Dozer Hrs Calc:

Total Hrs required to complete Project = Volume required to be moved x Production Production = Max. Production x Correction Factors 1 1 0.75 0.83 19500 Ramp Slope = 1% down hill Grade Correction = 1 Operator capability = Average Job Efficiency = (50min/hr) Total volume to be moved = 19,500 m3 Dozer available = D11 Max. Dozer distance = 100m Dozer Blade = Semi Universal 600 Dozer Max. Productivity = 600Lm3/hr

Production

= Max. Production x Correction Factors = 600 x 1 x 0.75 x = 373.5 Lm3/Hr

0.83

Volume Required to be Moved

= 0.3 x 65000 = 19500 m3

Total Hrs required to complete Project

= Volume required to be moved x Production = 19500 / 373.5 = 52.2088 62.6506 (safety factor = 1.2)

Total Days @ 9 hrs per day production

= 5.80098