DESCRIPTION
BILL NO
BILL DATE
CLAIMED
AMOUNT
VERIFIED
AMOUNT
R.A.BILL-01
21.03.12
101896.500
86274.400
15622.100
0.000
R.A.BILL-02
03.05.12
237949.00
233519
4430.000
0.000
R.A.BILL-04
03.05.12
143722.5
122164.125
0.000
21558.375
R.A.BILL-05
07.06.12
366785
366739
46.000
0.000
R.A.BILL-7
19.07.2012
233150.3
159114.8713
5843.041
68192.090
DEDUCTED
HOLD
REMARK
AMOUNT
AMOUNT
FABRICATION.ERECTION,DISMANTAL,SHEETING
R.A.BILL-10
09.04.2012
298759.874
265904.226
3308.86
29544.914
R.A.BILL-8(MS)
25.07.12
357296
238848.75
118447.25
0.000
R.A.BILL-09(MS)
07.09.12
216613
196243.425
20369.575
0.000
R.A.BILL-11
09.10.12
192218.67
190632.15
1586.520
0.000
10
FABRICATION.ERECTION,DISMANTLING,HANDRAI
LING
R.A.BILL-12
27/09/2012
794454.244
674752.784
406.080
119295.38
2942845.088
NET CLAIMED AMOUNT = RS
NET VERIFIED AMOUNT= RS
NET DEDUCTED AMOUNT = RS
NET HOLD AMOUNT = RS
2534192.731
170059.426 238590.759
2942845.088
2534192.731
170059.426
238590.759
TRUSST ENGINEERS