 Conc. G. F Beams 0%
1402 M&E first fix 0%
1403 Conc. Plantroom 0%
1404 Conc. Floor slab & swimming pool base 0%
1405 Blockwork 0%
1406 Conc. Swimming pool sides & overflow channels 0%
1407 Conc. Ring & tie beams 0%
1408 Roof & Ceiling 0%
1409 Fix wall plate & truss 0%
1410 Fix purlins and rafters 0%
1411 Fix shingles ( subject to receipt of timber) 0%
1412 Fix ceiing battens & joists 0%
1413 Fix ceiling boards 0%
1414 M&E first fix 0%
1415 Finishes 0%
1416 Wall plaster (internal & External) 0%
1417 M&E 1st fix 0%
1418 Floor finishes 0%
1419 Fix windows & doors 0%
1420 Swimming pool finishes 0%
1421 M&E final fix 0%
1422 Fix fittings and Fixtures 0%
1423 M&E Installations 0%
1424 Cable Tray, Conduit and Wiring 0%
1425 Electrical boards and connections 0%
1426 Electrical accessories 0%
1427 Light fittings and ceiling fans 0%
1428 Hot and cold water 0%
1429 Waste and sewage incl. biobox 0%
1430 Electric water heater 0%
1431 Swimming pool 0%
1432 Split unit installation 0%
1433 Toilet ventilation, grilles 0%
1434 Villa A3/24 0%
1435 substructure 0%
1436 set out 0%
1437 Excavate 0%
1438 Conc. Foundation 0%
1439 Backfill 0%
1440 termite treatment 0%
1441 DPC (where applicable) 0%
1442 M&E inlet/outlet works - first fix 0%
1443 frame 0%
1444 set kickers 0%
1445 Conc. Columns & shear walls 0%
1446 Conc. G. F Beams 0%
1447 M&E first fix 0%
1448 Conc. Plantroom 0%
1449 Conc. Floor slab & swimming pool base 0%
1450 Blockwork 0%
1451 Conc. Swimming pool sides & overflow channels 0%
1452 Conc. Ring & tie beams 0%
1453 Roof & Ceiling 0%
1454 Fix wall plate & truss 0%
1455 Fix purlins and rafters 0%
1456 Fix shingles ( subject to receipt of timber) 0%
1457 Fix ceiing battens & joists 0%
1458 Fix ceiling boards 0%
1459 M&E first fix 0%
1460 Finishes 0%
1461 Wall plaster (internal & External) 0%
1462 M&E 1st fix 0%
1463 Floor finishes 0%
1464 Fix windows & doors 0%
1465 Swimming pool finishes 0%
1466 M&E final fix 0%
1467 Fix fittings and Fixtures 0%
1468 M&E Installations 0%
1469 Cable Tray, Conduit and Wiring 0%
1470 Electrical boards and connections 0%
1471 Electrical accessories 0%
1472 Light fittings and ceiling fans 0%
1473 Hot and cold water 0%
1474 Waste and sewage incl. biobox 0%
1475 Electric water heater 0%
1476 Swimming pool 0%
1477 Split unit installation 0%
1478 Toilet ventilation, grilles 0%
1479 Villa A3/25 0%
1480 substructure 0%
1481 set out 0%
1482 Excavate 0%
1483 Conc. Foundation 0%
1484 Backfill 0%
1485 termite treatment 0%
1486 DPC (where applicable) 0%
1487 M&E inlet/outlet works - first fix 0%
1488 frame 0%
1489 set kickers 0%
1490 Conc. Columns & shear walls 0%
1491 Conc. G. F Beams 0%
1492 M&E first fix 0%
1493 Conc. Plantroom 0%
1494 Conc. Floor slab & swimming pool base 0%
1495 Blockwork 0%
1496 Conc. Swimming pool sides & overflow channels 0%
1497 Conc. Ring & tie beams 0%
1498 Roof & Ceiling 0%
1499 Fix wall plate & truss 0%
1500 Fix purlins and rafters 0%
1501 Fix shingles ( subject to receipt of timber) 0%
1502 Fix ceiing battens & joists 0%
1503 Fix ceiling boards 0%
1504 M&E first fix 0%
1505 Finishes 0%
1506 Wall plaster (internal & External) 0%
1507 M&E 1st fix 0%
1508 Floor finishes 0%
1509 Fix windows & doors 0%
1510 Swimming pool finishes 0%
1511 M&E final fix 0%
1512 Fix fittings and Fixtures 0%
page 107
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1513 M&E Installations 0%
1514 Cable Tray, Conduit and Wiring 0%
1515 Electrical boards and connections 0%
1516 Electrical accessories 0%
1517 Light fittings and ceiling fans 0%
1518 Hot and cold water 0%
1519 Waste and sewage incl. biobox 0%
1520 Electric water heater 0%
1521 Swimming pool 0%
1522 Split unit installation 0%
1523 Toilet ventilation, grilles 0%
1524 Villa A3/26 0%
1525 substructure 0%
1526 set out 0%
1527 Excavate 0%
1528 Conc. Foundation 0%
1529 Backfill 0%
1530 termite treatment 0%
1531 DPC (where applicable) 0%
1532 M&E inlet/outlet works - first fix 0%
1533 frame 0%
1534 set kickers 0%
1535 Conc. Columns & shear walls 0%
1536 Conc. G. F Beams 0%
1537 M&E first fix 0%
1538 Conc. Plantroom 0%
1539 Conc. Floor slab & swimming pool base 0%
1540 Blockwork 0%
1541 Conc. Swimming pool sides & overflow channels 0%
1542 Conc. Ring & tie beams 0%
1543 Roof & Ceiling 0%
1550 Finishes 0%
1558 M&E Installations 0%
1569 Villa A3/27 0%
1570 substructure 0%
1571 set out 0%
1572 Excavate 0%
1573 Conc. Foundation 0%
1574 Backfill 0%
1575 termite treatment 0%
1576 DPC (where applicable) 0%
1577 M&E inlet/outlet works - first fix 0%
1578 frame 0%
1579 set kickers 0%
1580 Conc. Columns & shear walls 0%
1581 Conc. G. F Beams 0%
1582 M&E first fix 0%
1583 Conc. Plantroom 0%
1584 Conc. Floor slab & swimming pool base 0%
1585 Blockwork 0%
1586 Conc. Swimming pool sides & overflow channels 0%
1587 Conc. Ring & tie beams 0%
1588 Roof & Ceiling 0%
1595 Finishes 0%
1603 M&E Installations 0%
1614 B223 Villas ( 7 nos) 0%
1615 Villa B2/01 0%
1616 substructure 0%
1617 set out 0%
1618 Excavate 0%
1619 Conc. Foundation 0%
1620 Backfill 0%
1621 termite treatment 0%
1622 DPC (where applicable) 0%
1623 M&E inlet/outlet works - first fix 0%
1624 frame 0%
1625 set kickers 0%
1626 Conc. Columns & shear walls to GF 0%
1627 Conc. Plantrooms 0%
1628 M&E first fix GF 0%
1629 Conc. GF slab and beams 0%
1630 Blockwork up to FF slab 0%
1631 set kickers on GF 0%
1632 Conc. Columns & shear walls to FF 0%
