SPECIFICATION DIV. :
19
SECTION:
3.4
GL13-15GL 11-15e A-C / BUILDING I / PRESSURE LEAK TESTING OF UNDERGROUND WATER SUPPLY PIPING IN ACCORDANCE TO METHOD STATEMENTREF# MS 27777-MS-06-00001 REV. 00 STATUS B, SHOPDRAWING REF# 2777-SD-06-00002 SHT. 001 & 002 REV. B CODE B & SECTION DETAIL REF# 2777-SD-03-00245 SHT. 001 REV. A CODE. A NOTE: TESTING SECTION OF PIPE = 22 mm dia. pipe = Approx. 30 LM, 28 mm dia. pipe = Approx. 6 LM, 35 mm dia. pipe = 18 LM RELATED IRF REF: 2777-RFIT-06-00022 REV. 00 Required Test Pressure: 1000kN/m2 (10 Bar) or twice the working pressure whichever is higher for minimum 12 hours. Actual: 10 Bar+
WE CONFIRM THAT THE WORK OF THIS HOLD POINT HAS BEEN COMPLETED AND WE HEREBY INVITE YOU TO INSPECT THE SAME ON 12 August 2012 @ 11:15 AM
ALAIN ZAILAH
REPLY:
APM INITIALS : DATE & TIME : RECEIVED BY CONTRACTOR : *Submit at least 24 hours before its commencement* DATE & TIME :
8/11/2012
F16 - RFHP