Professional Documents
Culture Documents
R.D. Varangaonkar
Gammon India Limited, Mumbai, India
SYNOPSIS: Pump concrete technique is adopted very often on most places. Efforts are made and designs
are improved to pump concrete to longer distances and higher heights. This paper deals with high pressure
concrete pumped to a height of 780m. As on date the world record for pumping concrete is for a height of
535m. To pump the concrete to 780m height, one concrete pump was specially designed and manufactured.
Concrete pipes were also specially designed and manufactured to take up such high concrete pressure
including the pipe jointing clamps. Method for cleaning the pipe was also developed in the eventuality of
chocking of concrete in pipe. A thorough and detailed planning was done to achieve this tough task. This
paper describes in detail the minute planning done for the projects to achieve this tough task.
TOSH NALLAH
CONCRETE DAM
DIVERSION TUNNEL HO
RS 6.0
E
R
O D IA
E LOT PB - 3. INCLUDES HRT
SH
AP FROM RD- 24733 TO 31371 M
E D
H.
R.
T. CONSTRUCTION ADIT
6.0 M DIA CIRCULAR H.R.T. ADIT NO. 3
HURLA NALLAH
TRENCH WEAR
FEEDER TUNNEL BOTTOM ADIT-2 JIW TAIL RACE CHANNEL
PANCHA-HURLA AN
FEEDER TUNNEL-II
3.0 M DIA. TO PRESSUIRE SHAFT AL
LA
SA
H IN
ADIT NO. 1 FEEDER TUNNEL-III
JR
PORTAL EL. 2185.00 IV
SHEELAGARH ER
PANCHA MALLAH
TRENCH WEAR POWER HOUSE
ADIT NO. 3A 4NO.PENSTOCKS 2.5M DIA.
2NO. PRESSURE SHAFTS 3.5M DIA.
ADIT NO. 3A ADIT TO PRESSURE SHAFT TOP
ADIT NO. 3
MANIHAR-PANCHA VALVE HOUSE
FEEDER TUNNEL-I
ADIT TO SURGE SHAFT BOTTOM
TRENCH WEAR APPROACH ADIT
ADIT NO. 2 TO SURGE SHAFT TOP
ADIT NO. 4
A
LAYOUT PLAN
Sketch showing the location of inclined pressure shafts and approach Adits
Adit No. 5 Bottom Adit-2 (for TBM Erection
2 NO. Pressure Shaft
Portal EL. 2100.00 (3.5 M Dia) at Spacing & Further Excavation of 3.5m. dia JIWA NALLAH
(6000Ø D Shaped Length 515m.) of 48m c/c Pressure Shaft
Portal EL. 1332.00 4 No. Penstocks
6000 Ø HRT (2.5 m. Dia at Spacing
Length 640.00m.
6000 Ø D Shaped of 24m c/c
Up Surge Gallery Bottom Adit-1 to Penstock
325m. Long at EL. 2225 Portal EL. 1332.00
Vertical Bend Line
(6500Ø D Shape Length 215m.
6000 Ø D Shaped
Down Surge Gallery
Access to Lower
250m. Long at EL. 2117.50 Manhole SA
IN J
SA
1148
length of 1542m. The surface powerhouse of then making arrangement for laying the
800MW, consisting of four units. These two concrete pipeline.
inclined pressure shafts were bored by Double • To carry the concrete by transit mixers
Shield Tunnel Boring Machine (TBM). The bored mounted on the trolley would be very slow
diameter of inclined pressure shaft is 4.8m operation and charging the transit mixers
diameter. would be tough or almost unfeasible.
• The pumping of concrete from top at 30 degree
2. THE TASK would be difficult because of air trapping.
Laying the pipeline would again interfere with
Inclined pressure shaft boring was completed by ferrule transportation.
TBM and was simultaneously lined by pre-cast • Approach to the concrete pipeline would be
segment lining. The task now left out is to install only from the trolley which is used for
the ferrules 3.5m diameter inside the pre-cast lined transportation of concrete.
tunnel and concrete behind the steel liner, i.e. to fill • Pumping from bottom also needed very
up the gap between pre-cast concrete lining and meticulous planning for –
steel ferrules.
