B. MICRONIZING Section
B.1 Driyer Micro ex. China 10.unit 10 unit Ok Tinggal finishing
C. WINOWING section.
C.1 SC 250x2000 IDR Screw input double roll.u/250x2000 10 10 9 8 off inproses team mekanik
C.2 DR.219-315-00 Double roll 10 10 9 8 off inproses team mekanik
C.3 BE 180x8000-00 Bucket elevator Input Winnowing 10 10 9 8 7 6 5 4 off inproses team mekanik(tinggal penyambungan belt)
C.4 W24-00 Assy.Drg WINNOWING machine 10 7 1 1 1 Ok 10 unit Minggu pertama bulan februari sdh selesai 7 unit,
dan diteruskan minggu ke tiga bulan maret karena mesin baru masuk
w24-Tcrew.450x900 Tank colecting return ex winowing (tank kulit) 10 sudah diposisi tinggal pemasangan piping shell section
C.5 BE.180x5500 Bucket Elevator L.180x5500 Return 10 10 9 8 7 6 5 4 3 off inproses team mekanik
C.6 CY W1320x5025-00 Cyclon For Winowing. 10 10 Ok Assembling sudah selesai 10 unit tinggal reposisi
C.7 BE.180/9500-00 Bucket Elevator ( Input silo NIBS ) L.180/9500-00 10 10 9 8 7 6 5 4 3 off inproses team mekanik (untuk line 9 dan 10 sudah selesai dan progress
belanjut diline 7) dan line 3 sampai 6 sudah diposisi semua.
C.8 NS.240-420 Nibs Silo. 10 10 Ok ok 10 unit
Total QTY Januari Februari Maret April Mei Juni
No Item No. Description
/ 10 line
Keterangan
I II III IV V I II III IV I II III IV V I II III IV I II III IV V I II III IV V
C.PIO.1 IWN 126/2250 Ducting Output Bucket Input Winowing ( Corong Output BE ) 10 10 9 8 7 6 Masuk kelompok ducting input winnowing
C.PIO.2 IRC 165x1725 Ducting Input Return Crusher ( Corong Output BE Return) 10 10 9 8 7 6 Dalam progress team mekanik
C.PIO.3 ISN 165x2597 Ducting Input Silo Nibs ( Corong Output BE Input Silo Beans ) 10 10 9 8 7 6
C.PIO.4 Piping Nibs Conveying Fr Silo NIBS to Hopper Scale 3 dia 4" 10 10 9 8 7 6 5,4,3,2,1 OK OK
C.PIO.5 Piping Shell Conveying Ø8" + 6" + 3" 2 ln:6,7,8,9,10 OK Pemasangan dimulai dari assy pipa 8'' area shell section,block line 6,7
8,9,10 sudah selesai (minggu ke dua bulan Mei dilanjut di blok line 1-5)
C.DS Dust Collecting System
C.DS.1 DUC. W 24 Ducting Suction Winowing 10 subkon Janur (line 5,6-7,8-9,10)
C.DS.2 ST.B 24 Structure Blower 10 5 5 OK OK
C.ST W 24-14 Structure / Plateform Winowing 10 7 1 1 1 Ok 10 unit Minggu pertama bulan februari sdh selesai 7 unit,
dan diteruskan minggu ke tiga bulan maret karena mesin baru masuk
C.BS.1 BDS.BE 180/8500 Bordes Bucket Elevator input Winowing 10 ln.10 ln 9 ln8 ln 7 6 inproses team mekanik
C.BS.2 BDS.W 240 Bordes Intermediete Winowing 10 7 1 1 1 Ok 10 unit OK
C.BS.3 BDS.BE 180/5500 Bordes Bucket Elevator Return 10 ln.10 ln 9 ln8 ln 7 6 inproses team mekanik
C.BS.4 BDS.BE 180/9500 Bordes Bucket Elevator input Silo Nibs 10 ln.10 ln 9 ln8 ln 7 6 inproses team mekanik
C.BS.5 BDS.NS 240/480 Bordes Silo Nibs 10 ln.10 ln 9 ln8 ln 7 6 inproses team mekanik
C.EQ.1 ex china Type : Y9- 38-6A Blower Centrifugal Fan for Shell suction Winnowing 10 OK Sudah diposisikan 10 unit
D. ROASTER Section
D.1 NHS.001 OT 216 Nibs Hopper Scale 3 10 10 OK OK
D.2 CY 13003 SC 3 Cyclone Dust For Scale 3 5 2 3 1 OK OK tinggal tunggu pemasangan ducting(pekerjaan subkon)
DC SCL3 H 001-1 Ducting Cyclone Scale 3 5 OK subkon Janur (line 5,6-7,8-9,10)
D.3 CR 7000-00 ROASTER set. 10 10 OK OK
D.4 CR 7004 Assembling inner assy 10 10 OK OK
D.5 CR 7007 Assembling ducting system 10 3 3 4 OK OK
D.6 CR 70011 Assembling nibs outlet 10 2 3 3 2 OK OK
D.7 CR 7003 Modifikasi as pintu 10 3 3 3 OK OK
D.8 CR 7011 Setting Instalasi gas train 10
D.9 Assembling burner 10 5 OK dan 5 unit lagi belum terpasang
D.10 CR 7010 WT.80/70 Assembling watter tank dan instalasinya 10 Watter tank sudah diposisikan
Assy chamber 10 4 5 OK OK tinggal pemasangan bata api
D.11 CR 4246-00 COOLER Assy 10 10 OK
Pemasangan bata api OK Sudah terpasang 10 unit subkon Rabana
D.12 RV 175-00 Air lock Rotary Valve Type 175. 10 OK 10 unit sudah diposisikan