1633 M&E first fix FF 0%
1634 Conc. FF slab & beams 0%
1635 Blockwork up to roof 0%
1636 set kickers on FF 0%
1637 Conc. Columns & shear walls to roof 0%
1638 M&E first fix roof 0%
1639 Conc. Ring & tie beams 0%
1640 Roof & Ceiling 0%
1647 Finishes 0%
1654 M&E Installations 0%
1665 Villa B2/02 0%
1666 substructure 0%
1667 set out 0%
1668 Excavate 0%
1669 Conc. Foundation 0%
1670 Backfill 0%
1671 termite treatment 0%
1672 DPC (where applicable) 0%
1673 M&E inlet/outlet works - first fix 0%
1674 frame 0%
1675 set kickers 0%
1676 Conc. Columns & shear walls to GF 0%
1677 Conc. Plantrooms 0%
1678 M&E first fix GF 0%
1679 Conc. GF slab and beams 0%
1680 Blockwork up to FF slab 0%
1681 set kickers on GF 0%
1682 Conc. Columns & shear walls to FF 0%
1683 M&E first fix FF 0%
1684 Conc. FF slab & beams 0%
1685 Blockwork up to roof 0%
1686 set kickers on FF 0%
1687 Conc. Columns & shear walls to roof 0%
1688 M&E first fix roof 0%
1689 Conc. Ring & tie beams 0%
1690 Roof & Ceiling 0%
1697 Finishes 0%
1704 M&E Installations 0%
1715 Villa B2/04 0%
1716 substructure 0%
1717 set out 0%
1718 Excavate 0%
page 108
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1719 Conc. Foundation 0%
1720 Backfill 0%
1721 termite treatment 0%
1722 DPC (where applicable) 0%
1723 M&E inlet/outlet works - first fix 0%
1724 frame 0%
1725 set kickers 0%
1726 Conc. Columns & shear walls to GF 0%
1727 Conc. Plantrooms 0%
1728 M&E first fix GF 0%
1729 Conc. GF slab and beams 0%
1730 Blockwork up to FF slab 0%
1731 set kickers on GF 0%
1732 Conc. Columns & shear walls to FF 0%
1733 M&E first fix FF 0%
1734 Conc. FF slab & beams 0%
1735 Blockwork up to roof 0%
1736 set kickers on FF 0%
1737 Conc. Columns & shear walls to roof 0%
1738 M&E first fix roof 0%
1739 Conc. Ring & tie beams 0%
1740 Roof & Ceiling 0%
1747 Finishes 0%
1754 M&E Installations 0%
1765 Villa B2/05 0%
1766 substructure 0%
1767 set out 0%
1768 Excavate 0%
1769 Conc. Foundation 0%
1770 Backfill 0%
1771 termite treatment 0%
1772 DPC (where applicable) 0%
1773 M&E inlet/outlet works - first fix 0%
1774 frame 0%
1775 set kickers 0%
1776 Conc. Columns & shear walls to GF 0%
1777 Conc. Plantrooms 0%
1778 M&E first fix GF 0%
1779 Conc. GF slab and beams 0%
1780 Blockwork up to FF slab 0%
1781 set kickers on GF 0%
1782 Conc. Columns & shear walls to FF 0%
1783 M&E first fix FF 0%
1784 Conc. FF slab & beams 0%
1785 Blockwork up to roof 0%
1786 set kickers on FF 0%
1787 Conc. Columns & shear walls to roof 0%
1788 M&E first fix roof 0%
1789 Conc. Ring & tie beams 0%
1790 Roof & Ceiling 0%
1797 Finishes 0%
1804 M&E Installations 0%
1815 Villa B2/06 0%
1816 substructure 0%
1817 set out 0%
1818 Excavate 0%
1819 Conc. Foundation 0%
1820 Backfill 0%
1821 termite treatment 0%
1822 DPC (where applicable) 0%
1823 M&E inlet/outlet works - first fix 0%
1824 frame 0%
1825 set kickers 0%
1826 Conc. Columns & shear walls to GF 0%
1827 Conc. Plantrooms 0%
1828 M&E first fix GF 0%
1829 Conc. GF slab and beams 0%
1830 Blockwork up to FF slab 0%
1831 set kickers on GF 0%
1832 Conc. Columns & shear walls to FF 0%
1833 M&E first fix FF 0%
1834 Conc. FF slab & beams 0%
1835 Blockwork up to roof 0%
1836 set kickers on FF 0%
1837 Conc. Columns & shear walls to roof 0%
1838 M&E first fix roof 0%
1839 Conc. Ring & tie beams 0%
1840 Roof & Ceiling 0%
1847 Finishes 0%
1854 M&E Installations 0%
1865 Villa B2/07 0%
1866 substructure 0%
1867 set out 0%
1868 Excavate 0%
1869 Conc. Foundation 0%
1870 Backfill 0%
1871 termite treatment 0%
1872 DPC (where applicable) 0%
1873 M&E inlet/outlet works - first fix 0%
1874 frame 0%
1875 set kickers 0%
1876 Conc. Columns & shear walls to GF 0%
1877 Conc. Plantrooms 0%
1878 M&E first fix GF 0%
1879 Conc. GF slab and beams 0%
1880 Blockwork up to FF slab 0%
1881 set kickers on GF 0%
1882 Conc. Columns & shear walls to FF 0%
1883 M&E first fix FF 0%
1884 Conc. FF slab & beams 0%
1885 Blockwork up to roof 0%
1886 set kickers on FF 0%
1887 Conc. Columns & shear walls to roof 0%
1888 M&E first fix roof 0%
1889 Conc. Ring & tie beams 0%
1890 Roof & Ceiling 0%
1897 Finishes 0%
1904 M&E Installations 0%
1915 Villa B2/08 0%
1916 substructure 0%
1917 set out 0%
1918 Excavate 0%
1919 Conc. Foundation 0%
page 109
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1920 Backfill 0%
1921 termite treatment 0%
1922 DPC (where applicable) 0%
1923 M&E inlet/outlet works - first fix 0%
1924 frame 0%
1925 set kickers 0%
1926 Conc. Columns & shear walls to GF 0%
1927 Conc. Plantrooms 0%
1928 M&E first fix GF 0%
1929 Conc. GF slab and beams 0%
1930 Blockwork up to FF slab 0%
1931 set kickers on GF 0%
1932 Conc. Columns & shear walls to FF 0%
1933 M&E first fix FF 0%
1934 Conc. FF slab & beams 0%
1935 Blockwork up to roof 0%
1936 set kickers on FF 0%
1937 Conc. Columns & shear walls to roof 0%
1938 M&E first fix roof 0%
1939 Conc. Ring & tie beams 0%
1940 Roof & Ceiling 0%
1947 Finishes 0%
1954 M&E Installations 0%
1965 B4 Villa (2 nos.) 0%
2056 Retail 1( subject to receipt of GFW drawings) 0%
2094 Retail 2( subject to receipt of GFW drawings) 0%
2132 Retail 3( subject to receipt of GFW drawings) 0%
2170 Seafood resort( subject to receipt of GFW drawings) 0%
2211 Greeting Pavillion( subject to receipt of GFW drawings) 0%
2250 External works ( subject to receipt of GFW drawings) 0%
2259 Drainage works ( subject to receipt of EME details) 0%
2262 Lot 3 0%
2263 A3 Villas ( 9 nos) 0%
