Exercises for 3 Dimensional Data Base I.

Exercise 1 Create Configurations

ETAP Workshop Notes

1996-2009 Operation Technology, Inc.

Page 1 of 2

Exercises for 3 Dimensional Data Base

1. Create following configurations Name Parameters Normal All PDs are closed. Tie-Open Open Tie CB Co Gen Off Open Generator terminal CB Network 1 Down Disconnect Network 1 from sources

Parameters CB9 open CB3 open CB4 and 6 open

II. Exercise 2 Create, Merge Revisions


1. Create following Revisions Revision Different from Base Revision Revision1 T1: Z=5.5; Cable 2: Length = 500ft, Size = 350 Grp1 Revision2 T3: Z=5.5; Cable 1: Length = 550ft, Size = 350 Grp1 Revision3 Lump 3: 6.5 MVA; T1: Z=6.5; T3: Z=6.5;

2. Revision Merge - I Create Revision4 Merge Revision 1 and Revision 2 to Revision 4. Check the difference between Revision 1 and 4. 3. Revision Merge - II Merge Revision 1 to Revision 3. Check T1 and T3 impedance. Are they same and why? 4. Change in Base Revision Data In Base Revision, change Cable1 and Cable 2: Length = 1000, Size = 750. Run Device Duty Calculation Check cable data in Revision 1 4. Are they same as Base and why? Check report

ETAP Workshop Notes

1996-2009 Operation Technology, Inc.

Page 2 of 2