Professional Documents
Culture Documents
Cash Flow Estimation
Cash Flow Estimation
Sensitivity Analysis
Separation Principle
Cash flows associated with the investment side and the financing side of the project should be separated. While defining the cash flows on the investment side, financing costs should not be considered because they will be reflected in the cost of capital figure against which the rate of return figure will be evaluated.
Incremental Principle
To ascertain a projects incremental cash flows you have to look at what happens to the cash flows of the firm with the project and without the project
Guidelines Consider all incidental effects Ignore sunk costs Include opportunity costs Examine carefully the allocation of overhead costs Estimate working capital properly
Post-Tax Principle
Cash flows should be measured on a post-tax basis The marginal tax rate of the firm is the relevant rate for estimating the tax liability of the firm
Consistency Principle
Cash flows and discount rates applied to these cash flows must be consistent with respect to the investor group and inflation Investor Group The consistency principle suggests the following match up: Cash flow Cash flow to all investors Cash flow to equity shareholders Discount rate Weighted average cost of capital Cost of equity
Principle of Compounding
The Principle of Compounding is used to value amounts received more frequently than annually. For example, the value of 8 percent interest receivable semi-annually would be: A=P(1+0.8/2)2 By similarity, an interest of i percent compounded m times a year would be A=P(1+i/m)m
Dr. Tanuj Nandan, SMS MNNIT Allahabad
Principle of Compounding
One other concept that is based on the principle of compounding, and that we will be using is Future Value (FV). It is the value of a cash flow or flows at some date in the future. In simple terms: where compound interest rates are involved, money moved forward in time is compounded, whilst money moved backward in time is discounted.
Dr. Tanuj Nandan, SMS MNNIT Allahabad
Principle of Discounting
The Principle of Discounting is used to determine the value amounts received in future in Present Value (PV) terms. An amount received in future would be worth less than it is worth today, owing to the concept of Time Value. For example, the value of one hundred rupees received a year from now should be discounted to its present value by using an appropriate Discount Factor. Dr. Tanuj Nandan, SMS MNNIT Allahabad
NPV
t=0
CF t ( 1 + k )
where, t = life of the project CFt = Cash flow (net) in period t (assumed to be at the end of the period; includes initial and terminal cash flows) k = Discount rate
Dr. Tanuj Nandan, SMS MNNIT Allahabad
The net of the inflows and outflows for a particular time period is taken as the cash flow for that period.
IMPORTANT: Depreciation doesMNNIT Allahabad not constitute a cash flow. Dr. Tanuj Nandan, SMS
Therefore, NPV= - 400,000/(1.12)0 + 160,000/(1.12)1 + 155,000/(1.12)2 + 150,000/(1.12)3 + 145,000/(1.12)4 + 140,000/(1.12)5 = 144,779.11 Rs.
Dr. Tanuj Nandan, SMS MNNIT Allahabad
Shortcomings of NPV
NPV is sensitive to changes in cash flows, and to discount rates. A change in market conditions, leading to either reduced levels of cash flows or more expensive capital (and hence higher WACC) could lead to a projects NPV becoming less over time. Even projects with negative NPVs may be useful to the firm- in case of strategic advantages or legal requirements.
Dr. Tanuj Nandan, SMS MNNIT Allahabad
CF /
t
t=0 (1+IRR)
t=0 where, n = life of the project CFt = Cash flow (net) in period t (assumed to be at the end of the period; includes initial and terminal cash flows) IRR = Internal Rate of Return
Dr. Tanuj Nandan, SMS MNNIT Allahabad
Scenario Analysis
What does Scenario Analysis do? It shows how changes in a variable such as unit sales affect NPV or IRR. Each variable is fixed except one. This one variable is changed to analyse the effect on NPV or IRR. Answers what if questions, e.g. What if sales decline by 30%?
Dr. Tanuj Nandan, SMS MNNIT Allahabad
Scenario Analysis
For example, Let us consider three alternate outcomes to the detergent powder example:
Probability Best Case Base Case Worst Case (Optimistic) (Most Likely) (Pessimistic) 0.20 0.60 0.20 Sales Volume (Tonnes) 1,750.00 1,500.00 1,250.00 Sales Price (Rs/ Tonne) 200.00 200.00 200.00
Scenario Analysis
What does Scenario Analysis do? It shows how changes in a variable such as unit sales affect NPV or IRR. Each variable is fixed except one. This one variable is changed to analyse the effect on NPV or IRR. Answers what if questions, e.g. What if sales decline by 30%?
Dr. Tanuj Nandan, SMS MNNIT Allahabad
Simulation Analysis
Simulation Analysis is a computerized version of scenario analysis which uses continuous probability distributions.
Computer selects values for each variable based on given probability distributions. NPV and IRR are calculated. Process is repeated many times (1,000 or more). End result: Probability distribution of NPV and IRR based on sample of simulated values. Generally shown graphically.
Dr. Tanuj Nandan, SMS MNNIT Allahabad
Simulation Analysis
Let us return to the detergent powder example.
We will assume that UNIT SALES are normally distributed, withMean= 1,500 Tonnes Standard Deviation = 125 Tonnes Further, we assume that the UNIT PRICE has a triangular distributionLower Bound =160 Rs/Tonne Most Likely = 200 Rs/Tonne Upper Bound = 240 Rs/Tonne
Frequency 80 100 120 140 160 20 40 60 0 -160000 -120000 -80000 -40000 0 40000 80000 120000 160000 Bin 200000 240000 280000 320000 360000 400000 440000 480000 520000 More Frequency
Histogram
Mean Standard Deviation Max Min CV (NPV) Median Number of Positive NPVs Prob (NPV>0)
Advantages
Reflects the probability distributions of each input. Shows range of NPVs, the expected NPV, NPV, and CVNPV. Gives an intuitive graph of the risk situation.
Limitations
Difficult to specify probability distributions and correlations. If inputs are bad, output will be bad: Garbage in, garbage out. Sensitivity, scenario, and simulation analyses do not provide a decision rule. They do not indicate whether a projects expected return is sufficient to compensate for its risk.
Dr. Tanuj Nandan, SMS MNNIT Allahabad
RFR
Risk
Dr. Tanuj Nandan, SMS MNNIT Allahabad