2264 Villa A3/14 0%
2265 Substructure 0%
2266 set out 0%
2267 Excavate 0%
2268 Conc. Foundation 0%
2269 Backfill 0%
2270 termite treatment 0%
2271 DPC (where applicable) 0%
2272 M&E inlet/outlet works - first fix 0%
2273 Frame 0%
2274 set kickers 0%
2275 Conc. Columns & shear walls 0%
2276 Conc. G. F Beams 0%
2277 M&E first fix 0%
2278 Conc. Plantroom 0%
2279 Conc. Floor slab & swimming pool base 0%
2280 Blockwork 0%
2281 Conc. Swimming pool sides & overflow channels 0%
2282 Conc. Ring & tie beams 0%
2283 Roof & Ceiling 0%
2284 Fix wall plate & truss 0%
2285 Fix purlins and rafters 0%
2286 Fix shingles ( subject to receipt of timber) 0%
2287 Fix ceiing battens & joists 0%
2288 Fix ceiling boards 0%
2289 M&E first fix 0%
2290 Finishes 0%
2291 Wall plaster (internal & External) 0%
2292 M&E 1st fix 0%
2293 Floor finishes 0%
2294 Fix windows & doors 0%
2295 Swimming pool finishes 0%
2296 M&E final fix 0%
2297 Fix fittings and Fixtures 0%
2298 M&E Installations 0%
2299 Cable Tray, Conduit and Wiring 0%
2300 Electrical boards and connections 0%
2301 Electrical accessories 0%
2302 Light fittings and ceiling fans 0%
2303 Hot and cold water 0%
2304 Waste and sewage incl. biobox 0%
2305 Electric water heater 0%
2306 Swimming pool 0%
2307 Split unit installation 0%
2308 Toilet ventilation, grilles 0%
2309 Villa A3/15 0%
2310 substructure 0%
2311 set out 0%
2312 Excavate 0%
2313 Conc. Foundation 0%
2314 Backfill 0%
2315 termite treatment 0%
2316 DPC (where applicable) 0%
2317 M&E inlet/outlet works - first fix 0%
2318 frame 0%
2319 set kickers 0%
2320 Conc. Columns & shear walls 0%
2321 Conc. G. F Beams 0%
2322 M&E first fix 0%
2323 Conc. Plantroom 0%
2324 Conc. Floor slab & swimming pool base 0%
2325 Blockwork 0%
2326 Conc. Swimming pool sides & overflow channels 0%
2327 Conc. Ring & tie beams 0%
2328 Roof & Ceiling 0%
2329 Fix wall plate & truss 0%
2330 Fix purlins and rafters 0%
2331 Fix shingles ( subject to receipt of timber) 0%
2332 Fix ceiing battens & joists 0%
2333 Fix ceiling boards 0%
2334 M&E first fix 0%
2335 Finishes 0%
2336 Wall plaster (internal & External) 0%
2337 M&E 1st fix 0%
2338 Floor finishes 0%
2339 Fix windows & doors 0%
2340 Swimming pool finishes 0%
2341 M&E final fix 0%
2342 Fix fittings and Fixtures 0%
2343 M&E Installations 0%
2344 Cable Tray, Conduit and Wiring 0%
2345 Electrical boards and connections 0%
page 110
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
2346 Electrical accessories 0%
2347 Light fittings and ceiling fans 0%
2348 Hot and cold water 0%
2349 Waste and sewage incl. biobox 0%
2350 Electric water heater 0%
2351 Swimming pool 0%
2352 Split unit installation 0%
2353 Toilet ventilation, grilles 0%
2354 Villa A3/16 0%
2355 substructure 0%
2356 set out 0%
2357 Excavate 0%
2358 Conc. Foundation 0%
2359 Backfill 0%
2360 termite treatment 0%
2361 DPC (where applicable) 0%
2362 M&E inlet/outlet works - first fix 0%
2363 frame 0%
2364 set kickers 0%
2365 Conc. Columns & shear walls 0%
2366 Conc. G. F Beams 0%
2367 M&E first fix 0%
2368 Conc. Plantroom 0%
2369 Conc. Floor slab & swimming pool base 0%
2370 Blockwork 0%
2371 Conc. Swimming pool sides & overflow channels 0%
2372 Conc. Ring & tie beams 0%
2373 Roof & Ceiling 0%
2374 Fix wall plate & truss 0%
2375 Fix purlins and rafters 0%
2376 Fix shingles ( subject to receipt of timber) 0%
2377 Fix ceiing battens & joists 0%
2378 Fix ceiling boards 0%
2379 M&E first fix 0%
2380 Finishes 0%
2381 Wall plaster (internal & External) 0%
2382 M&E 1st fix 0%
2383 Floor finishes 0%
2384 Fix windows & doors 0%
2385 Swimming pool finishes 0%
2386 M&E final fix 0%
2387 Fix fittings and Fixtures 0%
2388 M&E Installations 0%
2389 Cable Tray, Conduit and Wiring 0%
2390 Electrical boards and connections 0%
2391 Electrical accessories 0%
2392 Light fittings and ceiling fans 0%
2393 Hot and cold water 0%
2394 Waste and sewage incl. biobox 0%
2395 Electric water heater 0%
2396 Swimming pool 0%
2397 Split unit installation 0%
2398 Toilet ventilation, grilles 0%
2399 Villa A3/17 0%
2400 substructure 0%
2401 set out 0%
2402 Excavate 0%
2403 Conc. Foundation 0%
2404 Backfill 0%
2405 termite treatment 0%
2406 DPC (where applicable) 0%
2407 M&E inlet/outlet works - first fix 0%
2408 frame 0%
2409 set kickers 0%
2410 Conc. Columns & shear walls 0%
2411 Conc. G. F Beams 0%
2412 M&E first fix 0%
2413 Conc. Plantroom 0%
2414 Conc. Floor slab & swimming pool base 0%
2415 Blockwork 0%
2416 Conc. Swimming pool sides & overflow channels 0%
2417 Conc. Ring & tie beams 0%
2418 Roof & Ceiling 0%
2419 Fix wall plate & truss 0%
2420 Fix purlins and rafters 0%
2421 Fix shingles ( subject to receipt of timber) 0%
2422 Fix ceiing battens & joists 0%
2423 Fix ceiling boards 0%
2424 M&E first fix 0%
2425 Finishes 0%
2426 Wall plaster (internal & External) 0%
2427 M&E 1st fix 0%
2428 Floor finishes 0%
2429 Fix windows & doors 0%
2430 Swimming pool finishes 0%
2431 M&E final fix 0%
2432 Fix fittings and Fixtures 0%
2433 M&E Installations 0%
2434 Cable Tray, Conduit and Wiring 0%
2435 Electrical boards and connections 0%
2436 Electrical accessories 0%
2437 Light fittings and ceiling fans 0%
2438 Hot and cold water 0%
2439 Waste and sewage incl. biobox 0%
2440 Electric water heater 0%
2441 Swimming pool 0%
2442 Split unit installation 0%
2443 Toilet ventilation, grilles 0%
2444 Villa A3/28 0%
2445 substructure 0%