D.13 CY.C 1320x5025-00 Cyclone For Cooler 5 5 OK Sudah diposisikan OK
D.EQ.4 Centrifugal Fan (Aspiration- section). BRSZ.500.direct drive.(180°c) 7000m³/h.inlet 10 10 sudah diposisikan
ex china type : YX9-35-5C 350-outlet 300.-10hp OK
D.EQ.8 ex china type : 4-72-4-5A Blower Centrifugal Fan ( Aspiration Suction Cooler ) 10 10 OK sudah diposisikan
D.EQ.9 TRL 200 Blower ( Blower Nibs Transfer ke Silo Nib SMM ) 10
E. GRINDING section
E.1 NH SMM 001-OT-216 Nibs Hopper SMM 20 OK
PI.SMM 267 Ducting Input SMM 20 subkon Janur (belum ada progress)
E.2 CY-13003-SMM Cyclone Dust For SMM 10 10 OK sudah diposisikan OK
DCS.216 Ducting output Cyclone SMM 10 subkon Janur (belum ada progress)
E.3 SCD-SI-SMM.H 001-L2 Ducting Cyclone Nibs Hopper SMM 10 OK subkon Janur
E.9 FBM 42/2812-00 Fine Ball Mill Single Drum 40 OK(sudah diposisikan)
E.15 HMGRC 150 / 150 Homogenizer Tank 2 T / as per Hopper Massa Tanks 5 OK(sudah diposisikan)
E.PIO.2 LPLT…. Liquar Piping at Liquar Tank 10 ln.9,10 7,8 5,6 3,4 In progress team mekanik
E.EQ.1 Ropper Pump 3611 HB Non Jacket, Pump for Grinding Section 40 OK(sudah diposisikan)
F. PRESS section
F.1 Mesin Press Press Carle Mountenary 16 Pot 20 OK(sudah diposisikan)
F.3 FP 2000-600 Filter Butter 2,5 ton ( XAZ 40/630-30UB ( Ex China ) 5 OK Sudah diposisikan 10 Unit
F.4 CBF 600x750-001 Collecting Butter Filter 100ltr 10 OK Sudah diposisikan 10 Unit
Total QTY Januari Februari Maret April Mei Juni
No Item No. Description
/ 10 line
Keterangan
I II III IV V I II III IV I II III IV V I II III IV I II III IV V I II III IV V
F.PIO.1.6 BPPS-PM-CT.1D Butter Scale Table 20 9,10 7,8 5,6 3,4 1,2 OK OK
G. CAKE section
G.1 SC U 250 x 14000 Screw Out put Cake Breker U 250 x 14000 mm 5 9,10 7,8 5,6 3,4 1,2 OK OK
G.2 SC 250x5000.IBSC-00 Screw Input Silo Cake U250 x 5000 mm 5 9,10 7,8 5,6 3,4 1,2 OK OK
H. TEMPERING section
H.1 Butter Tangk (pakai Liquor Tank 18 Ton 5 Unit, mat MS (posisi Gd.2) 5 Ok(subkon)
Insulation Tanki 18 T 5 Ok(subkon)
H.5 BPBOS Butter Piping Block Off Section ( Pipa, Support, Valve dan komp ) 2 off Tunggu material Fitting
I. KULIT section
I.1 CY H 1320x5615-00 Cyclon for Husk 2 OK(sudah diposisikan)
I.2 RV 200 Air Lock : Rotary Valve RV 200 2 OK 2 unit sudah terpasang
I.3 ex china type : 4-72-8C Blower Collecting Shell Section 2 OK(sudah diposisikan)
I.4 SC 250x2000-IBSK Screw Input Bucket to Silo Kulit Kasar Type U 250 x 2000 mm 2 OK 2 unit sudah terpasang OK
I.5 BE 180/8000 Bucket to Silo Kulit Kasar L 180 x 8000 mm 2 OK 2 unit sudah terpasang OK
I.7 SC 250x3000-ICM Screw Input China Mill Type U 250 x 3000 mm 2 off in progress team mekanik(untuk block line 6-10 sudah OK)
I.8 China Mill/ Shell Crusher 2 off in progress team mekanik( Untuk block libne 6-10 sudah OK)
I.9 SC 250x3000-OCM Screw Output China Mill Type U 250 x 3000 mm 2 OK 2 unit sudah terpasang
Total QTY Januari Februari Maret April Mei Juni
No Item No. Description
/ 10 line
Keterangan
I II III IV V I II III IV I II III IV V I II III IV I II III IV V I II III IV V
I.10 BE 180/8000 Bucket Input Silo Kulit Halus L 180 x 8000 mm 2 OK OK
I.12 CY ADS 90/120 Cyclone Air ( Ø 900 x 1200 mm ) + Dust Stabilitzer 2 OK(sudah diposisikan)
J. UTILITIES
J.1 Boiler Cap : 4 t 1 OK
Cap : 6 t 1 OK
- Instalasi pipa Area Boiler Room 2 OK
- Instalasi pipa Main Line 1 in progress team mekanik
Instalasi pipa return in progress team mekanik
- Header 5
- Insulation 2
- PHE 2 OK
- Instalasi Input PHE ( Hot water ) 2 in progress team mekanik
Instalasi pipa return in progress team mekanik
- Insulation 2
J.3 Kompresor 2
- AIR COMPRESSOR & VESSEL 2 OK
J.4 Piping ( pipa kompressor, Fresh water, Cool water, Hot water, Steam ) 10
L. POWER PLANT
L.1 PLN
- Grinding-Liquor-Press-Cake 2 lot
- Gd Cake 2 lot
- Gd Butter 2 lot
- Gudang Kulit 2 lot
- Panel Pendukung
- Panel Mimic Diagram Mesin Produksi
SPESIFIKASI KETERANGAN
180
barang masih ditangerang