TERMINOLOGI TEKNIS
CAPACITY FACTOR = TOTAL GENERATION ( KWH )
INSTALLED CAPACITY (KW) X NUMBER OF HOURS

LOAD FACTOR

TOTAL GENERATION ( KWH ) PEAK LOAD ( KW ) X NUMBER OF HOURS INSTALLED CAPACITY PEAK LOAD PEAK LOAD

RESERVE MARGIN

ELECTRIFICATION RATIO

ELECTRIFIED HOUSE HOLDS TOTAL HOUSE HOLDS

KAPASITAS MAMPU LOSSES / RUGI-RUGI

= =

KAPASITAS TERPASANG X ( 1 DERATING RATE ) TOTAL NETT GENERATION TOTAL SALES

LOAD FACTOR
LF = TOTAL SALES ( KWH ) PEAK LOAD( KW ) X NUMBER OF HOURS

JAN LF = 438.000 80 MW X 8760 = 438.000 = 62,5 % 700.800

DES 33

10 in Asceding merit order

Installed Capacity

Power Plan Hydro Combine Cycle - Gas Fired - Oil Fired Steam - Gas Fired - Oil Fired - Coal Geothemal Gas Turbine Diesel Sub Total IPP Total

Outer Islands 624 876 310 590 20 646 2441 5,507 195 5,702

Java-Bali 2,391 3,268 2,717 1,000 800 4,200 360 1416 109 16,261 3,255 19,516

Total 3,015 4,144 2,717 1,000 1,110 4,790 380 2,062 2,550 21,768 3,450 25,218

% 11,96 16.43 10.77 3.97 4.40 18.99 1.51 8.18 10.11 86.32 13.68 100

Renewable Energy
Wind Power dapat digunakan untuk kondisi Peak load (TU/e holland 2010) PLTS digunakan untuk base load