2446 set out 0%
2447 Excavate 0%
2448 Conc. Foundation 0%
2449 Backfill 0%
2450 termite treatment 0%
2451 DPC (where applicable) 0%
2452 M&E inlet/outlet works - first fix 0%
2453 frame 0%
2454 set kickers 0%
2455 Conc. Columns & shear walls 0%
2456 Conc. G. F Beams 0%
2457 M&E first fix 0%
page 111
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
2458 Conc. Plantroom 0%
2459 Conc. Floor slab & swimming pool base 0%
2460 Blockwork 0%
2461 Conc. Swimming pool sides & overflow channels 0%
2462 Conc. Ring & tie beams 0%
2463 Roof & Ceiling 0%
2470 Finishes 0%
2478 M&E Installations 0%
2489 Villa A3/29 0%
2490 substructure 0%
2491 set out 0%
2492 Excavate 0%
2493 Conc. Foundation 0%
2494 Backfill 0%
2495 termite treatment 0%
2496 DPC (where applicable) 0%
2497 M&E inlet/outlet works - first fix 0%
2498 frame 0%
2499 set kickers 0%
2500 Conc. Columns & shear walls 0%
2501 Conc. G. F Beams 0%
2502 M&E first fix 0%
2503 Conc. Plantroom 0%
2504 Conc. Floor slab & swimming pool base 0%
2505 Blockwork 0%
2506 Conc. Swimming pool sides & overflow channels 0%
2507 Conc. Ring & tie beams 0%
2508 Roof & Ceiling 0%
2515 Finishes 0%
2523 M&E Installations 0%
2534 Villa A3/30 0%
2535 substructure 0%
2536 set out 0%
2537 Excavate 0%
2538 Conc. Foundation 0%
2539 Backfill 0%
2540 termite treatment 0%
2541 DPC (where applicable) 0%
2542 M&E inlet/outlet works - first fix 0%
2543 frame 0%
2544 set kickers 0%
2545 Conc. Columns & shear walls 0%
2546 Conc. G. F Beams 0%
2547 M&E first fix 0%
2548 Conc. Plantroom 0%
2549 Conc. Floor slab & swimming pool base 0%
2550 Blockwork 0%
2551 Conc. Swimming pool sides & overflow channels 0%
2552 Conc. Ring & tie beams 0%
2553 Roof & Ceiling 0%
2560 Finishes 0%
2568 M&E Installations 0%
2579 Villa A3/31 0%
2624 Villa A3/32 0%
2625 substructure 0%
2626 set out 0%
2627 Excavate 0%
2628 Conc. Foundation 0%
2629 Backfill 0%
2630 termite treatment 0%
2631 DPC (where applicable) 0%
2632 frame 0%
2633 set kickers 0%
2634 Conc. Columns & shear walls 0%
2635 Conc. Ground Beams 0%
2636 Conc. Plantroom 0%
2637 Conc. Floor slab & swimming pool base 0%
2638 Blockwork 0%
2639 Conc. Swimming pool sides & overflow channels 0%
2640 Conc. Ring & tie beams 0%
2641 Roof & Ceiling 0%
2647 Finishes 0%
2653 M&E Installations 0%
2664 B223 Villas ( 3 nos) 0%
2665 Villa B2/03 0%
2666 substructure 0%
2667 set out 0%
2668 Excavate 0%
2669 Conc. Foundation 0%
2670 Backfill 0%
2671 termite treatment 0%
2672 DPC (where applicable) 0%
2673 frame 0%
2674 set kickers 0%
2675 Conc. Columns & shear walls to GF 0%
2676 Conc. Plantrooms 0%
2677 Conc. GF slab and beams 0%
2678 Blockwork up to FF slab 0%
2679 set kickers on GF 0%
2680 Conc. Columns & shear walls to FF 0%
2681 Conc. FF slab & beams 0%
2682 Blockwork up to roof 0%
2683 set kickers on FF 0%
2684 Conc. Columns & shear walls to roof 0%
2685 Conc. Ring & tie beams 0%
2686 Roof & Ceiling 0%
2692 Finishes 0%
2697 M&E Installations 0%
2708 Villa B2/09 0%
2709 substructure 0%
2710 set out 0%
2711 Excavate 0%
2712 Conc. Foundation 0%
2713 Backfill 0%
2714 termite treatment 0%
2715 DPC (where applicable) 0%
2716 M&E inlet/outlet works - first fix 0%
2717 frame 0%
2718 set kickers 0%
2719 Conc. Columns & shear walls to GF 0%
2720 Conc. Plantrooms 0%
2721 M&E first fix GF 0%
2722 Conc. GF slab and beams 0%
2723 Blockwork up to FF slab 0%
page 112
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
2724 set kickers on GF 0%
2725 Conc. Columns & shear walls to FF 0%
2726 M&E first fix FF 0%
2727 Conc. FF slab & beams 0%
2728 Blockwork up to roof 0%
2729 set kickers on FF 0%
2730 Conc. Columns & shear walls to roof 0%
2731 M&E first fix roof 0%
2732 Conc. Ring & tie beams 0%
2733 Roof & Ceiling 0%
2740 Finishes 0%
2747 M&E Installations 0%
2758 Villa B2/10 0%
2759 substructure 0%
2760 set out 0%
2761 Excavate 0%
2762 Conc. Foundation 0%
2763 Backfill 0%
2764 termite treatment 0%
2765 DPC (where applicable) 0%
2766 M&E inlet/outlet works - first fix 0%
2767 frame 0%
2768 set kickers 0%
2769 Conc. Columns & shear walls to GF 0%
2770 Conc. Plantrooms 0%
2771 M&E first fix GF 0%
2772 Conc. GF slab and beams 0%
2773 Blockwork up to FF slab 0%
2774 set kickers on GF 0%
2775 Conc. Columns & shear walls to FF 0%
2776 M&E first fix FF 0%
2777 Conc. FF slab & beams 0%
2778 Blockwork up to roof 0%
2779 set kickers on FF 0%
2780 Conc. Columns & shear walls to roof 0%
2781 M&E first fix roof 0%
2782 Conc. Ring & tie beams 0%
2783 Roof & Ceiling 0%
2790 Finishes 0%
2797 M&E Installations 0%
2808 B4 Standard Villas ( 2 nos) 0%
2899 BC311 Executive Villa 0%
3115 P3 Presidential suites ( 3 nos) 0%
3245 Hilltop sunset deck( subject to receipt of GFW drawings) 0%
3280 External works ( subject to receipt of GFW drawings) 0%
3289 Drainage works ( subject to receipt of EME details) 0%
3292 Lot 4 0%
3293 Couple treatment room( subject to receipt of GFW drawings) 0%
3334 Single treatment room( subject to receipt of GFW drawings) 0%
3375 Dive Centre( subject to receipt of GFW drawings) 0%
3413 Kid's club( subject to receipt of GFW drawings) 0%
3452 Recreation House( subject to receipt of GFW drawings) 0%
3491 Watersports rental( subject to receipt of GFW drawings) 0%
3529 3 Meals restaurant( subject to receipt of GFW drawings) 0%
3570 Beach Pool Bar( subject to receipt of GFW drawings) 0%
3611 Signature Pool area( subject to receipt of GFW drawings) 0%
