QA/QC
CONTENTS OF PQP:-
a) Responsibility management
b) Document management and control
c) Requirement scope
d) Design control
e) Development control
f) Testing and quality assurance
g) Risk and quality audit
h) Training requirement
2) PROJECT ORGANIZATION:-
3) AUDITING:-
For every project, regardless of its size or the nature there should
be size periodic quality audits to measure the adherence to the
quality standards, these audits can be done by an internal team or
an external team.
2
Dec. 15
QA/QC
AUDIT
External Internal
Survey
Documentation First party
4) SCHEDULE-Q:-
3
Dec. 15
QA/QC
STARTING OF PROJECT:-
4
Dec. 15
QA/QC
Quality control plan ensure all the stages are completed and
signed off.
Inspection checklist ensure all the stages are completed and
signed off.
Verify material certificates such as mill test certificates etc.
Verify the following procedure such as Welding, repair, NDT,
PWHT, Hardness, PMI, Hydro test, Coating/Painting.
Verify the qualification level and validity of the welders and
NDT personals.
Verify the inspection report of following discipline and
ensure that they cover all appropriate joints and structure
such as Visual, NDT, Dimensional etc.
Verify the hardness test report.
Verify that PMI inspection report.
Verify the PWHT report/charts etc.
Verify the Hydro test, pneumatic test report.
Verify as build drawings are completed.
Verify weld map are available for traceability.
Verify name plate rubbing details are available.
Verify the concession request site query etc.
Verify permit to work.
Verify painting/coating inspection reports.