Professional Documents
Culture Documents
PROJECT (OIF )
OMIFCO
SUR – SULTANATE OF OMAN
Some Figures
- Cooling Water & Sea Water:
Total length 13 km
2000 spools
Diameter up to 3000 mm
INTRODUCTION (FW & PW)
Figures
Fire Water
1st site delivery was on Dec, 2003.
Cont.
INTRODUCTION
Erection of Pipes
Cont.
COMPOSITION
Pipes
Jointing
O-rings rubber type (diameters above 1800mm) “Kroll & Ziller” gaskets Reinforced C.S Blind Flanges
Backfilling.
Type of backfill material was taken into account
for the pipes design.In Omifco project the
following materials have been used
SC1 material (20mm aggregates): (diameters
above 700mm)
SC2 material (10mm aggregates): (all
diameters)
Backfilling
Cont.
INSPECTION
Joints Inspection
Lamination joints
Hardness test was applied to the joints after
24hr from erection by a Barcol tester
machine.
Cement Joints
Visual Inspection.
Double Bell Coupler Joints
Visual Inspection.
Rubber Seal Lock Joints.
Visual Inspection.
Lines Inspection
Cleaning
Wet cloth with broom stick
Deflection Test
Ovality of the pipes to be tested using deflect
meter supplied by the vendor.
HYDRO-TESTING
Backfilling
Pipes to be backfilled 1m above the pipe crown level and the joints to be left
exposed during the process.
Blind Flanges
Carbon Steel Blind Flanges to be used against the RTRP Blank Flanges
Design
C.S blind flanges required thickness is high according to the ASME BPV or
TC standards.
Reinforcement design to be used to reduce the required thickness as shown
in the picture.
Installation
Bolts to be tightened by sequence up to defined maximum torque value (depending
on gasket type & diameter)
Actions taken
1.) Client's Engineering approved to use SC2
material (as 10mm aggregates).
2.) Crusher plant was mobilized to produce SC2
material.
Problem & Action
2. Test limits
Problem description
On sea water and cooling water
networks, and as per to the lines design,
no valves limits are provided.
Actions taken
1.) Lines were extended to as much possible
as to site situation.
2.) Temporary spools with flange were used
to divide the lines.
3.) After completion of both tests, short
spool to be laminated to join the 2 lines
(Golden Joints), and those two
laminations joints will be left exposed
and to be tested during commissioning
at service test.
Problem & Action
3.Thrust Blocks
Problem description
As the non-restrained pipes (Double Bell Coupling
Joints)do not withstand axial thrust force due to
hydrotest pressure, thrust blocks have to be installed.
The testing pressure of the sea water supply line is 6
bars and the diameter is 2400mm.
The calculations give a thrust block of 420 tons ( 175
m3 of concrete).
Actions taken
An addition of 25 to 30 meters of restrained pipes and Joint Tester
Flange with short spool was erected to avoid thrust
block (height of backfilling above pipes depends on
length of restrained portion)
PROBLEM & ACTION
4. Gaskets
Problem description
Although CAF asbestos, Neoprene, and Kroll & Ziller non-load Bearing flange joints
gaskets were used for hydro-testing, but non of them was suitable for RTRP lines as
leaks occurred at pressure more than 5 bars.
Actions taken
“Kroll & Ziller” gaskets (G-ST-P / OE Flexible design Gasket with Visible Stainless
Steel) have been re-ordered by CCC for testing purpose and by Client as permanent
gaskets.
DynaFlow “Engineering”.
While designing, Venting were not taken in consideration.
Test limits were not taken in consideration, i.e. for non-restrained pipes
plain end were fabricated rather than double-bell coupler end “Wear
Box”.
Late answers for our inquiries.
Revised drawing were sent after when lines’ installation and testing are
accomplished.