3650 Wedding Chapel( subject to receipt of GFW drawings) 0%
3685 BOH/Admin Building( subject to receipt of GFW drawings) 0%
3726 Chi Sanctum( subject to receipt of GFW drawings) 0%
3767 Yoga Pavillion( subject to receipt of GFW drawings) 0%
3805 External works ( subject to receipt of GFW drawings) 0%
3814 Drainage works ( subject to receipt of EME details) 0%
3817 M&E Installations- External 0%
3828 Sundries 0%
3829 Site cleaning & demobilisation 0%
3830 Project Commissioning 0%
page 113
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 114
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 115
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
403 Waste and sewage incl. biobox 0%
404 Electric water heater 0%
405 Swimming pool 0%
406 Split unit installation 0%
407 Toilet ventilation, grilles 0%
408 Villa A3/06 0%
409 substructure 0%
410 set out 0%
411 Excavate 0%
412 Conc. Foundation 0%
413 Backfill 0%
414 termite treatment 0%
415 DPC (where applicable) 0%
416 M&E inlet/outlet works - first fix 0%
417 frame 0%
418 set kickers 0%
419 Conc. Columns & shear walls 0%
420 Conc. G. F Beams 0%
421 M&E first fix 0%
422 Conc. Plantroom 0%
423 Conc. Floor slab & swimming pool base 0%
424 Blockwork 0%
425 Conc. Swimming pool sides & overflow channels 0%
426 Conc. Ring & tie beams 0%
427 Roof & Ceiling 0%
434 Finishes 0%
442 M&E Installations 0%
453 C311 Executive Villas ( 1 nos) 0%
497 GM Villa ( subject to receipt of GFW drawings) 0%
537 Employees Facilities ( subject to receipt of GFW drawings) 0%
581 Laundry F& B service office ( subject to receipt of GFW drawings) 0%
625 Health Club/ Medical Centre( subject to receipt of GFW drawings) 0%
666 Administration Block ( subject to receipt of GFW drawings) 0%
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings) 0%
750 Main Lobby ( subject to receipt of GFW drawings) 0%
791 Tennis Courts ( subject to receipt of GFW drawings) 0%
807 External works ( subject to receipt of GFW drawings) 0%
816 Drainage works ( subject to receipt of EME details) 0%
819 Fuel Farm ( subject to receipt of EME details) 0%
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details) 0%
827 Desalination plant( subject to receipt of EME details) 0%
831 MLV Panel( subject to receipt of EME details) 0%
835 Step Up Transformer( subject to receipt of EME details) 0%
839 Incinerator/ Garbage room( subject to receipt of EME details) 0%
843 Sewer treatement plant( subject to receipt of EME details) 0%
847 Lot 2 0%
848 A3 Villas (17 nos) 0%
849 Villa A3/07 0%
894 Villa A3/08 0%
895 substructure 0%
896 set out 0%
897 Excavate 0%
898 Conc. Foundation 0%
899 Backfill 0%
900 termite treatment 0%
901 DPC (where applicable) 0%
902 M&E inlet/outlet works - first fix 0%
903 frame 0%
904 set kickers 0%
905 Conc. Columns & shear walls 0%
906 Conc. G. F Beams 0%
907 M&E first fix 0%
908 Conc. Plantroom 0%
909 Conc. Floor slab & swimming pool base 0%
910 Blockwork 0%
911 Conc. Swimming pool sides & overflow channels 0%
912 Conc. Ring & tie beams 0%
913 Roof & Ceiling 0%
920 Finishes 0%
928 M&E Installations 0%
939 Villa A3/09 0%
984 Villa A3/10 0%
985 substructure 0%
986 set out 0%
987 Excavate 0%
988 Conc. Foundation 0%
989 Backfill 0%
990 termite treatment 0%
991 DPC (where applicable) 0%
992 M&E inlet/outlet works - first fix 0%
993 frame 0%
994 set kickers 0%
995 Conc. Columns & shear walls 0%
996 Conc. G. F Beams 0%
997 M&E first fix 0%
998 Conc. Plantroom 0%
999 Conc. Floor slab & swimming pool base 0%
1000 Blockwork 0%
1001 Conc. Swimming pool sides & overflow channels 0%
1002 Conc. Ring & tie beams 0%
1003 Roof & Ceiling 0%
1010 Finishes 0%
1018 M&E Installations 0%
1029 Villa A3/11 0%
1074 Villa A3/12 0%
1119 Villa A3/13 0%
1164 Villa A3/18 0%
1209 Villa A3/19 0%
1254 Villa A3/20 0%
1299 Villa A3/21 0%
1344 Villa A3/22 0%
1389 Villa A3/23 0%
1434 Villa A3/24 0%
1479 Villa A3/25 0%
1524 Villa A3/26 0%
1569 Villa A3/27 0%
1570 substructure 0%
1571 set out 0%
1572 Excavate 0%
1573 Conc. Foundation 0%
page 116
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1574 Backfill 0%
1575 termite treatment 0%
1576 DPC (where applicable) 0%
1577 M&E inlet/outlet works - first fix 0%
1578 frame 0%
1579 set kickers 0%
1580 Conc. Columns & shear walls 0%
1581 Conc. G. F Beams 0%
1582 M&E first fix 0%
1583 Conc. Plantroom 0%
1584 Conc. Floor slab & swimming pool base 0%
1585 Blockwork 0%
1586 Conc. Swimming pool sides & overflow channels 0%
1587 Conc. Ring & tie beams 0%
1588 Roof & Ceiling 0%
1595 Finishes 0%
1603 M&E Installations 0%
1614 B223 Villas ( 7 nos) 0%
1615 Villa B2/01 0%
1665 Villa B2/02 0%
1666 substructure 0%
1667 set out 0%
1668 Excavate 0%
1669 Conc. Foundation 0%
1670 Backfill 0%
1671 termite treatment 0%
1672 DPC (where applicable) 0%
1673 M&E inlet/outlet works - first fix 0%
1674 frame 0%
1675 set kickers 0%
1676 Conc. Columns & shear walls to GF 0%
1677 Conc. Plantrooms 0%
1678 M&E first fix GF 0%
1679 Conc. GF slab and beams 0%
1680 Blockwork up to FF slab 0%
1681 set kickers on GF 0%
1682 Conc. Columns & shear walls to FF 0%
1683 M&E first fix FF 0%
1684 Conc. FF slab & beams 0%
1685 Blockwork up to roof 0%
1686 set kickers on FF 0%
1687 Conc. Columns & shear walls to roof 0%
1688 M&E first fix roof 0%
1689 Conc. Ring & tie beams 0%
1690 Roof & Ceiling 0%
1697 Finishes 0%
1704 M&E Installations 0%
1715 Villa B2/04 0%
1765 Villa B2/05 0%