STEEL LINER
3.50m
4.3m
4.70m
4.88m
Sketch showing the bored diameter, pre-cast segment and steel liner and showing the gap for concrete
Three options were available for concreting – - Arrangement for shifting and extending
1. To carry the concrete from top by transit pipelines.
mixers mounted on trolleys. - Arrangement for manpower to reach the
2. To pump the concrete from top. location of concrete.
3. To pumps the concrete from bottom. • Considering the advantages and disadvantages
of both the operations, it was decided to pump
First two options for carrying concrete from top was concrete from bottom. This will be having
extremely difficult because of : advantage that it will be independent from the
• It was interfering with the transportation of operation of ferrule transportation. Manpower
ferrules requiring very meticulous interaction can also easily reach with the help of
for carrying the ferrules to the location and independent winch and trolley from the
bottom. The only problem was to find a pump
1149
suitable for pumping concrete approximately at Table 1. Pump BP 4000 HDR – 180/125 –
a height of 800m. Specifications & Details
1150
4. PIPELINE designed in such a way that it would not tilt at 30
degree when pulled up. Necessary counter weight
4.1 Design of Pipe was designed. Five numbers of pipes weighing
In order to sustain such a high pressure of above approximately 1 ton would be transported at a time
300 bar, a special pipeline was designed and since frequent trips of winch need to be avoided.
manufactured in Germany. Also out of the various
Support for the rails was designed and “I” section
options of pipeline diameters of 100mm, 125mm
and 150mm, it was found that 125mm diameter pipe was laid down to cross members welded to erected
would be most suited for this type of work. For such ferrule. A proper arrangement also was made for
a high pressure, special pipe was to be manpower to safely travel on this winch.
manufactured and in case only one thickness of pipe
was adopted throughout the length, the cost was
coming exorbitantly high. Concrete pressure since 5.1 Selection of winch
will be reducing from bottom to top, it was planned The special trolley has to travel from 0m to 1542m.
to reduce the pipe thickness gradually. Two types of
It was since required to be pulled from top,
Pump-1
Pump-2
1151
Sketch showing inclined trolley, arrangement for rail and cross members and return pulley.
Keeping in mind the safety of the people .013cum/m. This amount of concrete will be stored
traveling on the winch and in the eventuality of in the length of concrete in use at particular
location. The task is to use the concrete in the
requiring to stop the winch anywhere on the path,
pipeline and not allowed to go waste and then clean
the winch was so designed that the wire rope was the pipe. It was therefore planned to use shut off
having one core of wire by which winch could be valves at designed locations which can be closed
operated by remote control by the passenger when required.
(i) In case of chocking, a particular section can be
traveling on the trolley.
isolated and cleaned.
Requirement of concrete was only 5 cum/m. (ii) Once the concrete is complete, shut off valve at
Therefore it was decided that the existing the bottom can be closed and sponge ball with
arrangement of 30 cum batching plant and three water column can be inserted in the pipeline
transit mixers will be used. The only addition was to and with the help of second pump with which
erect one silo and weighing arrangement for fly ash. bye-pass line is installed, water or bantonite
Planning was also required to be done for cleaning slurry can be pumped, pushing the complete
the pipeline. The pipeline would carry concrete concrete column up and to the location. When
1152
this sponge ball reaches the top, trap basket • Aligning of ferrules at location 2 hours
will not allow the ball to cross but complete • Preheating and welding for first ferrule 48 hours
concrete can be unloaded to the location. When • 48 hours x 2 (for second ferrule) 96 hours
the sponge ball reaches the top, water from the • Concreting of 60 cum 6 hours
pipeline can be emptied by the by-pass • Cleaning the pipeline 1 ½ hours
emptying pipes which unload the complete • Total cycle time for 12m pipeline 107 ½ hours
water and bantonite slurry into the tank and
cleaning the entire pipeline simultaneously. For
8. CONCLUSION
more than 100m of pipeline length, care was
taken that water is not allowed to empty • The work is very difficult and hazardous in
without a pressurized cleaning scrapper nature.
otherwise concrete may stick to the pipeline • The working place is also very restricted.
walls.
• Working on inclined 30 degree becomes very
6. SAFETY strenuous and difficult.
• Selection and design of concrete pump,
Considering the length of travel, restricted place of
work and tremendous load on the return pulley and suitable concrete pipeline was most important
winch, the following safety measures were taken. decision for success of project.
1153
He is Fellow of five premier institutions of India • Industrial Structures
including Indian National Academy of Engineering & • Cooling Towers, Water Tower, T.V. Towers.
Member of eleven institutions of various natures. • Silos & Prilling Towers.
He has about 40 years of rich experience in • Prestressed Concrete Bridges Rail-cum-Road
construction of variety of Civil Engineering large scale Bridges.
• Pile Foundation - Large diameter and depth.
projects as under.
• Mega Hydro-Electric Projects.
1154