Professional Documents
Culture Documents
Pinto Chapter 10
9-1
Most common type of sequencing Shown on the line joining the modes
Added during forward pass Subtracted during backward pass
0 A 6 Spec Design 6
6 B 11 Design Check 5
L 4 Lag
15 C 22 Blueprinting 7
10 A 16 Plumbing 6
30
31 A 33 Plumbing 6
30 D 36 Wiring 6
Least L t common type t of f lag l relationship Successors Successor s finish dependent on predecessors start
Lag 3 28 B 33 HVAC 5 33 C 34 Inspection 1
22 A 28 Plumbing 6
Crashing Projects
Accelerating a project by committing more resources than initially planned Principal methods for crashing Improving existing resources resources productivity Changing work methods Increasing the quantity of resources
Cost ($) Crash Cost Critical N Normal l C h Per Crash P Wk ($) Path? P th?
A B C D E F G H
2 3 2 4 4 3 5 2
1 1 1 3 2 2 2 1
2 2
2 2
4 4
4 10
7 13
2 Slack = 0 4 4 4 E 8 8
0 0
Slack = 0
0 1
3 4
3 4
Slack = 0 7 8
3 Slack = 1
4 Slack = 1
Managerial Considerations
Determine activity fixed and variable costs The crash point is the fully expedited activity Optimize time-cost tradeoffs Shorten activities on the critical path p Cease crashing when
the target completion time is reached the crash cost exceeds the penalty cost
What is the lowest cost to complete this project in 53 weeks? Times are in weeks and costs in dollars.
Activity A B C D E F G H Pred -A A B C B, D D E, F G Normal Time 14 5 10 8 6 9 7 15 Min Time 9 2 8 5 5 6 4 11 Normal Cost 500 1000 2000 1000 1600 1500 600 1600 Crash Cost 1500 1600 2900 2500 1900 3000 1800 3600
Program 3.1
Program 3.2
Program 3.3
Program 3.4
Program 3.5
Program 3.6
Program g 3.7