1815 Villa B2/06 0%
1865 Villa B2/07 0%
1915 Villa B2/08 0%
1965 B4 Villa (2 nos.) 0%
2056 Retail 1( subject to receipt of GFW drawings) 0%
2094 Retail 2( subject to receipt of GFW drawings) 0%
2132 Retail 3( subject to receipt of GFW drawings) 0%
2170 Seafood resort( subject to receipt of GFW drawings) 0%
2211 Greeting Pavillion( subject to receipt of GFW drawings) 0%
2250 External works ( subject to receipt of GFW drawings) 0%
2259 Drainage works ( subject to receipt of EME details) 0%
2262 Lot 3 0%
2263 A3 Villas ( 9 nos) 0%
2264 Villa A3/14 0%
2309 Villa A3/15 0%
2354 Villa A3/16 0%
2399 Villa A3/17 0%
2444 Villa A3/28 0%
2445 substructure 0%
2446 set out 0%
2447 Excavate 0%
2448 Conc. Foundation 0%
2449 Backfill 0%
2450 termite treatment 0%
2451 DPC (where applicable) 0%
2452 M&E inlet/outlet works - first fix 0%
2453 frame 0%
2454 set kickers 0%
2455 Conc. Columns & shear walls 0%
2456 Conc. G. F Beams 0%
2457 M&E first fix 0%
2458 Conc. Plantroom 0%
2459 Conc. Floor slab & swimming pool base 0%
2460 Blockwork 0%
2461 Conc. Swimming pool sides & overflow channels 0%
2462 Conc. Ring & tie beams 0%
2463 Roof & Ceiling 0%
2470 Finishes 0%
2478 M&E Installations 0%
2489 Villa A3/29 0%
2490 substructure 0%
2491 set out 0%
2492 Excavate 0%
2493 Conc. Foundation 0%
2494 Backfill 0%
2495 termite treatment 0%
2496 DPC (where applicable) 0%
2497 M&E inlet/outlet works - first fix 0%
2498 frame 0%
2499 set kickers 0%
2500 Conc. Columns & shear walls 0%
2501 Conc. G. F Beams 0%
2502 M&E first fix 0%
2503 Conc. Plantroom 0%
2504 Conc. Floor slab & swimming pool base 0%
2505 Blockwork 0%
2506 Conc. Swimming pool sides & overflow channels 0%
2507 Conc. Ring & tie beams 0%
2508 Roof & Ceiling 0%
2515 Finishes 0%
2523 M&E Installations 0%
page 117
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
2534 Villa A3/30 0%
2535 substructure 0%
2536 set out 0%
2537 Excavate 0%
2538 Conc. Foundation 0%
2539 Backfill 0%
2540 termite treatment 0%
2541 DPC (where applicable) 0%
2542 M&E inlet/outlet works - first fix 0%
2543 frame 0%
2544 set kickers 0%
2545 Conc. Columns & shear walls 0%
2546 Conc. G. F Beams 0%
2547 M&E first fix 0%
2548 Conc. Plantroom 0%
2549 Conc. Floor slab & swimming pool base 0%
2550 Blockwork 0%
2551 Conc. Swimming pool sides & overflow channels 0%
2552 Conc. Ring & tie beams 0%
2553 Roof & Ceiling 0%
2560 Finishes 0%
2568 M&E Installations 0%
2579 Villa A3/31 0%
2580 substructure 0%
2581 set out 0%
2582 Excavate 0%
2583 Conc. Foundation 0%
2584 Backfill 0%
2585 termite treatment 0%
2586 DPC (where applicable) 0%
2587 M&E inlet/outlet works - first fix 0%
2588 frame 0%
2589 set kickers 0%
2590 Conc. Columns & shear walls 0%
2591 Conc. G. F Beams 0%
2592 M&E first fix 0%
2593 Conc. Plantroom 0%
2594 Conc. Floor slab & swimming pool base 0%
2595 Blockwork 0%
2596 Conc. Swimming pool sides & overflow channels 0%
2597 Conc. Ring & tie beams 0%
2598 Roof & Ceiling 0%
2599 Fix wall plate & truss 0%
2600 Fix purlins and rafters 0%
2601 Fix shingles ( subject to receipt of timber) 0%
2602 Fix ceiing battens & joists 0%
2603 Fix ceiling boards 0%
2604 M&E first fix 0%
2605 Finishes 0%
2606 Wall plaster (internal & External) 0%
2607 M&E 1st fix 0%
2608 Floor finishes 0%
2609 Fix windows & doors 0%
2610 Swimming pool finishes 0%
2611 M&E final fix 0%
2612 Fix fittings and Fixtures 0%
2613 M&E Installations 0%
2614 Cable Tray, Conduit and Wiring 0%
2615 Electrical boards and connections 0%
2616 Electrical accessories 0%
2617 Light fittings and ceiling fans 0%
2618 Hot and cold water 0%
2619 Waste and sewage incl. biobox 0%
2620 Electric water heater 0%
2621 Swimming pool 0%
2622 Split unit installation 0%
2623 Toilet ventilation, grilles 0%
2624 Villa A3/32 0%
2664 B223 Villas ( 3 nos) 0%
2665 Villa B2/03 0%
2708 Villa B2/09 0%
2758 Villa B2/10 0%
2808 B4 Standard Villas ( 2 nos) 0%
2899 BC311 Executive Villa 0%
3115 P3 Presidential suites ( 3 nos) 0%
3245 Hilltop sunset deck( subject to receipt of GFW drawings) 0%
3280 External works ( subject to receipt of GFW drawings) 0%
3289 Drainage works ( subject to receipt of EME details) 0%
3292 Lot 4 0%
3293 Couple treatment room( subject to receipt of GFW drawings) 0%
3334 Single treatment room( subject to receipt of GFW drawings) 0%
3375 Dive Centre( subject to receipt of GFW drawings) 0%
3413 Kid's club( subject to receipt of GFW drawings) 0%
3452 Recreation House( subject to receipt of GFW drawings) 0%
3491 Watersports rental( subject to receipt of GFW drawings) 0%
3529 3 Meals restaurant( subject to receipt of GFW drawings) 0%
3570 Beach Pool Bar( subject to receipt of GFW drawings) 0%
3611 Signature Pool area( subject to receipt of GFW drawings) 0%
3650 Wedding Chapel( subject to receipt of GFW drawings) 0%
3685 BOH/Admin Building( subject to receipt of GFW drawings) 0%
3726 Chi Sanctum( subject to receipt of GFW drawings) 0%
3767 Yoga Pavillion( subject to receipt of GFW drawings) 0%
3805 External works ( subject to receipt of GFW drawings) 0%
3814 Drainage works ( subject to receipt of EME details) 0%
3817 M&E Installations- External 0%
3828 Sundries 0%
3829 Site cleaning & demobilisation 0%
3830 Project Commissioning 0%
page 118
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
As a result the delay caused by this event is not critical and the
time for completion has not extended the revised date of 9
September 2009.
