Resiting and M & E Activities S NO 1 DESCRIPTION SUB STATION 1 REMARKS * Civil work to start by March End & Complete

By May * Existing DG room to demolish * Site Development nearby to complete * To plan for material & vehicle movements * Consultant to submit Shape drawings by 14.02.08 * Excavacation can start by next week * Civil construction drawing will be available by next week * Vendor for equipment supply to finalise by Feb end * Vendor will be on Board by April * Vendor will be on Board by May * Vendor will be on Board by April * PO released * Post PO activities in progress * Delivery by June * Draft tender ready; Finalisation of Specs by Feb end.

ETP

3 4 5 6

ELECTRICAL WORKS HVAC FIRE FIGHTING ELEVATORS

7 8

DG SET IBMS BASEMENT PARKING MANAGEMENT RESITING

9 10

* Scheme to be finalised; targeted for June. * Canteen Building ready for demolition by mid April. * North Block will be ready for demolition by April End.