South Main Construction Co.

Weekly Construction Report

Project:: Stanger Street Sidewalks Contractor: Date: 12/1/11 Report Number: 7 Day: Su M T W Th F S

Work Performed: 5 Workers on site. One worker was removing metal shoring put in place for the sidewalks. Front loader was in use to pick up and break apart pieces of exisiting sidewalks and then placing them in the dump truck. It seemed that along with sidewalk work they were mapping out an area to run utilities. Already in place was number one rebar that was placed over gravel within concrete curbs that had already been set.
.

Weather
Temp: 36 Degrees F Wind: None Condition: Sunny Humidity: None

Subcontractors & Visitors


Blackstone Construction MIS LAS Trucking and Construction

Equipment at Site Front End Loader Excavator Demo Saw Dump Truck