page 119
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 120
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2658 Hot and cold water 0%
2659 Waste and sewage incl. biobox 0%
2660 Electric water heater 0%
2661 Swimming pool 0%
2662 Split unit installation 0%
2663 Toilet ventilation, grilles 0%
2664 B223 Villas ( 3 nos) 0%
2665 Villa B2/03 0%
2666 substructure 0%
2667 set out 0%
2668 Excavate 0%
2669 Conc. Foundation 0%
2670 Backfill 0%
2671 termite treatment 0%
2672 DPC (where applicable) 0%
2673 frame 0%
2674 set kickers 0%
2675 Conc. Columns & shear walls to GF 0%
2676 Conc. Plantrooms 0%
2677 Conc. GF slab and beams 0%
2678 Blockwork up to FF slab 0%
2679 set kickers on GF 0%
2680 Conc. Columns & shear walls to FF 0%
2681 Conc. FF slab & beams 0%
2682 Blockwork up to roof 0%
2683 set kickers on FF 0%
2684 Conc. Columns & shear walls to roof 0%
2685 Conc. Ring & tie beams 0%
2686 Roof & Ceiling 0%
2687 Fix wall plate & truss 0%
2688 Fix purlins and rafters 0%
2689 Fix shingles ( subject to receipt of timber) 0%
2690 Fix ceiing battens & joists 0%
2691 Fix ceiling boards 0%
2692 Finishes 0%
2693 Wall plaster (internal & External) 0%
2694 Floor finishes 0%
2695 Fix windows & doors 0%
2696 Fix fittings and Fixtures 0%
2697 M&E Installations 0%
2698 Cable Tray, Conduit and Wiring 0%
2699 Electrical boards and connections 0%
2700 Electrical accessories 0%
2701 Light fittings and ceiling fans 0%
2702 Hot and cold water 0%
2703 Waste and sewage incl. biobox 0%
2704 Electric water heater 0%
2705 Swimming pool ( not applicable) 0%
2706 Split unit installation 0%
2707 Toilet ventilation, grilles 0%
2708 Villa B2/09 0%
2758 Villa B2/10 0%
2808 B4 Standard Villas ( 2 nos) 0%
2899 BC311 Executive Villa 0%
3115 P3 Presidential suites ( 3 nos) 0%
3245 Hilltop sunset deck( subject to receipt of GFW drawings) 0%
3280 External works ( subject to receipt of GFW drawings) 0%
3289 Drainage works ( subject to receipt of EME details) 0%
3292 Lot 4 0%
3293 Couple treatment room( subject to receipt of GFW drawings) 0%
3334 Single treatment room( subject to receipt of GFW drawings) 0%
3375 Dive Centre( subject to receipt of GFW drawings) 0%
3413 Kid's club( subject to receipt of GFW drawings) 0%
3452 Recreation House( subject to receipt of GFW drawings) 0%
3491 Watersports rental( subject to receipt of GFW drawings) 0%
3529 3 Meals restaurant( subject to receipt of GFW drawings) 0%
3570 Beach Pool Bar( subject to receipt of GFW drawings) 0%
3611 Signature Pool area( subject to receipt of GFW drawings) 0%
3650 Wedding Chapel( subject to receipt of GFW drawings) 0%
3685 BOH/Admin Building( subject to receipt of GFW drawings) 0%
3726 Chi Sanctum( subject to receipt of GFW drawings) 0%
3767 Yoga Pavillion( subject to receipt of GFW drawings) 0%
3805 External works ( subject to receipt of GFW drawings) 0%
3814 Drainage works ( subject to receipt of EME details) 0%
3817 M&E Installations- External 0%
3828 Sundries 0%
3829 Site cleaning & demobilisation 0%
3830 Project Commissioning 0%
page 121
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
5.2. Conclusion
At the outset of the Contract the Contractor suffered delays in
setting out the works. This was followed by significant disruption
caused by excavation in hard rock and partial suspension of
Works. With respect to the Contract and the Contractor’s
Programme of Works to which consent has been given, such
departure from his original planning has caused significant
increased cost. In addition, significant increases in quantities of
work caused the Contractor to fall further behind his programme.
page 122
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
6. Financial Analysis
6.1. Consequences
During the periods of delay and disruption which results directly
from the varied site circumstances, varied scope of work, piece-
meal work or an adverse condition, the Contractor has incurred
costs of reduced and non-productive work necessitated by
retaining levels of resources, which otherwise would have been
decreased or deployed elsewhere. The Contractor would
maintain that it was not reasonable to discharge Staff and
Labour and remove equipment off Site for those periods. These
costs include idle equipment and labour and other direct costs,
and are recoverable under the terms and conditions of contract.
Finally, because of the delays, which are not the fault of the
Contractor, substantial completion of the whole Works can only
be achieved beyond the original date. Consequently, the
Contractor will incur additional costs in the extended period that
is not recovered through the rates and prices of the contract.
page 123
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
6.1.1.Direct Cost
The direct cost of this event, delay and disruption, is the cost of
labour, staff and equipment directly employed at the Site
including profit.
6.1.2.Indirect Cost
Indirect cost flows from on-site establishments such as the
Contractor’s head and site offices and yard, which overheads
are only partially recovered during the periods of planned
construction operations when extended.
6.1.3.Consequential Cost
The consequential cost is the effect on the work in terms of
disruption to the various activities and prolongation of the
Contractor’s time related resources arising from re-sequencing
the planned work.
page 124
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Suspension of Work;
The loss and expense were not provided for, nor reasonably
contemplated by, the Contract. The Instructions did not result
from a breach by the Contractor. Accordingly, the loss and
expense must be added to the Contract Price.
page 125
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
6.4. Conclusions
In failing to provide final survey data and all the various design
details, the unforeseen ground conditions, instructing
suspension of the Works and subsequently altering the
sequence, timing and logic of his original planning, the Employer
has caused the Contractor to unavoidably incur greater costs,
loss and expense than would have been the case had the failure
not occurred. These costs are evaluated in subsequent sections
of this submission.
Since these costs, losses and expense have flowed directly from
the Employer’s failure and subsequent deviation from the terms
of the Contract, the Contractor is entitled to be compensated for
them by the Employer paying a fair value for the different type of
work that has been performed.
page 126
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 127
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
8. Additional Payment
8.1. Introduction
Each of the sections in this document briefly describes the
events that have occurred that are contrary to those envisaged
at time of tender. Therefore, allowance for the event so
described has not been made in the tender rates and prices.
This Chapter of the document contains the financial details,
demonstrating the reimbursable additional value or cost of these
disruptive events.
page 128
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 129
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Total 683,441.44
8.2.1.2. Equipment
page 130
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Total 2,729,888.31
Total 37,067.84
page 131
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Total 111,203.51
Total 139,342.69
page 132
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Total 418,028.07
Total 4,118,971.85
page 133
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Equipment
page 134
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Total 3,218,973.43
8.2.4.Other Costs
The following activities caused the Contractor to incur additional
costs because of the changed events described in this
document. At time of preparing this submission these costs have
yet to be ascertained and will therefore, be part of future claim
submissions.
