Professional Documents
Culture Documents
Date No. 1 1 1 2 3 1 7 2
4-Jul-11 7. Equipment & Plant on Site Roller Shovel Water Bowser Lorries Pick up Vibrators Concrete Mixer Generators Backhoe Dumper Low loader No. 2 1 1 3 4 1 2 2 1 1 2
TOTAL 3 Proposed work for the following day Making form work for columns Concreting outdoor cable trench 6. Labour on Site
18 No. 8. Materials on site Ballast Sand Cable slab Building stones Cement Murram Y8 Steel Bar Y12Steel Bar Y16 Steel Bar Y 20 Steel Bar Kerb stones Metal Traupers Scar foldings R 6 Steel Bar Y 10 Steel Bar Concrete Blocks Stera phones Concrete Blocks Dust Binding wire Makers post Fence post Paving slabs Qty. 79 tonnes 102 tonnes 96 No 2177 Rf 82 bags 180 tonnes 82 pieces 0 0 0 133 No 70 pieces 150 pieces 25 pieces 0 490 No. 9"by 9" 44 pieces 105 No 6"by9" 72 tonnes 3.5 Rolls 32 No 47 No. 62 No.
60 8
TOTAL
68
4 Work Done Control Room and Generator Shed 1.Superstructural walling in progress- 270 ft build today 2.Making form work and concreting columns