COURSE/EXAMINATION SCHEDULE FOR SECOND MATE (FG), FIRST MATE (FG), MASTER (F G), EXTRA MASTER, FISHING GRADE

AND DREDGE GRADE FOR THE YEAR 2012


Date: 19/10/2011

Month
Course Begins

JAN 2012
----1M Ph-II ASM Ex. M(A) ----1M Ph-II ----2M 1M Ph-I 1M Ph-II ASM -----------

FEB 2012
2M --------2M ----ASM ------1M Ph-II ----Dr. (Kol.) NCV, Upgradn. 2M (R) 1M (R) ---

MAR 2012
--1M Ph-I --ASM ----1M Ph-I ------2M ----ASM Fishing (Ch.) ---------

APR 2012
2M --1M Ph-II ----2M --1M Ph-II ASM Ex. M (A) 2M 1M Ph-I ------------Ex. M

MAY 2012
------ASM Ex. M(B) ----------2M --1M Ph-II ASM -----------

JUNE 2012
2M 1M Ph-I ------2M 1M Ph-I --ASM ------------NCV, Upgradn 2M (R) 1M (R) ---

JULY 2012
----1M Ph-II ASM ------1M Ph-II ---2M 1M Ph-I 1M Ph-II ASM -----------

AUG 2012
2M --------2M ----ASM Ex. M (B) ----1M Ph-II ----Dr. (Kol) ----Ex. M

SEPT 2012
--1M Ph-I --ASM Ex. M (C) --1M Ph-I ------2M ----ASM Fishing (Ch.) ---------

OCT 2012
2M --1M Ph-II ----2M --1M Ph-II ASM --2M 1M Ph-I ------NCV, Upgradn 2M (R) 1M (R) ---

NOV 2012
------ASM ------------2M --1M Ph-II ASM -----------

DEC 2012
2M 1M Ph-I ------2M 1M Ph-I --ASM Ex. M (C) --1M Ph-I ------------Ex. M

Course End

Exam

Note :1. 2M means 2nd Mate FG; 1M PH-I means 1st Mate (FG) Phase-I; 1M PH-II means 1st Mate (FG) Phase-II and ASM means Advanced Shipboard Management Examination of Master (FG). 2. Dr.(Kol) means Dredging Grade Examinations to be held at Kolkata. 3. Fishing (Ch.) means Fishing Grade Examinations to be held at Chennai. 4. Ex. M means Extra Master all grades 5. Ex. M(A) /Ex. M(B) / Ex. M.(C)-means Extra Master Part (A) / Part (B) / Part (C) respectively. 6. Duration of courses: - 2nd Mate (FG) Function: 4 months / 1st Mate Phase-I: - 3 months / 1st Mate Phase-II including STCW-2010 Upgradation: - 3 months / Advanced Shipboard Management (ASM): - 1.5 month. 7. Each course except course of Ex [M] and ASM shall commence on 15 th day of the month and will end on 14th day of the month after completion of the duration. ASM course shall commence on 1st day of the month and will end on 14/15th day of the month after completion of duration. 8. This Schedule does not include course / examinations for NCV grade and 2 nd Mate Foundation which shall be issued separately by LBS College. 9. NCV Upgradn. 2M (R) & 1M (R)means NCV, Upgradation 2nd Mate (FG) (Restricted), 1st Mate (FG)(Restricted) as per M.S. Notice No. 1 of 2006. 10. Scheduled Examination Results will be declared by 3rd week of the following month.

(Capt. S. I. Abul Kalam Azad) Nautical Surveyor-cumDy. Director General of Shipping [Tech]