PURPOSE OF REPORT
The purpose of this report is to keep up to date on the progress my girlfriend and I have made
remodeling our bus. We hope to have this project done by April 21st, 2022. Our estimated
budget for this project is $50,000. Our start date was January 21, 2022.
WORK ACCOMPLISHED:
JANUARY
• There were more mechanical issues than expected. Took extra days to diagnose and
repair.
• Raising the roof proved difficult with insufficient equipment.
WORK REMAINING
MARCH