Professional Documents
Culture Documents
Standard BoQ TEMPLATE Market Place
Standard BoQ TEMPLATE Market Place
LS M3
0.00
1.13
1.14
1.15 1.16
Mass concrete in 50 mm thick blinding layer (1:4:8 mix ) under the foundation wall. Rubble stone foundation wall in cement & sand mortar 1:4 ( 0.8 m x 0.4m wide) min. 15cm above ground level. R.C (1:2:4 mix) in ground beam (0.4m x0.15m ), with 4N0. Y12 re-bars & R6 links @ 300 mm c/c. 200 mm thick stone hardcore filling well compacted and leveled.
M3
0.00
M3
0.00
M3 M3
0.00 0.00
75mm thick murram or other approved backfill material, well compacted and 1.17 leveled. Total for Item 1.10
1.20 Bill of materials for Item 1.10 1.21 1.22 1.23 1.24 1.25
M3
0.00 0.00
(Substructure works) Ordinary portland Cement Bags River sand or other approved sand tonne Stone ballast (20mm size) tonne Foundation stone tonne Hardcore stone tonne
tonne Pcs Pcs Pcs Pcs Kg Kg Truck % %
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1.26 Murram or approved backfill material 1.27 1.28 1.29 1.30 1.31 1.32 1.33 1.34 1.35
Re-bar Y12 Re-bar R 6 White timber 12x1 White timber 2x1 Wire nails 3 Binding wire Water Total materials Transport cost Labour Costs Total transport & labour Total for I tem 1.20
20cm thick cement block walling laid in cement & sand mortar 1:4 mix ( rate to 2.13 include making of blocks)
M2
0.00
R.C (1:2:4 mix) in two level conc. ring beams (40 cm x15 cm ), each with 4N0. Y12 re-bars & R6 links @ 250 2.14 mm c/c. R.C (1:2:4 mix) in 20 cm x 20 cm column shaft, each with 4N0. Y12 re2.15 bars & R6 links @ 200 mm c/c. R.C (1:2:4 mix) in display tables (1m x 2.16 0.7m x 0.05m x 12 N0. ). Total for Item 2.10
M3
0.00
M3 M3
2.20 Bill of materials for Item 2.10 ( Superstructure works ) 2.21 Ordinary portland Cement 2.22 River sand or other approved sand 2.23 Stone ballast (20mm size) 2.24 Re-bar Y12 2.25 Re-bar R 6 Well cured Sand /cement hollow blocks 2.26 (size 40x20x20 cm) 2.27 Walling stones 2.28 Water 2.29 White timber 12x1 2.3 White timber 2x3 2.31 White timber 2x1 2.32 Wire nails 3 2.33 Binding wire Total materials 2.34 Transport cost 2.35 Labour Costs Total transport & labour Total for Item 2.20 % % bags tonne tonne Pcs Pcs Pcs tonne Truck Pcs Pcs Pcs Kg Kg 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00
LM
0.00
Pcs
0.00 0.00
Total for Item 3.10 3.20 3.21 3.22 3.23 3.24 3.25 Bill of materials for Item 3.10 ( Roof work ) White timber 3 x 2 Pcs White timber 2 x 2 Pcs White timber 6 x1 Pcs White timber 12x1 Pcs GCI Sheets ( N0.28 ) Pcs
3.26 Roofing nails 3.27 Wire nails (assorted) 3.28 75 mm diam. Class A steel pipes Total materials 3.29 Transport cost 3.30 Labour Costs Total transport & labour Total for Item 3.20 4.10 Plastering and other finishing External & internal plastering ,12 mm thick, cement / sand mix 1:5, with 4.11 wood float finish. Apply two coats white wash and distemper paint to the plastered wall 4.12 surface. 40 mm thick 1;3 cement/sand floor 4.13 screed. Total for Item 4.10
Kg Kg Pcs
% %
M2
0.00
M2 M2
4.20 Bill of materials for Item 4.10 ( Plastering & other finishes ) 4.21 Ordinary portland Cement bags 4.22 River sand or other approved sand tonne 4.24 Water Trucks 4.25 Lime 4.26 Emulsion paint 4.27 Gloss paint Total materials 4.29 Transport cost 4.30 Labour Costs Total transport & Labour Total for Item 4.20 5.10 Gates, Doors & Windows
Supply and fix wooden panel doors (2.0m x 0.9m) single leaf, complete with hinges & locks and to include two coats of gloss paint. Supply and fix metal gate ( 3m x 2.5m) complete with hinges and locks and to 5.12 include 2 coats of gloss paint. Supply and fix wooden panel windows (1.0m x 1.2m ) complete with wooden frame, hinges & locks and to include two 5.13 coats of gloss paint. % %
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Pcs
Metal
0.00
0.00
Pcs
0.00
0.00
Pcs
0.00 0.00
0.00
Total for Item 5.10 6.10 Provisional Items (includes materials & labour )
6.11 Water tank / Plumbing works 6.12 Standard latrine units as per BoQ 6.13 Electrical installation works LS LS LS 1 1
0.00
1
1
0.00 0.00
0.00 0.00
Total for Item 7.10 Grand Total (Bill of materials, provisional items & other inputs Grand Total (BoQ, provisional items & other inputs)
Note: 1) Ideally the two Grand Totals should be the same, but this is difficult to achieve as long as the estimation methods are not based on exactly the same assumptions and criteria.
2) The higher of the two totals should be considered for costing purposes. Percentage of community contribution #DIV/0!