You are on page 1of 1

QATAR FOUNDATION EDUCATION CITY

REQUEST FOR HOLD POINT APPROVAL


BID PACK : CONTRACTOR : TO : QF OFFSITE WAREHOUSE AND DISTRIBUTION CENTRE CONSTRUCTION DEVELOPMENT COMPANY L.L.C M/s LOUIS BERGER SAS Hold Point No. : 2777-RFHPA-06-00008 Date: 11-Aug-12 Rev.: 0

CCS ACTIVITY No.: AREA / LOCATION / SUBJECT:

SPECIFICATION DIV. :

19

SECTION:

3.4

GL13-15GL 11-15e A-C / BUILDING I / PRESSURE LEAK TESTING OF UNDERGROUND WATER SUPPLY PIPING IN ACCORDANCE TO METHOD STATEMENTREF# MS 27777-MS-06-00001 REV. 00 STATUS B, SHOPDRAWING REF# 2777-SD-06-00002 SHT. 001 & 002 REV. B CODE B & SECTION DETAIL REF# 2777-SD-03-00245 SHT. 001 REV. A CODE. A NOTE: TESTING SECTION OF PIPE = 22 mm dia. pipe = Approx. 30 LM, 28 mm dia. pipe = Approx. 6 LM, 35 mm dia. pipe = 18 LM RELATED IRF REF: 2777-RFIT-06-00022 REV. 00 Required Test Pressure: 1000kN/m2 (10 Bar) or twice the working pressure whichever is higher for minimum 12 hours. Actual: 10 Bar+

WE CONFIRM THAT THE WORK OF THIS HOLD POINT HAS BEEN COMPLETED AND WE HEREBY INVITE YOU TO INSPECT THE SAME ON 12 August 2012 @ 11:15 AM

CONTRACTOR : RECEIVED BY QF:

ALAIN ZAILAH

DATE & TIME : DATE & TIME :

REPLY:

APM INITIALS : DATE & TIME : RECEIVED BY CONTRACTOR : *Submit at least 24 hours before its commencement* DATE & TIME :

8/11/2012

F16 - RFHP