Professional Documents
Culture Documents
COST BREAK DOWN Weld Split Tee Saim
COST BREAK DOWN Weld Split Tee Saim
PROJECT NO. PROJECT NAME.:Welding & Inspection split tees for hot tapping
Prepared By Checked By Approved By 25/07/2012
Item A
Description
Q'ty
Unit
Unit P
Amount
Engineering Cost
WPS/PQR/WQT Welding Record and Inspection Report 1 1 Lot Lot 35,000 12,500 35,000 12,500
Construction Cost
Mobilization Fitup&Weld Split tees - 12" onto 24" - 10" onto 20" - 16" onto 18" - 4" onto 10" - 4" onto 12" - 6" onto 20" - 8" onto 12" NDE -RT 100% Buttweld(Fitting) -PT Fillet /BW Split tee Equipment/tool -Weld generator/Haib/etc. 1 Lot Sub Total for Labour Cost 75,000 75,000 440,922 440,922.40 20% 7% 88,184.48 37,037.48 566,144.36 1 1 Lot Lot 20,000 8,500 20,000 8,500 2 1 3 1 1 1 1 Sets Sets Sets Sets Sets Sets Sets 31,819 26,634 28,521 12,810 14,822 24,034 17,422 63,638 26,634 85,562 12,810 14,822 24,034 17,422 1 Lot 45,000 45,000
Sub Total Cost OPT Vat Total Cost ( Baht ) NOTE : 1.This price excluding scafloding work 2.This price base on working day time(mon-sat) for holiday factor 1.2 multiply Item B.cost
Item A
Description
Q'ty
Engineering Cost
WPS/PQR/WQT Welding Record and Inspection Report 1 1
Construction Cost
Mobilization Fitup&Weld Split tees - 12" onto 24" - 10" onto 20" - 16" onto 18" - 4" onto 10" - 4" onto 12" - 6" onto 20" - 8" onto 12" NDE -RT 100% Buttweld(Fitting) -PT Fillet /BW Split tee Equipment/tool -Weld generator/Haib/etc. 1 Sub Total for Labour Cost Sub Total Cost OPT Vat Total Cost ( Baht ) NOTE : 1.This price excluding scafloding work 2.This price base on working day time(mon-sat) for holiday factor 1.2 multiply Item B.cost 20% 7% 1 1 2 1 3 1 1 1 1 1
DOWN FORM
r hot tapping
Checked By Approved By 25/07/2012
Unit
Unit P
Amount
Lot Lot
35,000 12,500
35,000 12,500
Lot
45,000
45,000
Lot Lot
20,000 25,000
20,000 25,000
Lot
85,000