WORK AUTHORISATION

(Outside Normal Working Hours)


Requested by: Site Agent...Approved by: Resident Engineer....
Description of works to be done:
.
.
.
BOQ Item:
Day:....

Date Proposed:...

Resources Required
PLANT

LABOUR

MATERIAL

Request for Supervision ( Q C and Q A Checks).


Assigned Engineers
Representative:.........................
Overtime (hours) @; Rate to be decided by Accounts.
ACTIVITY

DURATION(PERIOD)

Hours witnessed by: Site Agent..


Checked and paid by: Accounts ..
Date:

TOTAL HOURS