page 135
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Q uantity
Des c ription of Materials Ordered Date O rdered Amount rec eived B alanc e C omments
F OR AL L 55 VIL L AS
50K G bags P ortland C ement 2,800.00 04/04/07 300.00 2,500.00 B alance on order s ubject to payment to s upplier
P lywood for S huttering/R oofing 6,000.00 14/11/07 1,800.00 4,200.00 B alance on order s ubject to payment to s upplier
C rus her D us t 6,000.00 23/06/07 1,565.13 4,434.87 B alance on order s ubject to payment to s upplier
Aggregate 8,000.00 25/06/07 1,222.64 6,777.36 B alance on order s ubject to payment to s upplier
P las tering S and 1,000.00 16/07/07 80.00 920.00 B alance on order s ubject to payment to s upplier
150mm S oild concrete B locks 125,000.00 05/07/07 31,975.00 93,025.00 B alance on order s ubject to payment to s upplier
100mm Hollow concrete B locks 15,000.00 15/07/07 2,340.00 12,660.00 B alance on order s ubject to payment to s upplier
A252 W eld Mes h (R oadworks ) 912.00 14/05/07 162.00 750.00 B alance on order s ubject to payment to s upplier
High tens ile s teel-8,10,12,16,25mm (tons ) 500.00 14/01/07 158.00 342.00 B alance on order s ubject to payment to s upplier
C edar S hingles (s qm) 12,757.64 03/05/07 3,712.00 9,045.64 B alance on order s ubject to payment to s upplier
Iroko timber (external cladding) L M 54,198.00 07/05/07 1,548.00 52,650.00 B alance on order s ubject to payment to s upplier
12mm G yps um boards (S H E E T S ) 5,600.00 03/02/07 5,600.00 0.00 Awaiting for other building from I.D
S tainles s s teel threaded rods 12,16mm 16,300.00 09/11/07 8,110.00 8,190.00 B alance on order s ubject to payment to s upplier (Not B .O .Q item)
S tainles s s teel gus s et plates (variation) 450.00 09/11/07 50.00 400.00 B alance on order s ubject to payment to s upplier (Not B .O .Q item)
B alau T imber (L M) 169,074.50 08/06/07 6,148.16 162,926.34 B alance on order s ubject to payment to s upplier
T reated P ine T imber (L M) 94,148.50 20/04/07 43,225.50 50,923.00 B alance on order s ubject to payment to s upplier
8.2.5.Finance Costs
The additional costs defined within the preceding sections of this
chapter on claim for additional payment have been borne and
financed by the Contractor. The Contractor has paid the costs
by obtaining bank loans or overdrafts, or by the use of working
capital that would have been employed in profitable work. These
financing costs are an additional cost incurred as a
consequence of the circumstances herein and, become part of
the reimbursable sum.
The Contractor has carried this additional cost since the outset
of the Contract to the present date, end of May 2008, a period of
about 14 months.
page 136
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
8.2.6.Grand Summary
The additional costs defined within the preceding sections of this
chapter are summarised below:
page 137
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 138
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
9. Statement of Claim
During the course of performing the Contract Works to May
2008, the Contractor has drawn the Project Manager’s attention
to the fact that the Employer has deviated from certain of the
contractual requirements established in the Contract. He has
required the Contractor to perform the Contract Works in a
manner significantly different from that laid down in the Contract
Conditions and Specifications. These deviations are:
page 139
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
10.Appendices
The next table shows the average indirect costs for the head
office (Victoria, Mahe) and site office expressed as a
percentage. The Contractor expects to recover as a return on
turnover, approximately 9% on the head office costs and 3% for
the site office costs.
page 140
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
A3 Villas - Lanai screens - Request for Contractor requested design for Clarification provided on 13 Mar '08.
005 12-Mar-08 RFI-005 Island Construction Polus Investments designs required Information A3 Villas lanai screens Information was required by 15 Mar '08
All Villas – Bathroom Entrance
Door Type DO.02 – Infill Clarification required on the
Bamboo Resin Panel – Request for descrepancy in sizes of the bamboo
006 12-Mar-08 RFI-006 Island Construction Polus Investments Discrepancy in Size Information Villas resing panel Clarification provided
Clarification required on the
Mock Up Villas – Window Sill & desrepancy in sizes of window sill
Lining Details – Cut Stone Request for Mock up villas A3/32 shown in the desgn and the one Clarification provided on 16 Mar '08.
007 13-Mar-08 RFI-007 Island Construction Polus Investments Cladding – Discrepancy in Size Information and B2/03 supplied Information was required by 16 Mar 08
page 141
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
10.3. Correspondence
ID Date Reference From To Subject EventType Location EventDescription Notes
PS, Ministry of Concessions Granted for the Shangri-La Resort Concessions granted during the
001 05-Jul-07 FIN/PS/POLUS/83 Finance Polus Investments Project Information Project construction phase of the project
Environment Visit Report - 10 Shangri-La Resort Contractor's response to
002 11-Jul-07 LIHRD/env/05 Island Construction Polus Investments July 2007 Environmental Project Environmental visit report
Quotation for Retaining Wall
along CHI-SPA Shangri-La Resort Quotation for Retaining wall along
003 30-Aug-07 LIHRD/VO/01 Island Construction Polus Investments area/Restaurant Area Quotation Project CHI-SPA area/Restaurant area
Shangri-La Resort PM requested to approve the list of
004 30-Aug-07 LIHRD/VO/02 Island Construction Polus Investments List of Variations Variations Project variations
Shangri-La Resort New rates for boat transport as a
005 03-Sep-07 Angel Fish Island Construction New Rates for Boat Transport Information Project result of increased fuel prices
Shangri-La Resort Schedules for boat transport from
006 12-Sep-07 Island Construction Angel Fish Transfer Boat to Long Island Information Project Mahe to Long Island and back
Inquiry from Independent Shangri-La Resort Submission of the company's
007 19-Sep-07 Island Construction Polus Investments Engineer Information Project technical profile
Instructed variations and changes are
being made prior to reaching
agreement on the price contrary to
terms and conditions of the contract.
Lump Sum Contract Price - There exists disparities between BQ
Variations to Scope of Works - Shangri-La Resort Request for Employer's agreement to quantities and quantities measured
008 24-Oct-07 Island Construction Polus Investments Instructions Variations Project payment of changes and variations from construction drawings.
page 142
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Shangri-La Resort
015 26-Oct-07 Island Construction Polus Investments Quotation for Rock Excavation Quotation Project Quotation for rock excavation
page 143
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 144
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
page 145
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Interim Report on Programme Programme & Shangri-La Resort Report on Programme of Works and
056 08-Apr-08 Island Construction Polus Investments of Works, Progress & Valuation Valuation Report Project Request for Time Extension
PM responds to ICCL's objection to
Shangri-La Resort enter into nominated subcontract with
060 09-Apr-08 E-18-09.04.08 Polus Investments Island Construction Nominated Subcontractor Subcontract Project EME
Nominated Subcontract -
Subcontract Agreement - Shangri-La Resort Reason for Objection of nominated
061 14-Apr-08 E-17-07.04.2008 Polus Investments Island Construction Reason for Objection Subcontract Project subcontract agreement
Extension of Time for
Completion - First Interim Detailed Request for approval to submit
Entitlement - Detailed particulars for Shangri-La Resort detailed particulars within 45 days
062 15-Apr-08 Island Construction Polus Investments Particulars Extension of time Project from 15 April 2008
Shangri-La Resort Statement for works done up to End
063 15-Apr-08 Island Construction Polus Investments Interim Statement Nr. 08 Statement Project of March 2008
Interim Statement Nr. 08 -
Materials On & Off site - Shangri-La Resort Amended statement incorporating off
064 17-Apr-08 Island Construction Polus Investments Amendment Statement Project site Balau timber
page 146