M/S Elsytec Engineers reached site on 2-01-2014 for Pre commissioning testing of 63MW Power Plant along with the necessary testing equipments.
The pre commissioning testing of 63MW Power plant which included the relays at 132kv switchyard, 11kvswitch board, Transformers been carried out to M/s Inland power Ltd.
Also the stability test of 80MVA Transformer done,132/11KVswitchyard,Sikkidri switchyard & 11KV switchboard are back charged.
The defects noticed during testing were corrected & list of defective components were informed to M/S Inland power Ltd. In compliance to our request, Elsytec assured us to depute their engineers at our site at the time of charging of 132kv switchyard & Generator synchronization . M/S Elsytec representatives leaving site tonight i.e. Dt. 05-03-2014 .with testing equipments.